REPORT T0: Community & Infrastructure Services Committee
DATE OF MEETING: August 15, 2011
SUBMITTED BY: Jim Witmer, Director of Operations, ext 4657
PREPARED BY: Dan Locke, Manager of Operational Support, ext 4517
WARD(S) INVOLVED: Ward 3
DATE OF REPORT: July 28, 2011
REPORT NO.: INS-11-062
SUBJECT: ARDELT PLACE SNOW DUMP FACILITY LEASE
RENEWAL
RECOMMENDATION:
That the Mayor and Clerk be authorized to execute a lease agreement satisfactory to the
City Solicitor with the current property owner at 75 Ardelt Place in the City of Kitchener
for the use of the lands for the purpose of providing a snow dumping facility for the
exclusive use of City staff and their contractors.
BACKGROUND:
The City of Kitchener, Operations Division currently operates a snow dump facility at 75 Ardelt
Place and has been utilizing the site by an agreement since 2007.
The lease agreement for this location is up for renewal in August of 2011. Staff are currently in
the process of evaluating several other locations as alternative sites. As this evaluation will not
be completed for some time, a renewal of the lease agreement for a period of two years is
desired which would then extend the new lease agreement until July 31st of 2013.
REPORT:
The Operations Division has implemented several snow disposal solutions over the past few
years, 75 Ardelt being the primary snow dump location and 55 Bramm St. being the primary
snow melting location. A secondary snow dump location is available for City of Kitchener use
on Kitchener Wilmot Hydro lands at Graber Place on an emergency basis.
In September 2006 Council approved the purchase of a snow melting machine which in
conjunction with the snow dump sites make up the total snow disposal infrastructure available to
Operations.
9-1
1
Staff Re ort
p
Krr~.~-~~,i~iER ~nfrastru~ture Servrces Department www.kitthenerta
Staff has reached an agreement with the property owner at 75 Ardelt Place fora 2 year lease
renewal for a portion of the lands for a snow dump facility beginning in August 2011 and ending
in August 2013.
A Phase II Environmental Site Assessment has been completed on the site in accordance with
the Ministry of the Environment Guidelines for Snow Disposal and De-icing Operations in
Ontario.
ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN:
This initiative aligns with the Efficient and Effective Government Strategy. The snow disposal
strategy incorporates both snow dumps and snow melting locations to minimize costs while
maintaining safety levels required to meet provincial minimum maintenance standards for road
safety.
FINANCIAL IMPLICATIONS:
There will be an increase in the monthly lease rate from $2232 in 2007 (which had not been
increased) to a lease rate of $2500 per month (which includes the 3% increase per year since
the initial agreement) for the first year and an increase to $2575 per month for the second year.
Operations will fund this increase through the existing winter budget.
COMMUNITY ENGAGEMENT:
NIA
CONCLUSION:
The snow dump at 75 Ardelt is required for the effective disposal of snow resulting from snow
accumulations that the city traditionally experiences through the course of a normal winter.
Alternatives are currently being explored both by city staff and regional staff in an attempt to find
a permanent joint solution to snow disposal. In addition, permanent snow melting locations are
currently being explored as part of the overall solution.
ACKNOWLEDGED BY: Pauline Houston, Deputy CAO, Infrastructure Services, ext 2646