HomeMy WebLinkAboutINS-13-023 - Class Environmental Assessment for Strasburg Road Extension - New Technically Preferred Alignment
REPORT TO:
Special Planning & Strategic Initiatives Committee
DATE OF MEETING:
May 22, 2013
SUBMITTED BY:
Hans Gross,Director,AssetManagement ,519-741-2416
PREPARED BY:
Binu Korah, Manager, Development Engineering, 519 741
2974
WARD(S) INVOLVED:
Wards4 & 5
DATE OF REPORT:
May 10, 2013
REPORT NO.:
INS-13-023
SUBJECT:CLASS ENVIRONMENTAL ASSESSMENT (EA) FOR
STRASBURG ROAD EXTENSION FROM NORTH OF
STAUFFER DRIVE TO NEW DUNDEE ROAD(SOUTH
SECTION)NEW TECHNICALLY PREFERRED
ALIGNMENT (TPA)
RECOMMENDATION:
THAT the New Technically Preferred Alignment (W1) for the Strasburg Road Extension
from north of Stauffer Drive to New Dundee Road be approved; and further,
THAT staff be directed to prepare Preliminary Design for the New Technically Preferred
Alignment, complete the Environmental Study Report (ESR) and present the final ESRat
the October 21, 2013 Planning & Strategic Initiatives Committee meeting to endorse the
document for filing in the Public Record for the mandatory 30-day public review period.
BACKGROUND:
In April 2010, the City of Kitchener appointed SNC-
complete the Class Environmental Assessment for Strasburg Road Extension from north of
Stauffer Drive to New Dundee Road. In May 2012, staff presented a Draft Environmental study
for this project to Council and released it to the public for review and comments. Based on
comments received during the Draft ESR review period (May -September 2012), Council
determined that additional work was warranted to identify the Technically Preferred Alignment.
Further, Staff presented a report on November 27, 2012 (INS 12-084) with an additional Scope
of Work to address the public concerns and to complete the Class Environmental Assessment
for Strasburg Road Extension from North of Stauffer Drive to New Dundee Road. In accordance
with the approved scope of work, the Project Team currently selected aNew Technically
Preferred Alignment for this project.
1 - 1
REPORT:
This report summarizes the results of work conducted between December 2012 and May 2013.
Evaluation Criteria:
Based on public and agency comments since the May 2012 publication of the draft
Environmental Study Report (ESR), the Project Team proposed revisions to the Evaluation
Criteria, which were presented to Council through a workshop on February 4, 2013. The
objective of the workshop was to receive input from members of Council for their preferences
with respect to the scope and importance of the various evaluation criteria. Once a consensus
from Council as a whole was reached on the Evaluation Criteria and the associated importance,
this information was communicated back to the Project Team.
Table 1 presents the Evaluation Criteria used for completing the comparative assessment of the
alignment alternatives. Criteria that are new or modified from those used in the 2011
assessment of alignment alternatives are identified as such. Additional details on the rationale
for the Evaluation Criteria are provided in Appendix A.
Table 1: Proposed Alignment Alternatives Evaluation Criteria
FACTOR GROUP/FACTOR
1. NATURAL ENVIRONMENT
1A. Terrestrial Ecosystems
1B. Aquatic Ecosystems
1C. Groundwater Resources
1D. Surface Drainage
1E. Species at Risk Permits [NEW]
2. SOCIO-ECONOMIC ENVIRONMENT
2A. Land Use Policy [MODIFIED]
2B. Existing Land Use [MODIFIED]
2C. Communities
2D. Noise
3. CULTURAL ENVIRONMENT
3A. Archaeological Resources
3B. Built Heritage Features [MODIFIED]
3C. Cultural Heritage Landscapes [MODIFIED]
4. TRANSPORTATION/UTILITIES
4A Transportation Network/Infrastructure
4B. Municipal Services and Utilities
5. FINANCIAL/TECHNICAL
5A. Financial
5B. Technical
On February 22, 2013, the Project Team finalized the revised Evaluation Criteria based on input
from Council. The full set of Evaluation Criteria used to assess the advantages and
disadvantages of the alignment alternatives under consideration is presented in Appendix A.
Comparative Assessment:
Acomparative assessment was completed by the Project Teamfor the seven (7) alignments
using the revised Evaluation Criteria. The alignmentsincludefiveshort-listed alternatives (E1,
E2, E3, E4, C2 and W1), the Technically Preferred Alignment(E4 Modified) from the April 2012
Draft ESR, and(W2 Modified) (See attached Appendix B).
1 - 2
The Consultant Team further developed a detailed evaluation matrix and assessed the seven
alignment alternatives. The results of the detailed assessment were provided to the Project
Team in the form of reference documents in mid-March 2013. A Project Team workshop was
held on March 27, 2013, wherein the detailed assessment was presented to the Project Team
by various Consultant Team discipline specialists to ensure that all Project Team members
gained a full appreciation of the potential advantages and disadvantages associated with the
alignment alternatives. The identified advantages and disadvantages were then scored by the
full Project Team and around table discussion ensued to select the New Technically Preferred
Alignment (TPA).
Following is the summary of the comparative evaluation that was used to arrive at the selection
of the New TPA.
Alignments were scored by assigning a score of 10 to the alignment that best meets the project
objectives or would create the fewest adverse impacts, and indexing the remaining alignments
against the preferred alternative for each Factor (maximum score of 10; minimum score of 1).
Factor scores were averaged to arrive at a normalized score for each Factor Group, because
there are a different number of factors in each Factor Group.The Consultant Team presented
the initial scoring for each Factor/Factor group, which was then adjusted based on the
aforementioned round table discussion by the Project Team.
Natural Environment:
W1 is the preferred option with respect to potential impacts to natural heritage features
(terrestrial/aquatic) because it avoids crossings of the Blair Creek corridor (including the
significant woodlot at the west end, wetlands (including Provincially Significant Wetland),
Species at Risk (SAR) regulated habitat, regulated floodplain area, and the locally
sensitive groundwater recharge/discharge area. It overlies the Regional recharge area
and a small portion of a Wellhead Protection Area (Level 4), it will not interfere with an
active well, and is the furthest alignment from areas identified as a future Regional
groundwater source zone. It would also create less of a barrier to wildlife movement
because it does not cross contiguous natural features associated with the creek corridor.
E2 and C2 are the least preferred due to large (E2), or multiple crossings (C2) of the
Blair Creek corridor, which result in higher impacts to wetlands, aquatic habitat, wildlife
passage, and SAR habitat. E2 does not fall within a WPA, but will impact local recharge
discharge conditions and is close to an active well.
W2 Modified and E4 Modified have the shortest crossings of the Blair Creek corridor
which minimizes impacts to natural heritage features. W2 Modified has a shorter
crossing but is closer to high quality wetland communities. These shorter crossings
decrease groundwater impacts relative to other alignments; however, W2 Modified
overlies both the Regional and local recharge zones, and still requires crossings of the
PSW and has higher impacts than W1.
E3 and E4 have lower impacts to natural heritage features than E2 and C2 due to
narrower crossings of the Blair Creek corridor. E3 is preferred to E4 in this regard.
These alternatives are similar to E2 from a groundwater perspective.
W1 is preferred from a Species at Risk Permit perspective, as it avoids regulated habitat
for Jefferson Salamander. All other alternatives would necessitate securing an
Endangered Species Act permit from MNR for crossing this regulated area. C2 is
considered worst from this perspective, as it would also eliminate high quality potential
habitat.
Socio-Economic Environment:
With respect to land use policy, significant weight was attached to compatibility with the
-rural boundary,
1 - 3
and the potential for the new Strasburg Road alignment to create pressure for westerly
expansion of the urban envelope into the Protected Countryside.Alignment E2 exhibits
the highest degree of compatibility with land use policies, since it is closest to the
existing boundary, but is not much different than Alignments E4/E4 Modified in this
respect. Alignments E3 and C2 exhibit similar degrees of compatibility, while Alignments
W2 Modified and W1 exhibit a low degree of compatibility (potential for relatively
significant to very significant relocation of the urban envelope).
Alignment E2 imposes the least impacts to prime agricultural lands and agricultural
operations, and is the preferred option. However, the East alignments impose the most
impacts on the B&B business at 500 Stauffer Drive. Conversely, Alignment W1 imposes
the least impacts on the B&B business at 500 Stauffer Drive, but would result in the
greatest impacts to agricultural resources and operations. Potential impacts to the
planned development at the northeast corner of Reidel Drive and New Dundee Road are
not considered to be significant or different across the alignments. Alignment C2
represents the best balance of impacts to existing and approved future land use.
Alignment E2 would require the least private property and exhibits the highest degree of
compatibility with planned community boundaries (Brigadoon, Doon South Phase 2).
Alignments E3 or E4/E4 Modified represent the best opportunities for maintaining or
enhancing community connectivity, when considering retaining the existing Reidel Drive
corridor as part of the future Doon South trail system to enhance connectivity (see also
Cultural Environment Summary).
Background noise will increase in the study area due to natural growth in traffic. W1 is
the preferred option acoustically (only one sensitive receptor would experience
significant noise increases), but there are few receptors in the study area. Key receptors
are the residences at 500 Stauffer Drive and 271 Reidel Drive, and Alignments E2 and
E4/E4 Modified would create the most significant impacts to these locations.
Overall, Alignment E4 or Alignment E4 Modified is the preferred alternative from a socio-
economic perspective.
Cultural Environment:
W1 is the preferred option with respect to potential impacts to archaeological resources
because it avoids the most areas with indicated archaeological potential near the Blair
Creek corridor. E2 is the least preferred option because of its high impact to features
indicating archaeological potential (e.g. watercourses, identified archaeological sites).
C2 impacts the largest area of indicated archaeological potential; however, it impacts
fewer features indicating archaeological potential than E2.
W1 is the preferred option with respect to potential impacts to cultural heritage resources
because it avoids all four heritage roadscapes, the farm complex located on the existing
Reidel Drive corridor, and minimizes impacts to CHL 7 and the designated heritage
resource at CHL 2, which are located north of Stauffer Drive.
W2 Modified is the next preferred option given that it avoids the four identified heritage
roadscapes, and minimizes impacts to CHL 1, CHL 2 and CHL 7 (impacts are limited to
the disruption of fields).
C2 will result in lower impacts to CHL 2, a designated heritage resource, and to CHL 3
and CHL 4, scenic-heritage roadscapes. It will, however, negatively impact CHL 5 and
CHL 6 through full and partial removal, and disrupt significant views associated with
CHL1.
E2, E4 and E4 Modified are the least preferred options given their disruption to
landscape elements and associated views to and from CHL 2; disruption to landscape
1 - 4
elements associated with CHL 1; and disruption to roadscapes at CHL 3, CHL 4 and
CHL 5. Further, E2 will result in removal of CHL 6.
Alignments C2, W1 and W2 Modified will result in the extension of connector roads
through the southern fields associated with CHL 1, and the northern fields associated
with CHL 2 and CHL 7. The Robert Ferrie Drive extension, in particular, has the potential
to disrupt cultivated fields and hedgerows associated with CHL 2, as well as obstruct
significant views from the farmstead to the woodlot and fields.
Transportation/Municipal Services and Utilities:
E2 is the preferred option with respect to compliance with transportation/municipal
services policies, and also shows the highest projected use for passenger vehicle and
public transit usage. The use of existing Reidel Drive makes this preferred from a
servicing perspective as well.
E4, E4 Modified and C2 are only slightly less preferred options in these regards, due to
partial use of the existing Reidel Drive corridor, with E4 being more consistent with
transportation/municipal services policy. E4 Modified requires additional length of
watermain compared to E4, and is therefore scored slightly lower than E4 for the
Municipal Services/Utilities factor.
E3 and W1 and W2 Modified are the least preferred options, since their distance from
existing infrastructure reduces projected usage by passenger vehicles and transit users
and reduces demand/connectivity for services/utilities, while increasing new
infrastructure requirements.They also create the need for a staggered crossing of New
Dundee Road (to Cameron Road) via an additional intersection not required by the other
alignments that meet New Dundee Road at the existing intersection of Reidel Road and
New Dundee Road. E3 provides just minimal acceptable spacing between the existing
and new intersections, while W2 Modified and W1 provide reasonable spacing, but all
three cause north--west across New Dundee Road,
increasing volume and local traffic operations delay in the New Dundee Road corridor.
Technical and Financial:
E4 Modified is the preferred option from a financial perspective, with the lowest capital
and operational costs, followed closely by E4. Alignments E3, C2 and E2 have higher
capital and operational costs. W1 and W2 Modified have the highest capital and
operational costs, with W2 Modified the least preferred option financially.
The cost of mitigation for crossing Jefferson Salamander habitat varies, ranging from 0%
to 2.5% of overall capital costs. W1 has no mitigation costs (i.e., complete avoidance of
the regulated area), and E2 has the highest mitigation cost, since its alignment has the
longest crossing of the Jefferson Salamander regulated area. The cost of mitigation
does not affect the ranking of the overall capital costs.
Although all options are technically feasible, W1 is the easiest to construct from a
technical perspective due to the avoidance of large watercourse crossing structures and
of crossing of wetland areas, as well as reduced vegetation clearing requirements. C2
and E2 are the least preferred options due to their respective requirements for multiple
watercourse crossing bridge structures and multiple span bridge structures. C2 is
scored slightly higher than E2 due to its simpler road geometry.
Refer toAppendix Cfor the final scoring summary.
New Technically Preferred Alignment (TPA):
Alignment W1 received the highest scores from the Project Team. As a result of the Council
input session and in accordance with the recommendation of the Project Team, the Factor
Groups were considered to be of equal importance and therefore received equal weighting
1 - 5
during the scoring of the alternative alignments. It represents an acceptable balance of
advantages and disadvantages across the spectrum of evaluation criteria and is being carried
forward for presentation to stakeholders as the New Technically Preferred Alignment (See
attached Appendix D).
Rationale for selection of Alignment W1:
Avoids natural heritage features, including wetlands, forests, streams and fish habitat,
wildlife passage areas, groundwater recharge areas, regulated floodplain
Avoids regulated SAR habitat and significant challenges associated with obtaining an
Endangered Species Act permit
Results in the least significant impacts to owner-occupied residence and bed and
breakfast business at 500 Stauffer Drive
Results in the lowest noise impacts
Avoids cultural heritage features (roadscapes); limited impacts to other cultural heritage
features (farm complexes)
Provides the desired spacing between the new intersection on New Dundee Road and
the existing Reidel Drive-Cameron Road intersection
Is physically the easiest option to construct
COMMUNITY ENGAGEMENT:
As part of this Class EA project, four(4) Public Information Centres were conducted to provide
the public, agencies, stakeholders, interested and affected parties with an opportunity to review
and comment on the study findings including preferred alternative, along with the other
alternatives considered. The direct mail-outs, along with the newspaper advertisement advising
the public and property owners of the project commencement and the Public Information
Centres, provided a project overview, as well as contact names and information for those
interested.Furthermore,there were many project meetings conducted to discuss specific
issues with stakeholders and affected landowners. The City staff andconsultant also presented
the study findings to the Environmental committee and Heritage committee to obtain their
valuable input. Public Information Centre No. 4 was held within the time period covered by this
report.
Public Information Centre (PIC) No. 4 was held on Wednesday, April 24, 2013, where
approximately 95people attended and written comments were received from 59 people. The
response to the selection of alignments W1 as the New TPA was generally positive.
The purpose of the PIC was to present the new set of alternative alignments, their evaluation,
and identification of the New Technically Preferred Alignment. Public comments were
requested by May 8, 2013. Once all the comments are received and addressed, as appropriate,
the Project Team will prepare a revised Environmental Study Report for Council endorsement in
October 2013 and file the document with the Ministry of Environment for the 30-day mandatory
public review period.
FINANCIAL IMPLICATIONS:
The total cost estimate for the new technically preferred alignment (W1) of Strasburg Road and
associated infrastructure, which includes local road extensions/upgrades and a watermain, is
$22M. The Strasburg Road portion of the project is approximately $8M and exceeds the cost
estimate included in the current capital forecast by $2M. Any additional cost will be included in
the upcoming 2014 Development Charge Background Study and will either impact the
development charge rate or require a deferral of other projects.
1 - 6
ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN:
The Strasburg Road Extension project is aligned with the City of Kitchener Strategic Plan; refer
to Strategic Plan document, community priorities Development sections 1 & 3. Further, this
project is also one of the priority projects identified in the Kitchener Growth Management Plan,
as it provides service to lands identified as Priority B
CONCLUSION:
In accordance with Class Environmental Assessment process together with studies and detailed
assessment completed by the Consultant Team, the Project Team has selected a New
Technically Preferred Alignment for the Strasburg Road Extension from north of Stauffer Drive
to New Dundee Road.
There were several Public Information Centres andother consultation process mechanisms
used to solicit stakeholder input from April 2010 to May 2013 to review the detailed study
findings and receive comments onthis project. As part of the Class EA process, staff also met
with various agencies and affected property owners. In conclusion, staff recommend that the
New Technically Preferred Alignment (W1) for the Strasburg Road Extension from north of
Stauffer Drive to New Dundee Road be approved. Further, it is recommended that staff be
directed to prepare Preliminary Design of the New Technically Preferred Alignment, complete
the Environmental Study Report (ESR) and present the final ESR at the October 21, 2013
Planning & Strategic Initiatives Committee meeting to endorse the document for filing in the
Public Record for the mandatory 30-day public review period.
ACKNOWLEDGED BY:Pauline Houston, DCAO Infrastructure Services Department
1 - 7
Appendix A: Evaluation Criteria
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Impact to regulatory flood plain of Blair Creek (including need for GRCA work
-
permit)
-
-
-
-
-
1 - 8
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
1 - 9
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
1 - 10
Appendix B: Alignment Alternatives
1 - 11
Appendix B: Alignment Alternatives
East 2 [E2]
Diverges from Official Plan alignment at north end of farm/B&B operation at 500 Stauffer Drive
Skirts east side of farm/B&B operation pond and west side of Stauffer Woods (ESPA 33)
Connects to Reidel Drive 325 m south of Stauffer Drive and runs along existing Reidel Drive
corridor to New Dundee/Reidel Drive intersection
East 3 [E3]
Diverges from Official Plan alignment at north end of farm/B&B operation at 500 Stauffer Drive
Skirts east side of farm/B&B operation pond and west side of Stauffer Woods (ESPA 33)
Crosses narrowest point of Blair Swamp PSW
Connects to New Dundee Road 250 m west of Reidel Drive to improve intersection sight
distances compared to existing New Dundee/Reidel intersection
East 4 [E4]
Diverges from Official Plan alignment at north end of farm/B&B operation at 500 Stauffer Drive
Skirts east side of farm/B&B operation pond and west side of Stauffer Woods (ESPA 33)
Crosses relatively narrow point of Blair Swamp PSW
Swings east behind farm buildings at 271 Reidel Drive
Intersects New Dundee Road at an angle compatible with opposing Cameron Road leg
East 4 [E4] Modified previously identified as the Technically Preferred Alignment
Similar to E4 north of Stauffer Drive
Crosses narrowest point of Blair Swamp PSW (similar to E3)
Swings east behind farm buildings at 271 Reidel Drive and rejoins E4 to intersect New Dundee
Road at an angle compatible with opposing Cameron Road leg
Central 2 [C2]
Diverges from Official Plan alignment at north end of farm/B&B operation at 500 Stauffer Drive
Straddles Lot 9/Lot 14 Concession BT property line to south limit of farm/B&B operation
Connects to Reidel Drive corridor 625 m south of Stauffer Drive, and runs along existing Reidel
Drive corridor to New Dundee/Reidel Drive intersection
West 1 [W1]
Diverges from Official Plan alignment at north end of farm/B&B operation at 500 Stauffer Drive
Skirts west edge of most significant groundwater recharge area and upper Blair Creek corridor
Coincident with west boundary of lands in Lot 5 Con BNS south of Blair Creek
New intersection with New Dundee Road 720 m west of existing Reidel Drive intersection
West 2 [W2] Modified adaptation of original Alignment W2
Diverges from Official Plan alignment near north end of farm/B&B operation at 500 Stauffer Drive
Crosses Blair Creek just east of major woodlot at west end of creek corridor
Swings slightly east and then straight south to a new intersection with New Dundee Road 400 m
west of existing Reidel Drive intersection
Note:
The assessment of alignment alternatives west of Alignment E2/E3/E4 north of Stauffer Drive and
west of existing Reidel Drive has assumed that future Robert Ferrie Drive and future Blair Creek Drive will
be extended to connect to future Strasburg Road in order to achieve local road network connectivity. The
alignments shown for these collector roads are the best estimate of their possible location. The impacts of
these extensions have been included in the assessment of alternative alignments for Strasburg Road.
The future extension of Robert Ferrie Drive will be subject to a separate environmental assessment under
the Municipal Class EA process, or as part of the Plan of Subdivision approval process.
1 - 12
Appendix C: Final Scoring Summary
FACTORALIGNMENT ALTERNATIVE
E4 W2
E2E3E4C2W1
ModMod
1. NATURAL ENVIRONMENT
1A. Terrestrial Ecosystems56674107
1B. Aquatic Ecosystems46564108
1C. Groundwater Resources76793107
1D. Surface Drainage89998107
1E. Species at Risk Permits22221102
Natural Environment Score5.205.805.806.604.0010.006.20
2. SOCIOECONOMIC ENVIRONMENT
2A. Land Use Policy10699513
2B. Existing and Approved Land
65661077
Use
2C. Communities981010648
2D. Noise24335108
Socio-Economic Environment
6.755.757.007.006.505.506.50
Score
3. CULTURAL ENVIRONMENT
3A. Archaeological Resources24444104
3B. Built Heritage44245109
2C. Cultural Heritage
25346109
Landscapes
Cultural Environment Score2.674.333.004.005.0010.007.33
4. TRANSPORTATION/MUNICIPAL SERVICES AND UTILITIES
4A. Transportation
10799956
Network/Infrastructure
4B.Municipal Services and
10698745
Utilities
Transportation/Municipal
10.006.509.008.508.004.505.50
Services & Utilities Score
5. FINANCIAL/TECHNICAL
5A. Financial57910643
5B. Technical57786107
Financial/Technical Score5.007.008.009.006.007.005.00
TOTAL SCORE29.6229.3832.8035.1029.5037.0030.53
RANK5732614
% BEHIND FIRST RANKED
20211152017
ALIGNMENT
E4 W2
E2E3E4C2W1
ModMod
1 - 13
Appendix D: New Technically Preferred Alignment
(TPA)
(Alignment W1)
1 - 14