REPORT TO:Committee of the Whole
DATE OF MEETING:
2012-09-17
SUBMITTED BY: Larry Gordon, Director of Supply Services, 2214
PREPARED BY:
Laurie Stecho, Supervisor of Purchasing, 3576
WARD(S) INVOLVED: 3
DATE OF REPORT: 2012-08-02
REPORT NO.:
FCS-12-139
SUBJECT:
T12-003 - Block Line Road Extension (Lennox Lewis Way to
Courtland Avenue)
RECOMMENDATION:
That Tender T12-003 – Block Line Road Extension (Lennox Lewis Way to Courtland Avenue),
McLean Taylor Construction Limited, St. Marys, Ontario,
be awarded to at their tendered
price of $7,023,191.93, including provisional items and contingencies of $861,323., plus H.S.T.
of $913,014.95, for a total of $7,936,206.88; and further,
That the Director of Supply Services be authorized to execute an agreement satisfactory to the
City Solicitor.
BACKGROUND:
The City of Kitchener completed a Class Environmental Assessment for the Block Line Road
extension from Homer Watson Boulevard to Courtland Avenue in February 2011. This road
was to be completed in two phases; the first phase of construction, extending Block Line Road
from Homer Watson Boulevard to Lennox Lewis Way was completed in 2012. The
construction of the second phase will commence in September 2012. This project includes
construction of a 4 lane bridge, sidewalks, bike paths and installation of new signals at the
intersection of Courtland and Block Line Road. The completion of this secondary arterial road
will provide a vital connection between 2 main arterial roads via Homer Watson Boulevard and
Courtland Avenue.
REPORT:
Tenders were advertised publicly in the Daily Commercial News, on the City of Kitchener
website and the Internet through the Ontario Public Buyers Electronic Tendering Information
System. Documents were picked up by twenty-two (22) interested parties, and by the closing
th
date of Thursday July 26, 2012, four (4) tenders had been received.
The tenders were reviewed by D. McLeod, Aecom, the City’s Consultant for the project, and M.
Memon, Design & Construction Engineer, who concur with the above recommendation.
ï ·÷ ó ï
The following tenders were received:
Bid Price Adj. Bid Price
McLean Taylor Construction Limited St. Marys ON $7,936,206.88 *
E & E Seegmiller Limited Kitchener ON $8,294,694.38
Belor Construction Ltd. Mississauga ON $8,651,195.35 $8,706,963.01
Amico Design Build Inc. Oldcastle ON $9,126,790.83 $9,352,564.83
All Tenders were reviewed for mathematical errors and adjusted accordingly.
ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN:
Theme: Financial Management
Strategic Direction: Ensure responsible use of public funds within a supportive policy
framework.
The City of Kitchener’s purchasing policies and practices ensure openness, fairness and
transparency in the procurement of goods and services.
FINANCIAL IMPLICATIONS:
Tender T12-003
Block Line Road Extension
The total budget for all phases of this project is $17,456,399.00
Estimated Cost for this Phase of Work
Tender T12-003 costs, including HST 7,936,206.88
less: HST rebate on tender (789,406.42)
Net Cost Being Awarded 7,146,800.46 A
Costs Incurred to Date -
Projected Costs (including Staff Time/Permitting/Material Testing/Railway
Relocation/Land Acquisition) 3,770,000.00
Total Estimated Cost for this Phase of Work 10,916,800.46 C
Budget for this Phase of Work
Development Charges 12,855,000.00
Total Budget for this Phase of Work 12,855,000.00 B
Estimated Surplus/(Deficit) for this Phase of Work (B - C) 1,938,199.54 D
Existing Surplus/(Deficit) in account (1,290.01)
Total Estimated Surplus/(Deficit) 1,936,909.53 E
The surplus will be returned to the Development Charge reserve.