HomeMy WebLinkAboutEnv - 2012-02-16 - Sub-Committee Report - Strasburg Road Extension EnvironmentStrasburg Road Environmental Assessment Sub Committee - Report Date: January 20, 2012 To: Environmental Committee Strasburg Road Environmental Assessment Sub-Committee From: (Rizwan Younis, Mark PetersonandCouncillor Fernandes) Subject: Strasburg Road Environmental Assessment Sub-Committee Report (EA) Study for the South Section of the Strasburg Road Extension from north of Stauffer Drive southerly to New Dundee Road. Background information was provided to the Committee as th part of the December 15 agenda package and a website link was provided to additional information available online. th At the December 15, 2011 Environmental Committee meeting, Ian Upjohn, Principal Planner Environment Division with SNC-Lavalin Inc. with assistance from his project team gave a presentation on the Strasburg Road Extension Environmental Assessment to the Committee. The presentation highlighted the following: Project location / Project objectives Alignment alternatives Land use, Natural heritage features and Central heritage features Evaluation criteria / Screening of alignment alternatives Preferred alignment In addition to the Consultant and his project team representatives were present from the City (Mr. Binu Korah,Manager, Development Engineering and Mr. Grant Murphy, Director of Engineering) to answer questions and receive comments and/or concerns from the Committee. Latter in the meeting several members inquired as to how their questions, comments and/or concerns would be addressed. The Committee decided that that a sub-committee would be established to provide comments. All comments and/or concerns from the sub-committee / Committee will be forwarded onto Mr. th Binu Korah. Mr. Binu Korah will return to the Environmental Committee for the February 16 Committee meeting. The following are the comments put forward by the Strasburg Road Environmental Assessment Sub-Committee: 1.Comments related to the project : It should be clearly identified whether or not the project is required because the 1.1. existing road infrastructure will not adequately handle the projected increase in vehicular traffic due to increased residential development in this area. 1.2. Other factors that were not discussed were that there is no development presently dependent on this road extension to access a major arterial road. Which begs the question of: If no further development occurs then is this road really necessary? 1.3. Another factor that is not stated anywhere in the material is the fact that these lands are presently under an OMB appeal. Therefore, it is the opinion of this review that until the 1 of 10 ì ó ï appeal is completed that no further work should move forward. The consultation process is costly and if the OMB upholds the Protected Countryside Line then no future development will be allowed at all in this location. 1.4. The pure desire for another road seems to have overridden the clear impacts on the wide range of conditions and sensitivities. 2. Comments related to the evaluation methodology employed : 2.1. In the EA, the method used to deduce the Recommendations i.e., which alignment receives further study and which alignment does not from the pie charts developed in the Screening of the Long List of Alignment Alternatives is not described. 2.2. The consultant who prepared the EA indicated that there was no numerical or weighting system applied to the Evaluation Criteria used to screen the Long List of Alignment Alternatives. The reviewer questioned how it is possible to accurately determine the best alignment alternatives without some objective scoring system. 2.3. As an exercise, each reviewer applied objective scoring systems using the information provided. 2.3.1. The first reviewer assigned a numerical score to each of the pie charts assigned to each alignment alternative. For simplicity, it was assumed that all evaluation - -for all the evaluation factors for each of the Long List of Alignment Alternatives were totaled, it was found that: Table 1: Review No. 1 AlternativeScoreRank (in alignment preference) W1 441 W2 339 W3 377 C1 422 C2 394 E1 368 E2 394 E3 386 E4 403  2.3.2. This evaluation matched the EA Comprehensive Summary Comments/Recommendations with the exception of alignment C1. Specifically, in the use a weighting system for each of the evaluation factors, but in reality some of the evaluation factors may indeed be more important than others. For example, technical factors may be deemed to be more important than financial factors which may not be as important as land use considerations.  2 of 10 ì ó î 2.3.3. The second reviewer performed a similar but different analysis based on a (analysis included on pages610). Slide 20 from the Dec 15, 2011 presentation was used for the analysis. The following ranking was obtained: Table 2: Review No. 2 AlternativesRank E2 4 E3 3 E4 3 E4-Modified 1 C2 5 W1 2 2.3.4. After reviewing the Long list of alternatives the third reviewer gave each pie a numerical ranking where a full pie was 5 and an empty pie was 1 the numbers showed the following: Table 3: Review No. 3 AlternativeScoreRank (in alignment preference) W1 441 W2 413 W3 386 (tied with E3) C1 422 C2 395 (tied with E2) E1 377 E2 395 (tied with C2) E3 386 (tied with W3) E4 404 2.3.5. From the analysis above it is interesting that C1 and W2 were not considered for further study even though the ranking places them 2nd and 3rd using the same pies as the consultant did. Also, it is interesting that it was not possible to replicate the same preferred alignment(s) as shown in the short list of options. 2.4. The factors and indicators/measures comprising the evaluation criteria were thorough. However, because the Comprehensive Summary Comments (Recommendations) appear to be qualitative only, the method of arriving at these recommendations is not transparent. This raises the question of what was weighted more Environmental impacts or transportation impacts? Cultural impacts or Socio impacts? Transportation or Cultural? 2.5. It is impossible to replicate the recommendations of the EA without some kind of scoring and weighting system in place to minimize subjectivity. The use of a weighting system would further refine the selection of the best alternative route. Consultants and/or City staff should look into more prudentquantitative methods to ascertain the most feasible alignment.  3 of 10 ì ó í 2.6. A peer review should be conducted specifically looking at the methodology of the EA process as well as how the preferred alignment was decided without any numerical ranking, weighting or scoring. 3. Comments related to woodlands: 3.1. A concern with the original plan of the road going through the woodlot (1980's) as well as other woodlots to the east. 4. Comments related to wetlands: 4.1. The clear indication of the wetlands as viewed on the map titled Study Area boundaries where Endangered Species occur. Therefore it is reasonable to conclude that any road built within those boundaries or the MNR regulated area will have significant impact on the Endangered species. 5. Comments related to water resources: 5.1. The area of the EA is considered a Well Head Protection Area (WHPA) under the 5.2. The western option appears to address issues related to sensitive wildlife (fauna) in the area but does not adequately address concerns of impacts to the groundwater resource which in my mind is a greater environmental issue. 5.3. Reduction of the permeable surface area footprint would present a threat to the recharge capability in this area. 5.4. Reduction of the permeable surface area footprint would have a negative impact on the groundwater quantity in this area. 5.5. is a man-made feature and can be recreated 6. Comments related to: 6.1. development will undoubtedly have a significant impact on the groundwater recharge facilitate further infilling by developers as the majority of the surrounding area was identified as being owned by developers. 6.2. The western option would only defer the takeover of the Bed and Breakfast operation due to the poten  4 of 10 ì ó ì 7. 7.1. It appears that the cost of purchasing the land from a viable business that also has historical value has not been factored into the financial criteria but only the cost of building the road. The owners of land that W1 impacts also one owner but whose interests are not in farming as the assessor has viewed minimal farming activity on those lands in the last number of years. Acquisition of ALL lands must be factored into the financial component. 8.Comments related to the information available: 8.1. should be completed with the most recent information before the consultant makes any further presentations on this subject. 8.2. Also note that Slide 20 from the Dec 15, 2011 presentation does not match with the Project Information Package -Full Text Matrix. 9. The Strasburg Road Environmental Assessment Sub-Committee of Kitchener Environmental Committee (KEC) recommends the following: 9.1. A peer review should be conducted specifically looking at the methodology of the EA process. Consultants and/or City staff should look into more objective quantitative methods to ascertain the most feasible alignment. 9.2. These lands are presently under an OMB appeal at the Regional level. Therefore it is the opinion of this review that until the appeal is completed, that no further work should move forward. NOTE: The role of the Environmental Committee will be complete once the Committee has provided their advice to standing committee/council through resolution or otherwise at the th February 16, 2012 meeting.  5 of 10 ì ó ë  6 of 10 ì ó ê  7 of 10 ì ó é  8 of 10 ì ó è  9 of 10 ì ó ç  10 of 10 ì ó ïð