Loading...
HomeMy WebLinkAboutINS-13-083 - Scope Increase for Purchase Order T12-069 - Bramm Yards Development - 55 Bramm Street REPORT TO: Finance and Corporate Services Committee DATE OF MEETING: September 9, 2013 SUBMITTED BY: Justin Readman, Director, Transportation Services, 7038 PREPARED BY: Paul A. McCormick, Manager, Parking Enterprise, 7155 WARD(S) INVOLVED: 9 DATE OF REPORT: 2013-26-09 REPORT NO.: INS-13-083 SUBJECT: Scope Increase for Purchase Order T12-069-Bramm Yards Development (#55 Bramm Street) RECOMMENDATION: That a $184,000, plus H.S.T. increase to the existing purchase order T12-069 with Network Sewer and Watermain Ltd., Cambridge Ontario, referenced in report FCS-12-185 be approved. BACKGROUND: Council approved the recommendations and opportunity for the development of temporary public parking in the Bramm Street Yards upon relocation of the City Operations to the Kitchener Operations Centre as presented in report DTS-10-110 on May 17, 2010. Development costs were estimated at approximately $500,000 for Lot A and Lot B. Funding for the development was taken from the $500,000 EDIF allocation for Digital Media and would be repaid with interest from net parking revenues. City Operations occupied the Bramm Street location until 2011 when it relocated to the Kitchener Operations Facility on Goodrich Drive. In 2010 the project scope included demolition of the main building, environmental work, new light standards and related underground infrastructure, concrete curbs, sidewalks, asphalt repairs and replacement, and landscaping to the City’s standard for parking lots in the core. The original scope was for the development of the two most northerly areas of the site with redevelopment of the larger southerly portion at a later date, as demand increased. However, operations required the continued use of the most northerly area for snow melting. This required a scope change and increased the size of the initial phase of the development resulting in a tender value of $785,508.16 plus HST. . Council approved the recommendations to award Network Sewer and Watermain Ltd. a contract in the amount of $785,508.16 plus H.S.T. to complete the redevelopment of the temporary public parking in the Bramm Street Yards. (Report FCS-12-185 on November 6, 2012). 4 - 1 REPORT: The current contract value with Network Sewer and Watermain Ltd. will exceed the original purchase order value of $785,508.16, plus H.S.T. The new total is projected to be $969,509, an increase of $184,000 plus H.S.T. The overage is a result of the following: Item Description Amount Scope of Work Changes Continuous pedestrian sidewalk along after awarding contract Bramm Street Frontage Crime Prevention Through Environmental Design (CPTED) recommendations Chain link fence o Securing existing salt shed o $28,000 Blue light emergency phone stations – o the conduit has only been installed at this time Creation of additional barrier free parking spots to meet newly introduced Accessibility for Ontarians with Disabilities Act (AODA) requirements Asphalt changes (see Quantities below) Unanticipated Disposal of waste sludge from an old Environmental underground storage tank (UST) Conditions Additional excavation costs to remove an old underground concrete bunker discovered on site $55,000 Trenching for new lighting system uncovered some contaminated soil that needed to be relocated Additional quantities of Contaminated soil discovered while trenching granular and asphalt for lighting system could not be reused and $101,000 material was replaced with granular materials To obtain necessary grading levels, additional gravel was need to cover the existing concrete floor The condition of the existing pavement which was to receive a new overlay of asphalt was worse than anticipated and needed to be replaced Scope of work changes - Extra asphalt required to complete Park Street entrance, the perimeter along the railway tracks and south edge of property Total$184,000 4 - 2 FINANCIAL IMPLICATIONS: This project is funded by EDIF. An increase in the value of the contract with Network Sewer and Watermain Ltd. will result in a longer payback period of time. The original payback was estimated to be approximately 3 years. The additional cost will increase the payback period by approximately 6-12 months. Bramm Street Yards Development Approved Projected Difference Tender T12-069 costs including HST $887,624$1,095,545 $207,920 Less: HST rebate on tender ($102,116)($126,036) ($23,920) Net Cost $785,508$969,509 $184,000 The additional tender costs associated with this recommendation are proposed to be funded from the EDIF Employment Land Allocation ($37.3K), EDIF Studies ($36.7K) and the Environmental Remediation fund ($110K). ACKNOWLEDGED BY: Pauline Houston, Deputy CAO Infrastructure Services Department 4 - 3