HomeMy WebLinkAboutFCS-13-038 - T13-014 - Glasgow St Reconstruction REPORT TO:Committee of the Whole DATE OF MEETING: 2013-03-25 SUBMITTED BY: Larry Gordon, Director of Supply Services, 7214 PREPARED BY: Larry Gordon, Director of Supply Services, 7214 WARD(S) INVOLVED: 8 DATE OF REPORT: 2013-03-11 REPORT NO.: FCS-13-038 SUBJECT: T13-014 – Glasgow Street (Belmont Avenue West to Westmount Road West) Reconstruction RECOMMENDATION: That Tender T13-014 – Glasgow Street (Belmont Avenue West to Westmount Road West) Verly Construction Group Inc., Mississauga, Ontario Reconstruction, be awarded to at their corrected tendered price of $2,047,271.40, including provisional items and contingencies of $174047.50, plus H.S.T. of $266,145.28, for a total of $2,313,416.68. BACKGROUND: Engineering Services is proceeding with the reconstruction of Glasgow Street (Belmont Avenue West to Westmount Road West). Funds for construction have been approved by Council as part of the 2013 budget. This section of Glasgow Street was originally constructed in the 1920’s with segmented construction of underground services in the subsequent decades and is in need of replacement. The project involves the replacement of the roadway, curb and gutter and sidewalk and all underground services (including a regional raw water transmission system, funded by the Region) and surface works. The administration, design and tendering of this project has been completed by City staff. The construction administration and inspection of this project will be completed by City staff as well. REPORT: Tenders were advertised publicly in the Daily Commercial News, on the City of Kitchener website and the Internet through the Ontario Public Buyers Electronic Tendering Information System. Documents were picked up by twenty (20) interested parties, and by the closing date of Thursday, March 7, 2013, thirteen (13) tenders had been received. The tenders were reviewed by J. Seip, Engineering Technologist, and S. Allen, Manager, Engineering Design and Approvals, who concur with the above recommendation. 1 iii) - 1 The following tenders were received: Bid Price Corrected Bid Price Verly Construction Group Inc. Mississauga ON $2,313,669.20 $2,313,416.68 * Regional Sewer and Watermain Ltd. Cambridge ON $2,539,589.28 J. Weber Contracting Limited Breslau ON $2,604,113.38 $2,604,117.91 40754 Ontario Limited o/a Sousa Concrete Branchton ON $2,627,281.05 $2,627,279.92 Sierra Construction (Woodstock) Limited Woodstock ON $2,638,585.61 $2,638,589.00 Elgin Construction St. Thomas ON $2,853,417.30 Network Sewer & Watermain Ltd. Cambridge ON $2,855,607.39 Bel-Air Excavating & Grading Ltd. Cambridge ON $2,860,541.44 Terracon Underground Ltd. Brantford ON $2,914,146.38 Steed and Evans Limited St. Clements ON $2,947,040.00 C. H. Excavating London ON $3,030,660.60 GRT Excavating Woodstock ON $3,080,521.28 Amico Infrastructures (Oxford) Inc. Woodstock ON $3,410,358.22 ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN: Theme: Financial Management Strategic Direction: Ensure responsible use of public funds within a supportive policy framework. The City of Kitchener’s purchasing policies and practices ensure openness, fairness and transparency in the procurement of goods and services. 1 iii) - 2 FINANCIAL IMPLICATIONS: Tender T13-014 Glasgow Street - Phase 1 - Reconstruction The total budget for all phases of this project is $5,368,849.00 Estimated Cost for this Phase of Work Tender T13-014 costs, including HST 2,313,416.68 less: HST rebate on tender (230,113.20) Net Cost Being Awarded 2,083,303.48 A Costs Incurred to Date - Projected Costs: Staff Time/Permitting/Material Testing 229,514.00 Total Estimated Cost for this Phase of Work 2,312,817.48 C Budget for this Phase of Work Sanitary Utility 1,119,829.00 Storm Water Utility 559,914.00 Water Utility 754,667.00 Region of Waterloo (Raw Watermain Construction) 402,022.00 Total Budget for this Phase of Work 2,836,432.00 B Estimated Surplus/(Deficit) for this Phase of Work (B - C) 523,614.52 D Estimated Surplus/(Deficit) from previous phases 93,802.00 Total Estimated Surplus/(Deficit) 617,416.52 E Surplus is to be retained in the account to fund future project costs. COMMUNITY ENGAGEMENT: Not applicable ACKNOWLEDGED BY: Dan Chapman, Deputy CAO & City Treasurer, Finance and Corporate Services 1 iii) - 3