HomeMy WebLinkAboutFCS-12-045 - T12-009 Duke & Ontario Parking Garage 2012 Rehab P1 KITC;H~.N~.R Staff Report finance and Corporate Ser~rices Department www.kif[henerca REPORT TO: Committee of the Whole DATE OF MEETING: 2012-03-26 SUBMITTED BY: Larry Gordon, Director of Supply Services 2214 PREPARED BY: Larry Gordon, Director of Supply Services WARD(S) INVOLVED: 10 DATE OF REPORT: 2012-03-14 REPORT NO.: FCS-12-045 SUBJECT: T12-009 -Duke & Ontario Street Parking Garage 2012 Rehabilitation Program RECOMMENDATION: That Tender T12-009 -Duke & Ontario Street Parking Garage 2012 Rehabilitation Program be awarded to Canadian Construction Controls Ltd., Breslau, Ontario at their tendered price of $1,117,560. including provisional items and contingencies of $150,000., plus H.S.T. of $145,282.80, for a total of $1,262,842.80; and further, That the Mayor and City Clerk be authorized to execute an agreement satisfactory to the City Solicitor. BACKGROUND: The Duke & Ontario Garage was constructed in 1967 using a post tensioning tendon system which provided the structural support for the garage. The tendons have reached their life expectancy and must either be repaired or portions of the garage closed to parked vehicles. Since this garage meets the parking needs of many surrounding businesses and potentially additional developments in the area, it must be maintained. The 2012 repairs, which are the last phase of the repair program, will include the installation of new external post tensioning and waterproofing on the P3 South and P4 North slabs, repairs on the helical ramp as well as repairs and installation of an elastomeric wall coating on the facade of the garage. REPORT: Tenders were advertised publicly in The Record, the Daily Commercial News, on the City of Kitchener website and the Internet through the Ontario Public Buyers Electronic Tendering Information System. Documents were picked up by twenty-nine (29) interested parties, and by the closing date of Thursday, February 23`d, 2012, ten (10) tenders had been received. 1 iv) - 1 The tenders were reviewed by Michael Pond, Read Jones Christoffersen Ltd., the City's Consultant for the project, and John McBride, Director of Transportation Services, who have elected to award the project to Canadian Construction Controls Ltd., Breslau, Ontario. The following tenders were received: Canadian Construction Controls Ltd Clifford Restoration Ltd. Amlin Contracting Ltd. Alliance Restoration Ltd. Decora Building Restoration Ltd. Brook Restoration Ltd. ConCreate USL Ltd. Partnership Complete Concrete Restorations K.I.B. Building Restoration Inc. Global Restoration Ltd. Breslau ON Scarborough ON Mississauga ON Bolton ON Toronto ON Toronto ON Bolton ON Milton ON Mississauga ON Downsview ON Bid Price $1,262,842.80 $1,405,211.05 $1, 426, 738.00 $1, 497, 069.20 $1,531,715.00 $1, 610, 250.00 $1, 656, 467.00 $1, 791, 050.00 $1, 877, 474.66 $1, 904,168.65 ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN: Theme: Financial Management Strategic Direction: Ensure responsible use of public funds within a supportive policy framework. The City of Kitchener's purchasing policies and practices ensure openness, fairness and transparency in the procurement of goods and services. 1 iv) - 2 FINANCIAL IMPLICATIONS: The total available funding in the Parking Duke & Ontario Garage repairs capital account is $1,593,669. The projected surplus at the end of the this phase of work (E) will be considered for closeout as part of the 2013 budget preparations and could be used to offset the 2011 deficit of $317,000 in the Parking enterprise. Financial Summary for Tender T12-009 Duke & Ontario Garage Rehabilitation 2012 Internal Order Group -Parking Duke & Ont Garage Repairs (59500208) As at March 12, 2012 Estimated Cost for this Phase of Work Tender T12-009 costs, including HST 1,262,842.80 less: HST rebate on tender (145,282.80) Net Cost Being Awarded 1,117,560.00 A Costs Incurred to Date - Projected Costs for Structural Engineering 68,365.00 Total Estimated Cost for this Phase of Work 1,185,925.00 C Budget for this Phase of Work City of Kitchener 1,300,000.00 Total Budget for this Phase of Work 1,300,000.00 B Estimated Surplus/(Deficit) for this Phase of Work (B - C) 114,075.00 D Surplus from previous phases 361,925.00 Projected Surplus balance at the end of this phase 476,000.00 E COMMUNITY ENGAGEMENT: Theme: Financial Management Strategic Direction: Ensure responsible use of public funds within a supportive policy framework. The City of Kitchener's purchasing policies and practices ensure openness, fairness and transparency in the procurement of goods and services. ACKNOWLEDGED BY: Dan Chapman, Deputy CAO & City Treasurer, Finance and Corporate Services 1 iv)-3