HomeMy WebLinkAboutCSD-13-099 - ION Corridor Streetscape Design Priorities
REPORT TO:
Planning & Strategic InitiativesCommittee
DATE OF MEETING:
September 30, 2013
SUBMITTED BY:
Alain Pinard, Director of Planning
PREPARED BY:
Janine Oosterveld,Manager, Site Development & Customer
Service(519-741-2200ext. 7076)
WARD(S) INVOLVED:
Wards 3, 9 &10
DATE OF REPORT:
September 19,2013
REPORT NO.:
CSD-13-099
SUBJECT:
ION (RAPID TRANSIT) CORRIDORSTREETSCAPE
DESIGNPRIORITIES-ADDITIONAL INFORMATION
RECOMMENDATION:
For information
BACKGROUND:
This report has been prepared as follow-up to Report CSD-13-093 which made Council aware
of on-going discussions between City staff andth
streetscape priorities along the ION LRT corridor.The Rapid Transit team has advised that an
opportunity exists to incorporate final changes by addendum to the RFP for the Design Build
Finance Operate Maintain (DBFOM) contract prior to submission of bids later this year.
Decisions regarding what will, and will not, be within the scope of the final RFP must be made
by the end of September.
REPORT:
Process of Coordination
CSD-13-093, staff has continued discussions with the
Rapid Transit team on the streetscape priorities identified in that report and provide the following
updates:
(1) Pedestrian-scaled lighting
The Rapid Transit team has committedto incorporate pedestrian-scaled lighting at each ION
Station Stop platform.They also provided an estimate for the cost of adding the infrastructure
needed to install future pedestrian-scaled lighting beyond the Station Stop platform.Refer to
Appendix A regarding incremental cost options for pedestrian-scaled lighting along the corridor.
Staff is not recommending that Council fund the incremental cost of this infrastructure because
capital funding could not be identified to accommodate the expenditure. Staff note, however,
that the provision of pedestrian-scaled lighting at each Station Stop platform is a positive
advancement in the baseline design and support this addition.
8 - 1
(2) Enhanced pedestrian crossings
The Rapid Transit team has committed to incorporating an alternative crossing treatment to
ladder striping for intersections associated with ION Station Stops including the King
Street and Victoria Street intersection. In evaluating the intersections that staff deemed
s commitment are identified:
Charles Street at Madison Street (at Cameron Heights Collegiate Institute), located one
block east of the Cedar Street ION Station Stop; and,
Courtland Avenue at Hillmount Street, located at the western end of the Block Line Road
ION Station Stop where pedestrian access to the Station Stop is currently not proposed.
Given that the majority of crossings recommended for enhanced pedestrian crossings areat the
Station Stops, staff is generally satisfied with how this streetscape priority will be addressed and
will continue to discuss solutions with the Rapid Transit team with respect to the two remaining
intersections.
(3) Hydro substation integration
The Rapid Transit team has committed to proceeding up-front to pre-submission consultation for
the hydro substation site plans, with a commitment to context-sensitive design for the three
most prominent hydro substations. Major upgrades at these three substations could include
cladding such as brick or spandrel panels and a pitched roof, as appropriate for the respective
neighborhood.The formal Site Plan approval process will proceed after the DBFOM contract
has been awarded.At the time of writing this report, the Rapid Transit team has been made
hydro substations but has not yet determined an appropriate public consultation strategy.
(4) Sidewalks
No additional updates to report with respect to sidewalks. For sidewalks directly adjacent to the
street, the Rapid Transit team has clarified that the sidewalk width shall be no less than 1.8 m,
including the maintenance strip. The design will meet AODA (Accessibility for Ontarians with
Disabilities Act) standards and where opportunities exist, the baseline design includes a wider
sidewalk.
(5) Cycling infrastructure
The Rapid Transit teamhas confirmed thatline paintingwill be incorporated along the corridor,
wherethe pavement width allows, for the informal accommodation of cyclists. The striping will
not be formally identified as a cycling lane in order toprovideadequate pavement widths for
emergency service vehicles.
(6) Connectivity
One of the key connectivity elements discussed is a recommended sidewalk or multi-use trail on
the south/west side of Courtland Avenue. With the exception of a pedestrian connection to the
ION Station Stop at Block Line Road, the Rapid Transit team is not proceeding with additional
pedestrian/cycling linkages at this location through the RFP due to constraints associated with a
creek crossing and slope issues.
(7) Streetscape furnishings and landscaping
No further updates to report with respect to streetscape furnishings and landscaping. These
items are not part of the DBFOM contract, further discussions are expected at a later phase in
the project.
8 - 2
FOLLOW-UP TO COUNCIL QUESTIONS:
At the time of report w
th
raised at the September 9 CIS Committee meeting. Appendix B includes responses to
questions received to date.
CONCLUSIONS:
Of the streetscape priorities that staff identified, the Rapid Transit team has been able to
accommodate alternative crosswalk delineation and pedestrian-scaled lighting at the ION
Station Stops within the RFP. They are also committed to undergoing Site Plan review for the
hydro substations with upgrade considerations at prominent locations. On-going discussions
with the Rapid Transit team have been productive in working through many streetscape
priorities. Because staff is not able to identify any available capital funding sources to contribute
to the scope of the RFP contract at this time, no recommendations are included in this report
with respect to pedestrian-scaled lighting infrastructure.Should Council chose to fund upgrades
for pedestrian-scaled lighting infrastructure, a direction to staff to proceed with a memorandum
th
of understanding with respect to cost-sharing would be needed at the September 30 meeting
in order to meet Regional timelines.
COMMUNITY ENGAGEMENT:
The community providing public
access to Committee agendas and reports. The Region has also held a number of public
consultations on the topic of rapid transit throughout the planning of the rapid transit corridor
including the Environmental Assessment phase, Community Building Strategy and the ION
Station Stop design concepts. This report follows the inform strategy of the Community
engagement continuum- to provide the public with information to assist them in understanding
how design considerations are being addressed in the ION RFP process.
ACKNOWLEDGED BY:
Michael May,Deputy CAO
Community Services Department
Attachments:
Appendix A. Pedestrian-scaled lighting details
Appendix B. Response to questions
8 - 3
APPENDIX A- Pedestrian-scaled lighting cost implications
Extent of WorkIncremental Cost to City
Entire Corridor.
Midpole fixture added to street light poles
$1,004,000
Within a block of each Station Stop.
Midpole fixture added to $662,000
street light poles
Infrastructure only within a block of eachStation Stop.
$350,000
Midpole cut-out and supporting conduit added to street light
poles
Note that in some areas of the corridor with narrow rights-of-way such as Duke and Charles
Streets, street lights are only situated on one side of the street. Additional costs would be
incurred to establish pedestrian-scaled lighting on the opposite side of the street at
approximately $7000 per pole.
8 - 4
Appendix B.Responses to questions
th
The following are responses to questions raised at the September 9 CIS Meeting as available
at the time of report writing:
1. Substations:
a. Noise and vibration. Regional staff has reviewed studies which indicate that no
audible noise beyond the ambient noise would be detected from these facilities.
No noticeable vibration will be detected from these facilities.
b. Hydro-substations could be integrated into a future redevelopment (e.g. parking
structure)
2. Heated Sidewalks (for snow melting) The Rapid Transit team indicated that this
upgrade would be cost-prohibitive within the scope of the RFP.
3.Wi-Fi Availability will be considered as part of a broader Regional initiative at a future
date.
4. Addressing AODA requirements, particularly as it relates to individuals with visual
impairments. The corridor design will meet AODA requirements.
5. Separation of cycling facilities. The Rapid Transit team indicated that limitations in
available right-of-way width would limit opportunities to separate cycling facilities along
the corridor as part of the ION construction.
8 - 5