HomeMy WebLinkAboutDTS-10-073 - Noise Exemption - King St reconstruction - Young/College St to Francis St1
Kl~rc~~R
Qevelo pment &
Technical Services
Report To: Development and Technical Services Committee
Date of Meeting: April 12, 2010
Submitted By: John McBride, Director of Transportation Planning
Prepared By: Stephanie Brasseur, Traffic Project Co-ordinator (741-2373)
Ward(s) Involved: Ward 1-Bridgeport -Center
Ward 6 -West -Victoria Park
Date of Report: March 31, 2010
Report No.: DTS-10-073
Subject: KING STREET RECONSTRUCTION - YOUNGICOLLEGE
STREET TO FRANCIS STREET -NOISE EXEMPTION
RECOMMENDATION:
That the City of Kitchener Engineering Services and its contractor(s) be exempt from the
provisions of Chapter 450 Noise of the City of Kitchener Municipal Code Article 6
Construction Work during the King Street Reconstruction project in the City of Kitchener.
The request for the noise by-law exemption is for between the hours of 7:00 p.m. and
7:00 a.m. for the period April 5, 2010 to November 1, 2010.
BACKGROUND:
The 2010 stage for the reconstruction of King Street (Contract T08-015) between Young Street
and Francis Street will commence on or about April 5, 2010, weather permitting, and is
anticipated to be completed by the end of September, 2010. This project includes the following
planned work:
Municipal services -miscellaneous storm sewer and fire hydrant relocation
Underground utilities -underground electrical, gas and telecom services
Street lights and special event power
• Roadway surface, sidewalks and paving stones
Curb and gutter, and,
• Landscape construction.
REPORT:
In order to complete the work and minimize disruption for the King Street businesses and
complete the necessary improvements, extended hours and weekend work must take place to
complete the project within the established time allotment. This exemption is requested to
complete certain operations of work to mitigate the impact of construction.
8-1
The present work that is proposed to date for after hours work includes, but is not limited to:
Watermain servicing and hydrant relocation will be completed early in the project and will
entail work after hours when businesses are closed, during the approximate times of
2:00 a.m. to 6:00 a.m. Prior to commencement, this work will be communicated by letter
to all businesses and residents that will be directly affected. These times were chosen in
order to minimize the impact on adjacent businesses and their operations.
SCOPE /STAGING OF WORK:
There are several stages to the King Street Streetscape (see copy attached). The staging of
the work proposed for 2010 includes:
Stage 4a: Young Street to College StreetlGaukel Street including Young St intersection
Stage 4b: College Street to Water Street including the Water St intersection
Stage 5: Water Street to Francis Street
In general, the scope of this project includes the following planned work:
• Fire hydrant relocation (typically between 2:00 a.m. to 6:00 a.m.)
• Concrete sidewalk removal (typically between 4:00 a.m. to 7:00 a.m.) -this is specific to
business access purposes only.
• Paving stone installation (typically between 7:00 p.m. to 7:00 a.m.) and
• Potential paving operations.
TYPE OF NOISE:
The majority of the noise will be created by the removal of concrete and services along with
excavation of the sidewalk area in order to complete the work. During the road works, the use
of a milling machine and paving equipment will be used to resurface King Street. This work will
be undertaken during permitted working hours (7:00 a.m. to 7:00 p.m.). The road works will be
completed at the end of the project, once the sidewalks are complete. There may be extended
work hours implemented in order to accommodate an increased work schedule in each stage of
the work. Concrete pours will be scheduled beyond regular working hours where necessary to
address concerns for business access during business hours to entrances directly onto King
Street.
These additional hours of permitted work are requested to allow for the most impactful work
operations to be conducted during the hours of 7:00 a.m. to 7:00 p.m., allowing for less
impactful operations such as preparation work, forms preparation and removal and general site
clean up to be completed outside of these hours. This less impactful work will not commence
before 6:00 a.m. and is expected to go no later than 10:00 p.m.
Noise protocol will be followed, which covers administrative measures such as scheduling of
noisy activities at times of least impact, selection of haulage routes to minimize close proximity
to neighbours, and maintaining contact with residents.
Additionally, the City of Kitchener and their consultant have advised that any changes to the
work schedule proposed by the contractor will be addressed on its own merits and that any
additional noise impacts outside of the permitted hours will require further approval by the
project team and as such, detailed communication will be provided to residents and businesses
along King Street.
8-2
In order to expedite the construction and allow extended hours of work to take place for this
project, thereby minimizing traffic impacts, we recommend that this request for a noise by-law
exemption be granted. The extension of the working hours will accommodate intersection/
detour traffic and business needs.
DURATION:
Regular working hours will include and are permitted 7:00 a.m. to 7:00 p.m. Monday to
Saturday; however the Contractor is requesting to work extended hours when required to
complete work sensitive to traffic issues and to benefit the project timelines. Regular extended
hours will include 7:00 p.m. to 7:00 a.m. Monday to Saturday in order to reduce impacts of
business operations. Sunday work may occur between 8:00 a.m. to 5:00 p.m. and would be
limited to general clean up and preparation work where formal inspection would not be
necessary. Sunday work is a possibility for paving, but inspection would be required for this
operation.
All additional work will be assessed by City staff for allowing extended hours and will be defined
as a benefit to the project. Council will be notified at least a minimum of 48 hours in advance of
the work as the need arises.
FINANCIAL IMPLICATIONS:
None. Provisions have been included in the contract, encouraging the contractor to complete
this work as soon as reasonably possible.
COMMUNICATIONS:
The City of Kitchener and its contractor will communicate the expectation of extended working
hours to area residents I businesses and have been actively advising of any changes as they
develop. Communication updates will be provided on a regular basis.
CONCLUSION:
In order to expedite the construction and allow extended hours of work to take place for this
project, thereby minimizing-disruption and impacts of construction on businesses l residents, we
recommend that this request for a noise by-law exemption be granted.
ACKNOWLEDGED BY: Jeff Willmer, Interim General Manager
Development and Technical Services Department
8-3
8-4