Loading...
HomeMy WebLinkAboutCSD-10-031 - Consolidated Maintenance Facility - Status UpdateREPORT REPORT TO: Finance & Corporate Services Committee DATE OF MEETING: April 26, 2010 SUBMITTED BY: Pauline Houston, General Manager of Community Services PREPARED BY: Cynthia Fletcher, Director of Facilities Management (ext. 2424) WARD(S) INVOLVED: All DATE OF REPORT: April 21, 2010 REPORT NO.: CSD-10-031 SUBJECT: CONSOLIDATED MAINTENANCE FACILITY (CMF) PROJECT UPDATE - APRIL 2010 RECOMMENDATION: For information. BACKGROUND: On January 25, 2010, Council received staff report CSD-10-008 which provided a status update on the CMF project to that point in time. REPORT: This report provides a status update on the CMF project from January to April 2010. 1. Project Status Tasks Total Tasks Completed% Complete Project Initiation & Planning 30 30 100 Project Administration 102 29 43 Managing Change 93 43 50 Facility Development 72 49 60 Sub Trades Tenders 37 37 100 Construction 195 12 10 Business Continuity 127 5 4 Property Disposal 24 13 71 Wabanaki Drive 7 4 ïî ó ï Site & Building: Final architectural drawings have been completed and are available for viewing by Council and staff at a number of city facilities. The construction schedule is currently three weeks behind original projection. The project team is confident that the overall project timelines can be achieved as many construction activities will be scheduled to occur simultaneously on site. Demolition of the first floor office east side has been completed. Tender packages 1, 2 and 3 have been developed by Melloul-Blamey, with a total of 37 tenders. Tender packages 1 and 2 (23 tenders in total) have now closed and reviewed through an internal approval process including staff from Purchasing, Melloul-Blamey and the project team. In addition, a comprehensive budget analysis/management process has been set up to ensure that the overall project budget is aggressively controlled. A summary status report of the tenders has been included in Appendix A. People, Process and Service Integration: Work on Phase I of the service process reviews, including eight (8) groups looking at common function services and five (5) groups looking at divisional specific services, wrapped up at the end of January 2010. The recommendations from these groups are being reviewed internally to determine an implementation plan. Additional groups are being set up to review the remainder of the processes. Some examples of identified service improvements/efficiencies to date include: Indoor vehicle parking capabilities, protecting first-response vehicles from the weather, to allow them to warm up and get out on the road quicker to serve the public Larger fleet service bays that will accommodate vehicles that are hooked up to other equipment, such as snow plows; full disassembly will no longer be required, saving time Improved efficiency and use of vehicles and equipment; elimination of duplicated vehicles and equipment Streamlined process for vehicle fueling, washing and inspection will save time Records Management: development of a centralized file room and associated work processes which will reduce risk and improve MFIPPA (Freedom of Information legislation) compliance through easier access to information; in addition, through planning for the transition to the centralized space, over 150 boxes of inactive records have already been inventoried, reviewed and destroyed – this equates to 50 file drawers of equipment and cost avoidance through not purchasing equipment and built space or off-site records storage Waste Management: more efficient and environmentally friendly processes, reduction in the amounts of waste going to landfill, and identification of potential revenue streams for materials e.g. scrap metal, copper, wood Stores and Tool Cribs: Integrating multiple facilities into one will result in improved control and recording, consistent processes which run more smoothly, and improved access to tools and materials for staff who provide valued services to the community Relocation and Business Continuity: This project has been re-launched into 5 streams: Inventory of: Furniture (100%), Major Equipment (90%) Fleet & Equipment (10%), Records (phase 1 – 100%, phase 2 – 35 %) ïî ó î Purge/Disposal: committee in place; will begin working with records and furniture inventories Office/Parking Layout: interior vehicle layout and driving lane complete in draft format, exterior parking (10%), office layouts (70%) Relocation: draft re-location schedule to be reviewed by Relocation and Business Continuity group, Project Team and will be communicated to Steering Committee, manager/supervisor stake holder group and others Business Continuity: will tie in with re-location plan; contingency plans and communication plans will be developed MilestoneTarget Date StatusComments Demolition Phase I Starts Feb 19, 2010 Completed Demolition of 2 storey metal structure, concrete floor, walls in shops area Site Plan Approval Jan 15, 2010 Completed People Process & System Jan 29, 2010 Completed 8 Common Functions Service groups Integration (PPSI) to complete review and provide recommendations; five divisional groups, headed up by Directors, to complete review and provide recommendations. Building Permit Obtained Jan 29, 2010 Completed Permit ready; Architectural Drawings completed by December 31, 2009 and permit applied for first week of January, 2010 th Solar Roof Tender Award Feb 12, 2010 Completed Received OPA contract April 8; award th of tender the week of April 12; contracts with OPA and Kitchener- Wilmot Hydro being reviewed and finalized Construction Tenders Issued Feb/Mar, 2010 Completed Various tenders to be issued as per (Packages #1 & 2) Tender Schedule Sequencing; packages #1 and #2 have been issued Schedule: Future Major Milestones Through to Completion Date MilestoneTarget Date Completed Comments People Process & System June 30, 2010 PPSI group to validate and implement Integration (PPSI) recommendations, service process enhancements; required training for new service enhancements will be developed and/or implemented Re-location Schedule July 2010 Draft re-location schedule to be Finalizedfinalized then detailed divisional plans and communication plans can be finalized Re-format of the Beginning To work on the details of PPSI Manager/Supervisor April 20 and recommendations and the RBC Stakeholder Meetings futureschedules/plans meetings Strike the Work Place Culture April 2010 Committee will look at social Committeeopportunities leading up to and following re-location to the CMF ïî ó í Date MilestoneTarget Date Completed Comments Solar Roof Design May 2010 Detailed design of solar roof system underway; detailed production and installation schedule being developed and incorporated into overall construction schedule 2. Project Risk Assessment and Management This project has a strong focus on risk management. Since the original risk assessment prepared in July 2008 by KPMG where 45 active risks were identified, 40 of which were rated high in priority, a rigorous risk review process has been put in place, requiring regular monitoring and management of identified risks by both the project team and the Internal Auditor. It is not uncommon in projects with a broad scope such as the CMF project to have the number of active risks fluctuate a great deal throughout the life of the project as mitigation strategies are put in place and new risks identified. Currently, the project is tracking 26 active risks, of which 14 are rated high in priority. Key risks that will continue to require diligent and careful monitoring include project scope, budget and completion schedule. Risk Register Update Original Risk Assessment - July 3, 2008 Risk Rating Low 1-5 Medium 6-9 High 10 or Active Risks Calculated by 2 3 40 45 Impact x Likelihood Last Confirmed Risk Assessment Update - March 1, 2010 Risk Rating Low 1-5 Medium 6-9 High 10 or Active Risks Calculated by 3 12 9 24 Impact x Likelihood Current Risk Assessment Update - April 12, 2010 (for the month of March 2010) Risk Rating Low 1-5 Medium 6-9 High 10 or Active Risks Added 69,70,71 Closed 60 Modified 59,68 Updated Risk 2 10 14 26 Register 3. Budget On March 26, 2010, the City was advised that our application to the Federation of Canadian Municipalities Green Municipal Fund was approved, which includes a grant of $386,000 and a low interest rate loan of $3,869,000. This grant will be used towards funding the projected deficit of $1,265,000 per our September 2009 project update report, to $879,000. From a cost management viewpoint, project spending is strictly controlled and within the allocated budget. Council has approved project funding $48.2 million for the base budget plus $14 million for infrastructure funded enhancements and LEED components. To ensure ïî ó ì spending remains on track, the project’s cost management team reviews project finances on a regular basis. FINANCIAL IMPLICATIONS: None. COMMUNICATIONS: A full and detailed communications strategy for the consolidated maintenance facility (CMF) project is in place that targets all of the audiences and stakeholders who will be affected either directly or indirectly by the new facility, including city staff, city council, the general public and the residents of nearby Hidden Valley. The strategy also includes tools and methods for reaching all of these audiences with information as the project progresses, and especially at significant project milestones. CONCLUSION: The Consolidated Maintenance Facility project continues to be a high priority project for the organization, which will create the opportunity to deliver enhanced service for our residents. The original project budget commitment for the base project continues to be maintained while allowing adjustments to the project schedule and funding sources in order to accommodate the City’s contribution to the Infrastructure Stimulus program enhancements to the project. The funding shortfall identified in the original budget has been reduced and mitigation strategies as previously identified will continue throughout the life of the project. The next Project Status Report will be provided to Finance and Corporate Services Committee in August, 2010, based on a quarterly update schedule. This report is submitted on behalf of the CMF Project Steering Committee comprised of: Pauline Houston, General Manager of Community Services (Project sponsor and chair) Troy Speck, General Manager of Corporate Services Larry Gordon, Chief Purchasing Officer Wally Malcolm, Director of Utilities Don Miller, Director of Fleet Jim Witmer, Director of Operations Tracey Hare Connell, Executive Director of People Services and Organizational Development Michael May, Director of Corporate Communications and Marketing ACKNOWLEDGED BY: Pauline Houston, General Manager of Community Services ïî ó ë ïî ó ê ïî ó é