Loading...
HomeMy WebLinkAboutFCS-11-153 - Stimulus Project Update - Aug 2011REPORT TO:Finance and Corporate Services Committee DATE OF MEETING: Aug 15, 2011 SUBMITTED BY: Dan Chapman, Deputy CAO & City Treasurer PREPARED BY: Jaya Chatterjee, Junior Financial Analyst, Financial Planning WARD(S) INVOLVED: All DATE OF REPORT: Aug 10, 2011 REPORT NO.: FCS-11-153 SUBJECT: STIMULUS PROJECT UPDATE – AUG 2011 RECOMMENDATION: For information. BACKGROUND: This report is part of a series of bi-monthly updates to the Finance and Corporate Services Committee on the status of the City’s infrastructure stimulus projects. This reflects a commitment to ensure that infrastructure funds are spent in an open, transparent, and accountable manner and that Council is afforded an opportunity to track the progress of these projects on a regular basis. REPORT: Section 1 – Project Status Update Appendix “A” provides a summary of project status and Appendix “B” depicts the progress towards completion of each project compared to the planned timeline. The City had 16 Stimulus fund projects; eight projects were completed by the March 31, 2011 deadline. Eight projects received an extension; two of them have been substantially completed, and the remaining six projects are on track to be complete by the deadline of October 31, 2011. A status update follows for the Stimulus fund projects specifically still in progress: Storm Water Infrastructure Rehabilitation: Remaining ISF funds to be utilized for addressing drainage issues at various locations. All works to be completed prior to the end of October 2011. Sewer and Watermain Rehabilitation: The City has received approval for a scope extension, which will allow the unutilized contingency to be expended on the project for Sanitary Lining trenchless program on various streets. Consolidated Maintenance Facility: The dewatering area is under construction and is anticipated to be completed by mid October 2011. ë ó ï Solar Roof on the Consolidated Maintenance Facility: The remaining balance in the solar roof project of $92,500 ($61,666 of which is funded from the Province and the Federal Government) will be utilized to complete the replacement of the roofing membrane on the facility. All membrane beneath the solar panels has been replaced, and it was anticipated that the balance of the membrane would be replaced in the short to medium-term with funds from future capital budget roofing provisions. As a result of the extension of the project and the funds remaining in the project, it is beneficial to complete the work prior to the October 31 deadline. This will allow the City to take full advantage of the Provincial and Federal grants. The total cost is anticipated to be $275,000 net of the HST rebate, which will be funded from the solar roof project with the balance to be drawn from the roofing allocation in the 2012 capital budget (currently $474,000). Bridgeport Community Centre Project: The City has received the long-awaited approval for a scope extension from the Federal and Provincial governments to fund the addition of the meeting room. Harry Class Project: Construction near completion; with one set of lockers and few lighting installation pending. Project is expected to be substantially complete by the end of August 2011. The City has been regularly submitting monthly claims for ISF projects, RInC projects and the CAF King Street reconstruction project since December 2009. Section 2 – Expedited Purchasing Measures Council has previously approved a number of purchasing measures to expedite projects receiving funds under the Infrastructure Stimulus Program, while still maintaining a fair, open, and transparent procurement process. The measures, along with comments on their utilization, are outlined in Appendix “C”. Section 3 – Federal/Provincial Program Updates There are no new program updates at this time. ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN: Foundation: Efficient and Effective Government Goal: Financial Management Strategic Direction: Invest and manage assets strategically FINANCIAL IMPLICATIONS: N/A COMMUNITY ENGAGEMENT: To assist in ensuring the infrastructure stimulus funds are spent in an open, transparent and accountable manner, staff continues to implement the communications strategy that has been developed to assist in tracking the progress of all projects. The strategy contains various ë ó î communications tools that will give residents an opportunity to follow the work that is underway on each project. Federal and provincial signage has been installed at all project sites, recognizing federal and provincial funding support; only federal signage was required to be installed for the King Street reconstruction project, as it is supported by the federal Canada Adjustment Fund; Project-specific web pages, featuring an interactive map showing all project sites, is updated on a bi-monthly basis to ensure a user-friendly way for citizens to access information on each project. The web pages include background on each project, as well as status updates as they are provided by the project managers; Media releases and/or media events are planned for the completion of each project. Advance promotion of the media events will include invitations, posters, advertising, social media, and media advisories (dependant on project budgets). The following three completion events have taken place to date: Sportsworld Arena building improvements project, funded through the RInC program. The event was held on Sunday, March 27, at the arena, featuring a free public skate, cake-cutting and ribbon-cutting ceremony. Improvements to four aquatics facilities, funded through the RInC program. The celebration took place on Saturday, June 18, at Harry Class Pool, featuring ribbon- cutting, swim group demonstrations, a charity barbecue, and a free public swim. Unveiling of city's solar roof - the largest solar roof installation in the country, funded through the Infrastructure Stimulus Fund (ISF). The event took place on Wednesday, June 29, at the Kitchener Operations Facility, featuring a "flip of the switch" on the solar roof, as well as a visual display of the roof. Two more completion events have been or are in the midst of being planned: Grand opening of McLennan Park funded through the ISF program. The event will take place on Saturday, Aug. 13, featuring an official ribbon-cutting ceremony, sports demos, children’s activities, public-art acknowledgement, and a Geocache challenge. Celebration of building improvements at the Centre in the Square, funded through the ISF program. The event will take place in late August to mid September, date/time/details yet to be confirmed. Communications staff are currently working with Infrastructure Canada to determine the best time to announce the completion of the rest of the ISF and RInC funded projects by way of media releases. ACKNOWLEDGED BY: Dan Chapman, Deputy CAO & City Treasurer (Finance and Corporate Services) ë ó í ë ó ì ë ó ë Aug 10, 2011 Utilization of Council-Approved Expedited Purchasing Measures Expedited Purchasing Measure Utilization The Mayor and Clerk are authorized to sign ISF Contribution agreements have been received Provincial and Federal agreements as they relate and executed after being reviewed by the City to the Infrastructure Stimulus Fund and the Solicitor. CAF letter of offer has been received and Recreational Infrastructure Canada Fund, subject executed after being reviewed by the City Solicitor. to the satisfaction of the City Solicitor. The first set of RInC contribution agreements have been received and executed after being reviewed by the City Solicitor. RInC contribution agreements for the recently approved four aquatic facility projects have been received and executed after being reviewed by the City Solicitor. ISF amending Contribution agreements for the approval for an extension of project completion deadlines until October 31, 2011 for the five projects have been received and executed after being reviewed by the City Solicitor. RInC amending Contribution agreements for the approval for an extension of project completion deadlines until October 31, 2011 for the three projects have been received and executed after being reviewed by the City Solicitor. RInC amending Contribution agreement for the approval for a scope extension for Upgrades to the Bridgeport Community Centre project has been received and executed after being reviewed by the City Solicitor. The Chief Administrative Officer is designated to For Bridgeport Community Centre, expression of award tenders on Infrastructure Stimulus Fund interest for Consultant was awarded to AECOM with projects provided that the costs are within the CAO’s approval on October 20th 2009. Cost of the projected expenses outlined in the applications award is $218,925. Total budget of the project is and they are reported to Council by way of the bi-$2,249,740. There is a tight schedule for this project monthly update report. and a delay might jeopardize the project. Province confirmed funding for this project after a delay of almost 2 months. For Sewer and Watermain Rehabilitation project, expression of interest E09-100, Consultant Services – Rehabilitation of Infrastructure on Selected Streets Using Trenchless Technology has been awarded to Conestoga-Rovers & Associates, Waterloo with CAO’s approval on December 14th 2009. Cost of the award is $257,600., including a contingency of $22,400., and G.S.T. For Breithaupt Centre project, expression of interest E10-051, Consultant Services – Breithaupt Centre Accessibility Renovations and Mechanical Upgrades has been awarded to +VG Architects, with CAO’s ë ó ê Aug 10, 2011 approval on May 06, 2010. Cost of the award is $ 59,226.30, including a disbursement of $2,690.41 and G.S.T of $2,820.30. For Storm Water Rehabilitation project, tender T10- 014, Pond 4, Pond 22 and Pond 30 Stormwater Management Facilities Retrofit has been awarded to Golder Associates - Innovative Applications GAIA Inc., with CAO’s approval on May 19, 2010. Cost of the award is $1,232,134.05, including provisional items of $104,925., and G.S.T of $58,673.05. For Harry Class Community Pool project, expression of interest E10-025, Expression of Interest for Consultant Services has been awarded to John MacDonald Architect Inc., with CAO’s approval on May 19, 2010. Cost of the award is $102,590, including a disbursement of $2,000, and G.S.T. of $4,790. For Bridgeport Community Centre project, expression of interest E10-112, Expression of Interest for Construction Management firm has been awarded to Nith Valley Construction (2008) Ltd., with CAO’s approval on October 12, 2010. Cost of the award is $734,500, including H.S.T. of $84,500. For Centre in the Square project, T10-095, Refurbish Audience Seating has been awarded to Custom Cabinets, with CAO’s approval on October 15, 2010. Cost of the award is $378,598.59, including H.S.T. of $43,555.59. For Harry Class RInC project, T10-099, Harry Class Pool - Change House & Pool Deck has been awarded to Dakon Construction Ltd., with CAO’s approval on October 22, 2010. Cost of the award is $1,618,329.50, including H.S.T. of $186,179.50. For Energy Management Systems project, T10-106, Replacement of Existing Building Automation Systems has been awarded to ESC Automation Ltd., with CAO’s approval on October 8, 2010. Cost of the award is $304,422.51, including H.S.T. of $35,022.06. For Energy Management Systems project, T10-107, Installation of New Building Automation Systems has been awarded to TAC Controls & Automation Inc., with CAO’s approval on October 8, 2010. Cost of the award is $183,486, including H.S.T. of $21,109. For Centre in the Square project, T10-108, Sound ë ó é Aug 10, 2011 System has been awarded to Westbury National Show Systems Ltd, with CAO’s approval on October 15, 2010. Cost of the award is $157,418, including H.S.T. of $18,110.04. For Centre in the Square project, T10-109, Lighting & Rigging has been awarded to Westbury National Show Systems Ltd, with CAO’s approval on October 15, 2010. Cost of the award is $248,168.34, including H.S.T. of $28,550.43. For Energy Management Systems project, T10-126, Building Automation - Sportsworld has been awarded to TAC Controls & Automation Inc., with CAO’s approval on October 27, 2010. Cost of the award is $108,882.28, including H.S.T. of $12,526.28. For Breithaupt Centre project, T10-114, Breithaupt Community Centre - Accessibility Renovations has been awarded to Greyhound Contracting Inc., with CAO’s approval on November 8, 2010. Cost of the award is $ 824,900, including H.S.T. of $94,900. Consultants involved in the preliminary phases be This measure has been effective at expediting the retained and the consultant selection process be project timeline. waived for following projects mentioned below: McLennan Park – Walter Fedy Partnership CMF Improvements - Giffels Associates Limited/ IBI Group (Architect consulting services) CMF Improvements - Morrison Hershfield Limited (Mechanical and Electrical consulting services) CMF Improvements - Morrison Hershfield Limited (LEED consultant services) For Storm Water Infrastructure Rehabilitation This measure has been effective at expediting the projects, involving drainage upgrades only will be project timeline. delivered by general contractors under existing construction contracts through a standard change order process as per purchasing guidelines. That the Mayor and Clerk be authorized to This measure will expedite the project timeline. The execute a 'cost plus' agreement with Ball City has received a written confirmation from the Construction for the completion of the design and Federal government on this approach. construction of Sportsworld Arena improvements to an upset limit of $900,000; said agreement to be to the satisfaction of the City Solicitor. The King Street reconstruction project be This measure has been effective at expediting the delivered by general contractors and consultants project timeline. ë ó è Aug 10, 2011 under existing construction contracts and consulting contracts through a standard change order process as per purchasing guidelines. That the Mayor and Clerk be authorized to This measure has been effective at expediting the execute any amendments to Agreements project timeline. pertaining to Projects for which funding is approved through the Infrastructure Stimulus Fund, the Recreational Infrastructure Canada Fund, and the Community Adjustment Fund, if necessary, and provided said amendments are satisfactory to the City Solicitor. That the Mayor and Clerk be authorized to This provision ensures that the Mayor and the Clerk execute any agreements pertaining to the tenders have the authority to execute agreements for awarded with respect to Infrastructure Stimulus tenders awarded by the CAO. Fund projects provided said agreements are satisfactory to the City Solicitor. That the Chief Administrative Officer be authorized This measure has been effective at expediting the to approve the commencement of the project timeline. prequalification process and approval of awards to the prequalified vendors for Infrastructure Stimulus Fund and Recreation Infrastructure Canada Fund projects in instances where scheduling the matter for the next Council meeting would result in undue project delay, and that a report regarding these awards be brought to Council at a future meeting; That the Director, Supply Services be authorized to extend current consultant purchase orders for Infrastructure Stimulus Fund and Recreation Infrastructure Canada Fund projects to incorporate the costs of applications for various City building/planning approvals which would normally be incurred directly by the City, including related construction management fees or the other administrative fees. THAT the Mayor and Clerk be authorized to This provision ensures that the Mayor and the Clerk execute an amendment to the following contracts have the authority to release 2% holdback to avoid and agreements satisfactory to the City Solicitor to any loss of funds due to non-release of holdback provide for the early release of the 2% prior to March 31, 2011. maintenance holdback or portions thereof respecting projects for which infrastructure stimulus funding or other grant(s) have been obtained: McGillivray & Sons Contractors Limited (September 22, 2009) – to allow the City to release the 2% maintenance holdback on February 15, 2011 for the stimulus fund work completed for Greenbrook drive; Coco Paving Inc. (April 28, 2009) – to ë ó ç APPENDIX "C" STIMULUS PROJECT STATUS UPDATE Aug 10, 2011 allow the City to release the 2% maintenance holdback on February 15, 2011 for the stimulus fund portion of the work; THAT the Mayor and Clerk be authorized to This provision ensures that there is no loss of funds execute forthcoming contracts, agreements, and due to non-release of holdback prior to March 31, amending agreements satisfactory to the City 2011. Solicitor, reducing the release of the 2% holdback from two (2) years from the date of substantial completion to February 15, 2011 in relation to stimulus fund projects. That the Mayor and Clerk be authorized to ISF and RInC Contribution agreements have been execute any amendments that may be required to received and executed by the City after being the Infrastructure Stimulus Agreements and reviewed by the City Solicitor. Recreational Infrastructure Canada Agreements to address any extensions that may be given under the respective programs, said amendments to be to the satisfaction of the City Solicitor. ë ó ïð