REPORT TO:
DATE OF MEETING:
SUBMITTED BY:
PREPARED BY:
WARD(S) INVOLVED:
DATE OF REPORT:
REPORT NO.:
SUBJECT:
RECOMMENDATION:
Special Council Meeting
August 5, 2010
Mark Hildebrand, Director Community Programs and Services
Cynthia Fletcher, Director Facilities Management
Mark Hildebrand, Director Community Programs and Services
All
July 28, 2010
CSD-10-052
Bridgeport Community Centre Renovation and Expansion
Project
That work on the Bridgeport Community Centre Renovation and Expansion Project be
stopped and the project, under its current scope, be cancelled; and,
That staff reduce the Bridgeport Community Centre project scope to include the internal
renovations and upgrades, as outlined in report CSD-10-052, keeping within the current
CC funding envelope allotted for the facility renovation and expansion after incurred
expenses, and pursuing RInC funding for the reduced scope project; and,
That staff address the future facility space needs of the Bridgeport Community as part of
the 2011-2020 capital budget forecast; and further,
That the Mayor make a request to the Minister of Energy and Infrastructure and Minister
of Health Promotion that consideration be given to reallocating the remaining Bridgeport
Community Centre RInC funding to the projects as outlined in report CSD-10-052.
BACKGROUND:
The Bridgeport Community Centre (BCC) is a 5,454 sq. ft. facility that has been in operation in
the City of Kitchener since 1970. In 2008 a business case was completed to determine the
short and long term needs of the community and whether the current facility could meet these
needs now and into the future.
Research and public input indicated that a gap existed between the type of facility that is
currently in place and the needs of the community. It was determined that, considering the
current space, a renovation and expansion to include a single gymnasium, an additional
medium sized meeting/activity room, additional storage, additional office space and an improved
lounge and lobby area were significant needs for the community.
Due to funding challenges, the renovations and expansion were proposed in two phases and
placed into the 10 year capital forecast. The first phase included a small expansion and
renovation while the second phase, further into the 10 year forecast when resources could be
allocated, included a larger gymnasium renovation and expansion.
The implementation of the RInC program by the Provincial/Federal governments provided an
opportunity for both phases of the project to be completed at the same time in 2010/2011. Staff
applied for, and was awarded, $1.4 million under the RInC program to complete the entire
renovation and expansion of the facility. The City of Kitchener's contribution to this project is
$850,000 ($557,830 C/C and $292,170 D/C).
REPORT:
Since the application of the project for RInC funding, staff has been working hard to overcome
several challenges, which have threatened the City's ability to complete the project, within the
deadline period, and on budget. Below is a summary of the challenges that staff have
experienced.
Project Initiation was delayed due to inconsistent information
Staff made the initial application for RInC funding in May 2009. In June 2009 there was a public
announcement made indicating that the City was successful in the RInC funding applications
submitted for the Sportsworld Arena Upgrade project and the Aquatic Facility Upgrade project.
Confusion resulted when in July 2009 a letter was received from the Federal Minister of Industry
and the Provincial Minister of Energy and Infrastructure indicating that the Sportsworld Arena
upgrade and the Bridgeport Community Centre Expansion were approved. Staff was unclear
about which project, the Bridgeport Community Centre, the Aquatic Facility Upgrades, or both,
were approved. Clarification of this inconsistency was not provided until August 2009 and as a
result the Project initiation was delayed by two months. Although staff had to compress the
project timelines by two months in order to meet the funding deadlines of March 2011, it was felt
that project completion was possible if there were no other significant delays.
Project Designation changed from existing development to new development
The 2008 Business case identified that the Bridgeport Community Centre was located in the
GRCA regulatory floodplain, and any expansion was subject to the policies contained in the
GRCA's "Policies for the Administration of the Development, Interference with Wetlands and
Alterations to Shorelines and Watercourses Regulation" (Ontario Regulation 150/06), as well as
the City of Kitchener's land use policies and regulations.
During the development of the business case, general discussions were held with GRCA staff
and City of Kitchener planning staff regarding the required facility renovation and maximum
expansion permitted at this site, to ensure that the project as understood at the time could be
completed. It was understood that an expansion would be in compliance with the Official Plan
and the Bridgeport East Secondary Plan if appropriate GRCA approvals were obtained. At the
time, the project was believed to be designated as "existing development below the regional
flood-line".
However when more detailed drawings of the renovation and expansion were submitted and
reviewed by City of Kitchener planning staff, it was determined that the scope of the project
warranted the designation of "new development" rather than "existing development". This
designation required staff to engage in extensive discussions in order to receive GRCA and
planning approvals as well as approval from Committee of Adjustment to move the project
forward. Additional discussions with GRCA resulted in a delay of approximately one month to
the project. To compensate for the delay, staff reviewed and adjusted the project timelines to
ensure that we would be able to start facility construction on schedule.
In addition to the necessary approvals, the designation of new development brought a number
of planning and engineering requirements, which have significant budget impacts. Within the
property line, new storm-water management requirements (e.g. re-grading the site, installation
of catch basins etc.) are expected to impact the budget by approximately $300,000. In addition
to this, there is now a requirement to add services to the road right of way (e.g. storm sewers, a
new hydrant, water main connection) at an estimated cost of $370,000. The total budget impact
of the new requirements is estimated to be $670,000.
Tender Closure Over-expenditure
The project currently has a construction budget of $1.65 million before taxes. On July 22nd 2010
at tender closure, staff received four bids. Unfortunately the lowest bid was $2.06 million
resulting in a $410,000 over-expenditure in the construction budget. Considering the existing
impact of the engineering and planning requirements of $670,000, the total project over-
expenditure is currently $1.08 million.
While staff has managed to accommodate for the majority of the challenges to date and, up until
the tender closure date, have been able to keep the project on schedule, it has been concluded
that the accumulated over-expenditure is too significant to resolve within the existing tight
timelines, and therefore the cancellation of the project, at its current scope, is being
recommended. As of Monday July 26th, 2010, all aspects of the project have been placed on
hold. It is important to note that this further delay directly affects the work that can be completed
on site. As a result, it will not be possible to complete construction by the March 31, 2011
deadline.
In light of this recommendation, staff is proposing a reduced scope of work to the Bridgeport
Community Centre facility to address some immediate community and facility needs. A request
has been made to the Federal and Provincial governments to help fund the reduced scope of
work through RInC. Staff have put together two renovation plans; one that reflects RInC funding
as well as a second which considers renovations if we only have access to the C/C envelope of
$330,000 (C/C envelope net of costs incurred during the project including encumbrances). The
following internal renovations and upgrades are being proposed under the reduced scope:
1. If RInC funding is granted
Proposed Renovations
Estimated Costs
Building Exterior
Surrounding Property
Building Interior (paint, flooring etc.)
Entrance and Hallway
Office Area
Washrooms
Meeting Room/Storage Rooms
Main Multipurpose Room
Kitchen/Bar Areas
Utility Rooms/HVAC
General Contractor Overhead,
Contingencies, Consulting fees
Estimated Cost reduced scope:
Expenses Incurred to date
Including Encumbrances:
Total Costs:
$ 755,250
$ 223,870
$ 979,120
$69,000
$70,000
$153,000
$12,500
$20,500
$6,000
$19,000
$52,000
$90,500
$11,000
$251,750
Proposed Split:
$ 652,750 - RinC funding; $ 326,370 -City of
Kitchener
RInC Approval Required by: Mid August, 2010
If RInC funding is approved for the reduced scope of work for Bridgeport Community
Centre, the remaining balance in the C/C envelop will be approximately $230,000 after
the City of Kitchener's contribution of 1/3 to the project.
2. If RInC funding is not granted
Proposed Renovations
Estimated Costs
Building Exterior $69,000
Surrounding Property $7,000
Building Interior (paint, flooring
etc.) $88,000
Entrance and Hallway $4,500
Office Area $5,000
Kitchen/Bar Areas $40,000
General Contractor Overhead,
Contingencies, Consulting fees $106,750
Estimated Cost: $320,250
Proposed Funding: $320,250 would be funded out of the current project budget
C/C envelope net of costs incurred from the project,
including encumbrances ($330,000).
Approval Required by: RInC funding approval is not required.
Long term community space needs
To address the long term space needs of the Bridgeport Community, staff will review the
existing business case, consider all new information regarding the existing site of the Bridgeport
Community Centre, and refer any long term facility needs to the 2011 - 2020 capital budget
forecast.
Transferring RInC funds to other projects
Staff has contacted Provincial and Federal Government representatives to discuss the
possibility of transferring the remaining RInC funding from the Bridgeport project to other eligible
projects within the City. The City of Kitchener has been informed that the RInC funding
agreement does not permit a transfer of funds from one project to another, nor is there currently
any policy in place at the Federal/Provincial level to allow for this. Therefore staff is
recommending that the Mayor contact the appropriate Federal and Provincial Ministers and ask
them to consider reallocating the funds to other projects. The possible projects that could be
considered include:
1. Woodside Park Renovation
Project Description: The re-development of Woodside Park to a high quality
sport complex consisting of two artificial turf fields.
Work would include removal of the existing ball
diamond, new field installation, parking lot upgrades
and site furnishings/ stands.
Estimated cost: $1.2 Million;
2
3
Proposed split: $747,000 - RInC funding; $80,000 -Kitchener Youth
Soccer Club; $373,000 -City of Kitchener
Proposed funding: Staff are proposing to fund the City of Kitchener's
portion of this project ($373,000) from the Park's
Dedication Fund, to be repaid over the payback period
from additional revenues realized.
RInC approval required by: End of August, 2010
Breithaupt Centre Pool
Project Description: Original RInC application was approved to address
pool piping replacement, concrete repairs and
waterproofing to deal with micro cracks found in the
pool tank. Investigation found that there was extensive
damage to the concrete sections of the pool tank at the
point where the pool tank walls meet the floor. The
concrete in some of these sections have fallen away to
the point that the rebar supports are exposed. This
application will address costs associated with fixing
these additional tank structural issues that are outside
the scope of the original project.
Estimated cost: $150,000;
Proposed split: $100,000 - RInC funding; $50,000 -City of Kitchener
Proposed funding: Staff is proposing to fund the City of Kitchener's portion
of this project ($50,000) from the remaining funds in
the C/C envelope of the Bridgeport Community Centre
Project.
RInC approval required by: By Mid November, 2010
Sportsworld Arena Upgrades
Project Description: Address an over expenditure associated with the
building upgrades to the Sportsworld Arena Complex.
Tenders came in higher than estimated costs for this
project. Upgrades include improvements to the
operating equipment and systems including HVAC,
electrical, lighting and building control systems;
rehabilitation of rubber flooring in change rooms,
hallways, official's rooms and first-aid rooms; and
addition of snow melting equipment.
Estimated cost: $150,000;
Proposed split: $100,000 - RInC funding; $50,000 -City of Kitchener
Proposed funding: Staff is proposing to fund the City of Kitchener's portion
of this project ($50,000) from the remaining funds in
the C/C envelope of the Bridgeport Community Centre
Project.
RInC approval required by: By end of August, 2010.
It should be noted that, due to the lack of policy to deal with transferring grant dollars from one
project to another, it may be difficult to get the necessary approvals in time to move forward on
the above proposed projects and meet the RInC program deadline in March 2011.
Bridgeport Community Association Consultation
Recognizing that the Bridgeport Community Association is a significant partner in this project,
and is represented on the project team, staff met with them prior to the special meeting of
council, to provide details about the recommendation, discuss the business case and future
planning, and provide them with the opportunity to attend this meeting. Further meetings will be
scheduled with the Community Association upon further direction.
FINANCIAL IMPLICATIONS:
The following is a Project Year to Date Budget with encumbrances as at August 4, 2010.
Total
Revenues YTD Actual Budget Variance Encumbrances
Contribution from Capital (557,830) (544,000) (13,830)
Contribution from Development
Charges (292,170) (306,000) 13,830
Contribution from Province (25,000) (700,000) 675,000
Contribution from Federal (25,000) (700,000) 675,000
Total Revenues (900,000) (2,250,000) 1,350,000
Expenses
Construction Expenses 187,850 2,250,000 (2,062,150) 36,020
Total Project (Surplus) Deficit (712,150) 0 (712,150)
If staff receive direction to reduce the scope of the Bridgeport project and implement internal
renovations and upgrades, the maximum amount the City of Kitchener will be able to contribute
from the project budget will be approximately $330,000 (C/C envelope net of costs incurred
including encumbrances).
ACKNOWLEDGED BY: Pauline Houston, General Manager, Community Services