HomeMy WebLinkAboutCSD-10-044 - McLennan Park Phase 2 Tender Funding Information REPORT Report To:MayorCarl Zehr & Members of Council Date of Me eting:June 14, 2010 Submitted By: Pauline Houston, General Manager, Community Services Prepared By: Dan Ritz, Supervisor of Design & Development Ward(s) Involved: N/A Date of Report: June 7, 2010 Report No.: CSD-10-044 Subject: McLENNAN PARK PHASE 2 TENDER – FUNDING INFORMATION RECOMMENDATION: For additional information regarding the award of Tender T10-049 McLennan Park – Phase 2. BACKGROUND: Tender T10-049 closed on Thursday May 20, 2010 with construction proposed to begin in mid June subject to Council approval. The purpose of this report is to provide additional information, for Council’s consideration, regarding funding options so that the tender can be awarded and construction commence as quickly as possible in order to meet the March 31, 2011 deadline under the Infrastructure Stimulus Funding program. At Community Services Committee on June 7, 2010, Committee requested the following additional information further to the CSD-10-040 report with respect to the proposed funding sources for the award of Tender T10-049 McLennan Park – Phase 2: 1. Project detail with respect to each of the proposed additional capital funding sources (Major Park, Court Rehabilitation, Tree Planting & Community Trails). 2. Reduced project scope options for the McLennan Park Phase 2 Tender T10-049 and the associated future financial impact to implement at a later date. 3. Further information regarding the McLennan Park Phase 2 Tender work scope. 4. Clarification regarding the Kingsdale Community Centre budget at tender. ï ¨···÷ì REPORT: 1. Project Impact on Proposed Funding Source Each of the funding sources proposed exhibit a direct relationship to the type of work associated with the McLennan Park Phase 2 development (e.g. Community Trail funding - new trail construction within McLennan Park, etc.). Staff considered available budgets and project priorities with respect to each funding source in order to minimize impact to other departmental priorities as follows: Recommended Funding Sources: Uncommitted Funding Amount to be(prior to transfer): Capital Funding Item Transferred2010 Balance 2011 Budget A) Major Park Development 234,22843,138334,000 B) Court Rehabilitation 74,64774,64730,000 C) Tree Planting - Parks & Streets 72,40772,40751,000 D) Community Trails 175,000583,514 372,000 Total Capital to Capital Transfer $556,282 A) Major Park Revenue in 2010 from the Capital Budget process amounts to $334,890, with an opening balance of $29,406. Revenue proposed in 2011 from the Capital Budget process is projected to be $334,000. Major projects already accounted for or proposed in 2010 & 2011 include: i) Betzner Barn Foundation & Site Works – 2010 ($175,000) * *Split funding with Community Trails (see below) ii) Betzner Barn Design & Consultant Fees – 2010 ($29,000) iii) Sport Field & Facility Upgrades – 2010 ($50,000) iv) McLennan Splash Pad Recirculation System – 2010 ($110,000) PROPOSED v) – McLennan Park tender T10-049 ($234,228) vi) Sports Field & Facility Upgrades – 2011 –sites to be determined (100,000) ** ** Recommendation 4.1 from the draft 2010 Park Master Plan identifies that the city should continue to implement the recommendations of the Leisure Facilities Master Plan (2005) and examine priorities in 2010-2011 for associated sportfield upgrades. At this time staff have paused on sport field facility upgrades to review and re-prioritized the associated work. B) Court Rehabilitation Revenue in 2010 from the Capital Budget process amounts to $29,000, with an opening balance of $45,647. A balance of $74,647 remains in the account for 2010. No projects have been committed in 2010 pending the outcome of the Park Master Plan (June 2010). PROPOSED i) – McLennan Park Tender T10-049 ($74,647) C) Tree Planting – Parks & Streets Revenue in 2010 from the Capital Budget process amounts to $50,000, with an opening balance of $33,881. A balance of $72,407 remains in the account for 2010. Tree plantings typically occur across the city annually in various parks and street frontages. For 2010, staff recommend utilizing both the Environmental-Naturalization fund (2010 - $29,000) and the KW Hydro Corridor Planting fund (2010 -$35,000) to address associated tree planting projects. PROPOSED i) – McLennan Park Tender T10-049 ($72,407) ï ¨···÷ë D) Community Trails Revenue in 2010 from the Capital Budget process amounts to $549,000, with an opening balance of $63,616. Revenue proposed in 2011 from the Capital Budget process is projected to be $372,000. Major projects already accounted for or proposed in 2010 & 2011 include: i) Planning Staff Wages – 2010 ($49,000) *** ***Split funding with the General Parks ii) Community Trails Master Plan & Implementation Strategy – 2010/11 ($150,000) Betzner Barn Foundation & Site Works – 2010 ($170,000) * iii) *Split funding with Major Park (see above) iv) Doon Trails – 2010 ($75,000) v) Balzer Creek Trail – 2010 ($30,000) vi) Old Carriage Drive Trail – 2010 ($75,000) vii) Trail Restoration Projects – 2010 ($60,000) viii) Walter Bean Trail Bridge over Grand River -Consultant Fees – 2010 ($100,000) ix) Walter Bean Trail New Construction – 2010/11 ($300,000) **** ****Works to be invoice from Walter Bean Foundation (100% recoverable) x) Huron Natural Area – Strasburg Creek Trail & Boardwalk – 2010 ($175,000) ***** *****Potential private donation in the amount of $175,000 PROPOSED xi) – McLennan Park Tender T10-049 ($175,000) xii) Doon Trails – 2011 ($100,000) 2. McLennan Park Phase 2 Tender Reduced Project Scope Options Staff considered options to reduce the scope of the project in order to fit the current budget allocation. However, the magnitude of the reductions required (i.e. $556,282) would result in core components of the project being postponed, such as the washroom or skateboard park, which would be more costly to add at a later date as illustrated below. Savings if removed Consultant Estimate from Tender T10-049to construct separately Washroom Building $400,000 $475,000 Skate Park (bowl & street) $400,000 $525,000 3. McLennan Park Phase 2 Tender Current Work Scope The current tender for the phase 2 site works includes road and parking areas, associated lighting, Blackhorne Drive entrance works, signage, pedestrian trails, washroom/mechanical building, basketball/multi-use courts, beach volleyball courts, gazebo, skateboard park, great lawn area and site landscaping. (See attached McLennan Park "Development Plan 2010") This plan as well as additional drawings have been made available at earlier public information meetings and are available on the City of Kitchener web site (full colour download). 4. Kingsdale Community Centre Budget Staff were asked to provide a clarification as to the amount that the Kingsdale Community Centre was over budget at time of tender award. Due to an unexpected roof replacement and upgrading from LEED Silver to LEED Gold, additional funding in the amount of $458,000 was requested. ACKNOWLEDGED BY: Pauline Houston, General Manager of Community Services ï ¨···÷ê ï ¨···÷é