HomeMy WebLinkAboutCAO-11-032 - Boathouse Interior and Exterior RenovationsREPORT TO:Council DATE OF MEETING: January 16, 2012 SUBMITTED BY: Rod Regier, Executive Director PREPARED BY: Rod Regier, Pauline Houston WARD(S) INVOLVED: All DATE OF REPORT: December 31, 2011 REPORT NO.: CAO-11-32 SUBJECT: Boat House Interior and Exterior Renovation Options RECOMMENDATION: That the following recommendations be tabled to enable consultation with the Victoria Park Neighbourhood Association the Victoria Park Working Group, and the current Boathouse operator and that they be brought forward for Council consideration and approval on February 6, 2012; That the Victoria Park Lake Boathouse improvements identified as Option # 2 Report CAO 11-030 be undertaken using the $500,000 provision in the 2012 Capital Budget to secure the Boathouse as a City of Kitchener asset which is suitable for use as a cultural and commercial venue; That lease revenue and/or energy savings from this property be allocated to fund the $109,000 shortfall under Option #2 over the term of the lease; That tenant specific upgrades, such as the relocation of the kitchen, should be financed by the operator subject to the negotiation of a satisfactory long-term lease. BACKGROUND: The Victoria Park Boat House was constructed in 1968. For many years its primary function was to serve as a rental facility for the boats provided on Victoria Lake during the summer and as a skating change room during the winter. In the 1990’s the City of Kitchener was approached by an interested party to open a music/concession venue in the Boathouse called the “Tearoom”. That particular use struggled financially and the rental agreement was assigned to Mr. Kevin Doyle. The building has operated successfully since that time as an independent music venue. Victoria Park is considered the City’s “Crown Jewel”; and it provides very important social, cultural and recreational functions for the local community and the entire City. In 2003, the Victoria Park Foundations Plan and Strategic Plan were developed to guide the future and long term improvements for Victoria Park. This plan identified restoration of the landscape around the Boathouse as a significant priority. It did not address the interior requirements of the boat house or the operating framework of the facility. î ó ï Building Maintenance History Over the past 30 years, the City of Kitchener has engaged in basic building maintenance. 1981-82 – Window replacement, exterior brick repairs and pointing 1994-95 – Public washroom floors replacement, walls tiled, new fixtures installed 1997 – (Heating) new boiler installed 1999 – Minor kitchen cabinets/shelving upgrades 2004-05 – Major flood- building flood damage cleaned/or repaired/new floor installed 2006 – Air Conditioning installed 2007 – Sound attenuation measures to address neighborhood concerns over noise It is noteworthy that the interior configuration of the building and exterior patio have not been modified since the building was constructed. The building shell remains un-insulated. The kitchen configuration was originally designed to support an exterior concession window rather than the current interior entertainment venue. It has significant design deficiencies which detract from its effectiveness and the quality of the venue. The exterior patio has become unsafe and is planned for replacement during the reconstruction of Victoria Lake. In December 2011, work commenced on Victoria Lake. 2011 tendered drawings for the Victoria Park Lake Improvements included the reestablishment of the lake edge behind the boathouse along with the restoration and reinstatement of landscaping along the sides of the boathouse which is currently being used as a construction access point into the lake. The landscaping on the tendered drawings took into account the public input from the Victoria Park Lake Improvements public consultation process, the 2003 Victoria Park Strategic plan and the existing landscape improvements which have occurred within the park over the past several years. The overall tendered prices that came in for the Victoria Park Lake Improvements were significantly higher than budgeted. In an attempt to meet the funding that was available, the boathouse dock and patio improvements as well as the upper lake pedestrian bridge items were removed from the tendered and provisional items list. In October 2011, Council supported the continued use of the Boathouse as a cultural venue for independent music and directed an analysis of required upgrades to the building to support this use. The following report outlines the required work and potential costs of various options for both the exterior and interior of the Boathouse. REPORT: As requested by council on November 14, 2011 please find below a review of options for internal and external renovations to the Boathouse for council consideration. Exterior Landscaping The original boathouse landscaping, proposed as part of the 2011 Victoria Park Lake Improvements tendered drawings, included the landscaping at the rear of the boathouse up to the lake edge and the restoration of the west and east side of the boathouse. The landscaping incorporated a public boardwalk, private patio with an armour stone planter separating the two uses, concrete unit paver surfacing for the patio and walkways adjacent to the boathouse, raised planting beds along the sides of the boathouse, along with new asphalt pathways connecting the new landscape with the existing pathways and front landscape of the boathouse. As part of this report the entire landscaping around the boathouse has been incorporated, including the rear of the boathouse up the lake edge, both sides of the boathouse and the front of the boathouse up to Jubilee Drive. î ó î Option 1 (Attachment #1): This option includes a 4m wide boardwalk along the lake edge, concrete unit paving around the boathouse, a private patio at the rear of the boathouse, and various raised planters. Between the lake edge and the rear of the boathouse, an armour stone planter creates an aesthetically pleasing separation barrier between the public walkway and private patio, and also provides seating for the public along the entire length of boardwalk. The front of the boathouse incorporates planting beds to soften the exterior of the building, provides a vehicular lay-by and a safe pedestrian crossing on Jubilee Drive. Estimated Cost: $500,000 Option 2 (Attachment #2): This option is the same as option 1 but with the removal of the 4m wide boardwalk and the armour stone planter between the walkway and patio. The boardwalk will be replaced with a 3m wide asphalt walkway. A railing will be installed along the walkway to provide a safe barrier from the lake. An armour stone seat wall is provided along the lake edge between the walkway and patio. Estimated Cost: $375,000 Option 3 (Attachment #3): The option removes additional concrete unit pavers from around the boathouse and replaces it with asphalt paving, with the exception of the patio and door entrances. The raised planters around the boathouse have been removed and replaced with at- grade planting beds. An armour stone seat wall is provided along the lake edge between the walkway and patio. Estimated Cost: $250,000 Interior Renovations Interior renovations are required to ensure the building is able to meet the separate obligations and needs of the landlord and those of the tenant. The landlord is generally required to provide a secure and efficient building shell, including accessible entrance and basic services such as washrooms and electrical, mechanical and plumbing services stubbed off for tenant lease hold improvements. The tenant is generally obliged to finish the interior space to meet their specific operating requirements. These upgrades generally include operationally specific mechanical and electrical, trade fixturing, millwork, interior partitions and production facilities such as kitchens. In most cases of a single purpose building, the tenant is responsible for the cost of utilities and maintenance and the landlord is responsible to ensure the maintenance of the exterior building shell and entrance facilities. Facilities management met with the Boathouse tenant Mr. Doyle and identified a list of potential work to address building deficiencies and improve operating efficiency. An external architect was then contracted to develop a cost estimate of the potential works. The work fell into three basic categories: washroom and accessibility upgrades, kitchen relocation, and electrical and mechanical. It should be noted that of the categories, all but the kitchen relocation would normally be associated with the provision of a serviceable commercial building shell suitable for tenant occupancy and upgrading. The City of Kitchener will need to address these issues whether the current use continues or the building is used for some other purpose in the future. Boathouse Rental Property – Landlord Requirements and Tenant Inducements In the case of the Boathouse, short-term landlord responsibilities fall into three areas: meeting current accessibility standards, providing an energy efficient building envelope, and the î ó í provision of secure, functional washroom facilities and mechanical rough-ins. Estimates of the costs to establish these features are listed below. As standard landlord responsibilities, these upgrades are independent of the potential use or tenant and are required to deliver a building that can meet the conditions of the current commercial rental market. In the case of accessibility, current standards are a legislated requirement and the City has no choice but to address current deficiencies. In the case of the interior insulation, the un-insulated building shell would not meet current City of Kitchener standards for environmental stewardship. Kitchener is currently responsible for the utility costs for the building. Providing an insulated shell would provide a potential payback through reduced utility Isolating the washrooms and ensuring their effective operation is a standard landlord responsibility and would be required by any tenant or City of Kitchener run operation. Building Exterior Budget including contingencies and HST Accessibility $ 36,000 Building Shell Budget including contingencies and HST Interior insulation and mechanical rough-ins $110,000. Building Interior Budget including contingencies and HST Washrooms requirements $ 89,000 Total Landlord upgrades $234,000 Specialty Tenant Interior Requirements As noted above, the existing kitchen was constructed to serve a seasonal concession stand. The current and proposed use require a fully operational commercial kitchen. In addition, the relocation of the kitchen to the east side of the building, currently used for storage, would increase patron seating, improve the presentation of the interior space to Boathouse clients and significantly improve operational efficiency. This move would allow for the construction of efficient walk-in refrigeration capacity, and dramatically improve the efficiency of the building as a whole. It is anticipated that these efficiencies would result in the ability of the operation to finance the improvements over a reasonable period. These works are normally the responsibility of a tenant in a standard commercial lease, subject to landlord approval, and will be dealt with accordingly in this case. ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN: Kitchener City Council recently affirmed the role of the Boathouse as a strategic cultural asset in the support of the City’s independent music industry. It further reaffirmed this role in the Kitchener Economic Development Strategy 2011. A full cluster strategy for the independent music industry in Kitchener has been initiated and a stakeholder consultation is expected to begin in the late winter or early spring, 2012. î ó ì FINANCIAL IMPLICATIONS: Both interior and exterior renovation projects have alternatives based on the scope of the renovation. This allows the estimation of three financial scenarios (high, medium and low) for the total project cost. The 2012 City of Kitchener Budget has a capital allocation of $500,000 to complete exterior and interior renovations of the Boathouse. Total Cost Summary Option 1: Exterior Renovations Option 1 $500,000 Interior Renovations $234,000 Estimate: $734,000 Option 2: Exterior Renovations Option 2. $375,000 Interior Renovations $234,000 Estimate: $609,000 Option 3: Exterior Renovations Option 3 $250,000 Interior Renovations $234,000 Estimate: $484,000 Under option #2 (recommended) there is a shortfall of $109,000 attributed to the installation of the interior insulation. COMMUNITY ENGAGEMENT: During the Victoria Park Lake Improvements process, various public information centre meetings were held. During these meetings, the public provided input regarding the boathouse dock and public access to the lake edge. The tender drawings reflected the information gathered from the public information centres with the continuous trail adjacent to the boathouse patio. In September 2011, Kitchener received input from over 200 members of the public regarding the use of the Boathouse as a venue for independent music. The proposed program responds to in part to the input received during that process. Additional feedback is now required to inform Council’s decision on the options for both interior and exterior renovations to the Boathouse and its immediate surroundings. As a result, between January 17 and January 27, the proposed interior and exterior renovation options will be taken into a consultation with the Victoria Park Working Group, Victoria Park Neighbourhood Association and advocates for the Boathouse. In addition, information gathered from recent public consultations regarding the Downtown Strategic Plan will be evaluated as they relate to this issue. CONCLUSION: The Boathouse is a City of Kitchener facility which has been repurposed several times during over the past 44 years. The City as landlord is responsible for basic maintenance of the building shell and core services. The effective utilization of the building as a cultural and entertainment venue requires structural and systems improvements to continue its function and meet î ó ë increasingly demanding operating standards. A number of the systems currently in place, such as building accessibility or washroom access, require upgrading. The kitchen was originally designed as a concession stand facility, but has been serving a restaurant with a capacity of 85 persons. The exterior decking has deteriorated to the point of being unsafe and has now been removed. These basic facilities are considered within the responsibility of a landlord and need to be addressed. The proposed interior and exterior programs address the key deficiencies and set the stage for the Boathouse as a sustainable commercial operation and a significant contributor to the cultural life of the city. All suggested exterior facility accessibility upgrades shall be reviewed and approved by the Heritage Committee prior to commencing. ACKNOWLEDGED BY: Carla Ladd î ó ê î ó é î ó è î ó ç