HomeMy WebLinkAboutINS-11-051 - City of Kitchener 2010 Wastewater Capacity Study1
Staff Re ort
p
Krr~.~-~~,i~iER ~nfrastru~ture Servrces Department www.kitthenerta
REPORT TO: Community and Infrastructure Services Committee
DATE OF MEETING: May 30, 2011
SUBMITTED BY: Grant Murphy, Director, Engineering Services - 2410 ~
PREPARED BY: Greg McTaggart, Manager, Infrastructure Asset Planning -
2634
WARD(S) INVOLVED: All
DATE OF REPORT: May 19, 2011
REPORT NO.: INS-11- 051
SUBJECT: CITY OF KITCHENER 2010 WASTEWATER CAPACITY
STUDY
RECOMMENDATION:
That the final report regarding the findings of the City-wide Sanitary Sewer System Capacity
Study conducted by AECOM Canada Ltd. consultants be accepted, and that recommendations
for sanitary sewer system upgrades contained within the report be taken into consideration by
staff in the capital budget's 10-year forecast.
EXECUTIVE SUMMARY:
In November of 2009 the City of Kitchener retained AECOM Canada Ltd. to perform a City Wide
Sanitary Sewer System Capacity Study. The purpose of the study was to:
• Evaluate available capacity and performance of the City's existing sanitary sewer network,
both currently and the system's ability to accommodate future growth scenarios
• Identify potential constraints in the system, both currently and under future growth scenarios
and identify remediation strategies
• Facilitate best practice in infrastructure asset management now and in the future by
enhancing growth planning of the sanitary sewer system
• Provide the City with a hydraulic computer model of the sanitary drainage system that can be
operated by staff on an ongoing basis
Project work was substantially completed in October of 2010, with the primary products of the
study being a 730 page report of the findings and recommendations for improvements to the
sewer network relating to system capacity, and a computer dynamic hydraulic model of the
City's entire sanitary sewer network.
The hydraulic model will be used as a comprehensive tool to evaluate sanitary sewer network
system performance. It will also enable staff to evaluate the impact of development proposals
and potential future zoning changes on the sanitary sewer network. This ability will become
increasingly important into the future, as the Provincial "Places To Grow" Growth Plan stipulates
that a significant portion of future development in Kitchener must take place with the current
is - i
1
Staff Re ort
p
Krr~.~-~~,i~iER ~nfrastru~ture Servrces Department www.kitthenerta
urbanized area of the municipality. The City has prepared a Growth Management Strategy to
further identify specific intensification areas for potential development under the current zoning.
One of the applications of this Capacity Study is to support the implementation of the Kitchener
Growth Management Strategy and the creation of the City's new Official Plan.
BACKGROUND:
In past years, the City of Kitchener has undertaken various studies of portions of its sanitary
sewer system in order to better understand functional capacity and overall performance within
specific areas of the system. Following on from this, the City retained AECOM consultants in
November 2009 to create a computer hydraulic model of the City's sanitary sewer network and
then use it to perform acity-wide sanitary sewer system capacity study. The City's sanitary
sewage collection system includes approximately 735km of sewer mains and 24 sewage
pumping stations all discharging to a single treatment plant operated by The Region of
Waterloo. The City's system also has multiple connections to neighbouring municipalities
including townships of Wilmot and Woolwich, and the cities of Waterloo and Cambridge.
The computer model uses InfoSWMM, a software application, and the City's GIS data to
simulate the operation of the entire sanitary sewer network under a wide range of conditions. A
primary output from this model is how much sewage the system is conveying at any given
location in the network, and how much additional capacity the system has to accommodate
additional sewage volumes. The model was then used as a tool to perform a study on a city-
wide scale of the City's sanitary sewer system capacity currently and what capacities may be
required of the system by sewage volumes generated by future urban growth. This will facilitate
best practices in infrastructure asset management now and into the future by facilitating planned
and budgeted sanitary sewer system upgrades that will address capacity requirements. Specific
objectives of the study were as follows:
• Conduct a detailed background data collection and review
• Develop and calibrate a hydraulic model of the existing sanitary sewer system
• Undertake an extensive flow monitoring program and data analysis intended to measure
actual system performance and calibrate the computer model
• Assess the capacity of the existing sanitary collection system
• Identify the system constraints under defined future growth scenarios
• Develop and evaluate mitigative measures to address existing issues and service new
growth.
REPORT:
Four operating scenarios were studied for the City's sanitary sewer network: current sanitary
sewer system capacity and performance, theoretical future flows based on percentages of the
potential capacity to accommodate population densities under current zoning identified in the
Kitchener Growth Management Strategy (50%, and 100%), and lastly flows generated by a
theoretical full build out to current zoning capacity (a city population of 511,000}. With each
scenario, the calibrated hydraulic model was used with a 25yr, 12hr AES design storm to
evaluate available capacity within the existing sanitary sewer system in a "worst case" scenario.
As part of the Background Study to the Kitchener Growth Management Strategy, the City
estimated how much population and employment growth could be accommodated under current
2
1$-2
1
Staff Re ort
p
Krr~.~-~~,i~iER ~nfrastru~ture Servrces Department www.kitthenerta
zoning conditions. Several assumptions were used to prepare scenarios that calculated the
potential increase in new dwelling units, persons, non-residential floor space, jobs and density
primarily located within Intensification Areas while maintaining existing, stable neighbourhoods.
The scenarios investigated the capacity to accommodate growth up to 50% of the maximum
density that the zoning permitted within those areas and up to 100% of that maximum.
The City provided a copy of these background estimates to AECOM to utilize in running sample
"what if" modeling scenarios to the current flow/capacity of the sanitary sewer system. The
expectation is that the sanitary sewage network should reasonably be able to accommodate
growth in certain areas of the city under the current zoning.
Pipe Nefwork:
The study has identified 156 conduits (pipes) with genuine capacity concerns in the existing
sewer system, 209 for the 50% KGMS growth scenario, and 237 for a build out up to the 100%
KGMS growth scenario were taken forward for further consideration. Although this may seem a
significant figure, for comparison there are over 11,500 pipe segments that comprise the City's
sanitary sewer network as a whole. These identified conduits can be grouped into 18 specific
problem areas. Using the calibrated hydraulic model, mitigation measures to alleviate these
concerns and provide additional capacity up to the 100% scenario were identified, costed and
prioritised for implementation depending on the extent of surcharge and timeframe when these
capacity constraints are first exhibited. Figure 1 below illustrates locations and extents of
capacity concerns requiring mitigation identified for the current, 50% KGMS, and 100% KGMS
build out. Appendix "A" lists the locations in greater detail along with cost estimates.
Figure 1: Illustrating the locations and extents of sanitary sewer network capacity concerns and the timing
of when these locations are expected to become of concern, in terms of the current (existing) situation,
50% KGMS build out, and 100% KGMS build out.
18-3
1
Staff Re ort
p
Krr~.~-~~,i~iER ~nfrastru~ture Servrces Department www.kitthenerta
The last scenario modeled was a full build out to current zoning. Should the City allow
development up to the current zoning capacity, large areas of the existing local and trunk sewer
system will have insufficient capacity to accommodate these theoretical flows. It must be noted
that this would not occur for a very significant period of time, if at all. The consultant has
however noted as well that the City's existing design specifications for sewage quantities
generated per person is very conservative, and revisiting those specifications may well show
additional capacity in the system in general not currently permitted for use. This is an activity
planned as a follow-up to the study.
Sewage Pumping Stations:
From the analysis it was determined that four of the City's sanitary sewage pumping stations
have capacity concerns regarding their ability to accommodate existing sanitary flows. These
facilities are: Homer Watson, King St East, Old Mill, and Bleams Road. The Homer Watson
facility is being upgraded this year. The King Street (Freeport) facility is slated for replacement
in several years from now, and is part of the current 10-year capital forecast with design
anticipated to commence later this year. Further monitoring of the Old Mill facility will occur as a
follow-up activity to the study to better characterize the situation at that facility, and is identified
in the 10-year Capital forecast for improvements. The Bleams Road facility is a temporary one
and will be decommissioned when the Middle Strasburg trunk sanitary sewer is constructed
upstream to that point.
Regarding the future growth scenarios, one facility is analyzed to be able to accommodate up to
the 50% KGMS growth scenario but no more, six facilities to the 100% KGMS growth scenario,
and nine facilities are expected to accommodate up to the full build out to current zoning
scenario. The one facility (Patricia Ave) that can only accommodate up to the 50% KGMS
growth scenario will require upgrades at some point to support such that level of growth,
however the facility is relatively small and work that is not expected to occur in the near to mid-
termfuture.
ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN:
This study has supported community priorities of:
1) Planned and sustainable development by ensuring the efficient and proactive provision of key
services necessary for future development.
2) Environmental stewardship by ensuring that the City's wastewater system continues to
operate in a safe and environmentally responsible manner.
The study also supports the corporate foundation of efficient and effective government by
providing an increased understanding of and ability to proactively plan and budget for a major
class of critical City infrastructure assets.
FINANCIAL IMPLICATIONS:
There are no immediate new financial implications for the City as a result of this study over and
above what is currently allocated in the 10-year capital forecast for sanitary sewer infrastructure.
There are however 18 locations in the sewer network that were identified in the study requiring
mitigation measures to address system capacity concerns. A class "C" cost estimate for all
identified works was developed by the project consultant, with a total estimated cost of all works
a
18-4
1
Staff Re ort
p
Krr~.~-~~,i~iER ~nfrastru~ture Servrces Department www.kitthenerta
being $12.75 million. Much of this work is anticipated to occur over a span of time as the city
grows though (perhaps 20 years, dependent on the rate of future urban growth), and includes
the King Street East pumping station and catchment area which is currently in the 10-year
Capital forecast and budgeted for. The value of newly identified work recommended for the near
to mid-term commencement is estimated at $5.5 million. This work would be included into the
ten-year capital forecast within the current forecasted funding envelope over the breadth of the
forecast through reprioritizing proposed work.
Other works identified to support the 50% up
when growth in the city approached those
estimated to occur 20+ years from now.
to 100% KGMS growth scenarios would occur
thresholds. These levels of development are
See appendix "A" for a description of identified work and cost estimates.
COMMUNITY ENGAGEMENT:
This study being a strictly technical exercise, members of the public were not involved in this
study. However all direct stakeholders within the corporation were actively involved in this
project, including staff from INS-Engineering, INS-Operations, Community Services-Planning,
and Finance and Corporate Services-Information Technology. Staff from all divisions listed
provided input and participation in the project as direct participants andlor subject matter
experts.
CONCLUSION:
Analysis of the results showed that in general the existing sanitary sewer system has sufficient
capacity to accommodate flows up to the 100% KGMS anticipated growth scenario. 18 specific
locations were identified where existing or future flows exceed current available capacity and
the hydraulic model was used to evaluate proposed upgrades. These upgrades are proposed to
be included into the 10-year capital forecast and in out-years beyond that, with timing based on
demand from current and future population levels. Additional analysis should be performed as
further growth and servicing information is known.
The InfoSWMM hydraulic model created during this study is a living document which will be
used by staff to assess the impact of future development and to evaluate sanitary sewer system
upgrades. The model provides a accurate representation of the system as it existed when the
model was built. In order to remain a useful planning tool into the future it is imperative that the
model is updated regularly. Plans to do so are currently underway, or will be put into place later
this year.
ACKNOWLEDGED BY: Pauline Houston, Deputy CAO
Infrastructure Services Department
J
18-5
1
KITCx~i~~R
Staff Report
~nfrastrurture Services Department
~w.k~~~~~r~erca
,~
~ ~,
s ~
~S ~
°~
~ ~
~+ ~1
~' ~
~~
~~
~~ ~
w
~ ~ ~L
~~ ~
'~
~~
. ~ ~ ~ ~. ~
. ~
~aa,.
Y ~
~
~ ~~1
w L
~ ~ ~~i
Lk ~~g
"+
~ ~
~ ~
I ~
~
N ~
~
C ~ ~'
~ Vh
O
~
~+
'~
.+C_+
~
'-
~
~ ~
~
~
~
~ "a`n ~
t1 "~
~
~
~ ~
+~
~ - ~''
~ f1J
'
~ C
~
~ QJ
~
~ d7
f0
y
~
O
++
C ~
~
~
~ ~ `'
'C
~
~
f'+"1
+-' ~ Z
3
rl~ ~ 41
~ 4J
~ ~ N
O 4~i ~ 41 7 ~ ~ ~' '~ ~ ~
~ 4;7
~ u7 ;}..
~ ~ '~ G A
~ ~
~ ~
~
~; ~ ~
~ ~ r~
~ r
~ ~ a
~ m ~
a ~
~
o
~ r ~.
~ ~ ~ 41~
~ ~,
~ ~ ~
~ ~
~
.~ a, w ~' ~ ~ ~ o ~ ~ ~ ~ ~ ~ ~' a, ~ su °~.,
Lf Y 3 ~l C7 417 Q7 'C 1!7 C] O ~ ~ ~ ~ `~ d1 P`i' ~ ~ ~ ~ ~ 41
ao a~a ~ ro as c ~ ~ na as au ~ ~ ~ ~ a c o "~ ~ c ~ ~
U ~
~ w ~
~ ~ ~^
~] G ~
~ ' ~
~ ~ ~
~ n
4F ~
~ ~ n
~ ~ ~
+~ d] p ~ ~ ~_'
~ ~ ~
~ ~ 2
~ C~ 2
Q r~
Q
~ 3U
~ 91
~
~
~
~
~
~ '
~
O ~
~ 41J
an '~ 1~
"~ H
~
~ ~ ri
~
`~ '?Q
w
-I G
~h ~
~ ~ `~ ~ ~
u ~ Ci
~n '~
'~ ~
~ ~
t'~1 ~ fv
i ~; ~+
d7 Q
U
Y1 0 ~ ~ ~y ~ '~'
~4 ~ ~3
c0 Lea
iU
M
.~
~ 4
~J
IV
.~
I;L ~
{~
iy
.~ ~
ore
4ry dl
~ Q
~' ~7
1V
~'~
[1 q7
~
nID ~,
'C7 ~ tQ
~ ~
Ll~1 7
,~
~ I
41!
N
~
~ tU ~
N ~
~`~
41 47 r
~U
N
~'~
d ~ R1
~ p4
C `
IC 4
OJ
N
'^
Cl VY ~ 'Rk
en ~
~ L~? Gi
~
~, ~} ~
~
CU ,~ fll
'!
~
O ~ ++
~ ~
O '
= +l!
N
~~
fl
C~1 ~ ~ ~,
~ ~ .~ ~ ~
CC ~
J 4xY ~ ~ ~ 7] ~ ~
~ ~ ~ ~
W iL t~S rp
~ W #~+ s
~ ~ ~
t~
C
~ ~
~
.~ ~
~
~ 40
~
.~ ti0
~
°~ 411
C
~ GO
~
~
~ 411
4'
~ 40
~
°~ #~
~
~ 4d
4-
in
'~
w
a~
w
'~
w
'74
w
'7~
w
`~t
w ~
~
'~
w
~
'~
w
'~
uu ~
~ Q
~
'~
'~
'ac
w
w a
~--~
C
~
~
~
~ ~y
~/}
~
4
~
~
Ud
4fl C7
~
4U
4b 4]
~
4i
t ~,
~
~ L
Q)
[~.J
,~T~J
M1..l ~
~q ~,
IfJ
~
~
~' ~
.
~ ~ ~
4~ +~
~Q1
~
~
~
1r
J LJ~ ~ ~ ~ J [1
~ [~ ~ CI J fLG
~
~
J
4U
~
~
~
~ +,
~
~
~
C
~
~
~
~
~
~ [L
~
r {q
~ ~
~
C ~
~ }
~ ~
~
~ ~
~ q7 ~
~
~ 4J
is
~ u
n
e ~
~
'
o-~
~ ~
a 4U
~
c
c ~
40
~ ~
se ti
H
+~ ~ ~ ~ ~ ~ df ~ ~ ~ ~ o c u
~ ~ ~ •~ ~ ~~y ~ ~ ~ a~ ~ ~
U I ~
~ ql
.5G C7
i7 V1
~ 4C ~
~ '4~ ~]
~ ~ ~
~ ~ ~
I>3 ~
R# ~
..~ d1 ~ ~
~ ~,F tll
~ "~
~
~
~ '~''
~ ~
~ C
~ ~
~ ~7
~ ~
~ ~ ~
~ 10 [
~ ~
U ~
~~
~ C
'~ ~
CI ~
~ ~ ~
~y Q 9J Q1
ii ~ n CJ c-1 2 2 4~ C1 ~ u
i ~ ~ C] C3 w 41
si a'V tY! ~ ~ ~ lD f+ GO tat ~ ~ ~ ~ e~~i ~ e~i ~
Appendix "A": Identified locations for mitigation measures, timing, and estimated cost.
G
18-6