Loading...
HomeMy WebLinkAboutINS-13-094 - Victoria Park Washroom Project - Update IIStaff Rep►�►r I r Infrastruc�ture5ervrresDepartment wvwuukitchenerra REPORT TO: Council DATE OF MEETING: October 7, 2013 SUBMITTED BY: Cynthia Fletcher, Director — Facilities Management- 741- 2600 x 4424 PREPARED BY: Doug Hergott, Manager - Facilities Management — 741 -2600 x 4684 WARD(S) INVOLVED: All DATE OF REPORT: October 3, 2013 REPORT NO.: INS -13 -094 SUBJECT: VICTORIA PARK WASHROOM PROJECT — Update II RECOMMENDATION: For information. BACKGROUND: On September 30, 2013, staff was asked to bring back a report to review the potential to implement this project in 2 phases, with the desire to accomplish a project and retain at least some of the CIIF allocation. The concept of phasing the project would entail pouring the slab before the frost season and changing the design /scope of the above grade components to reduce the overall project costs. As noted previously, it is already challenging to meet the timelines of the CI IF program, as construction will be done during the winter months. Any further delay in the project will require the City to pay a premium on slab construction or move the project onset to the spring. The first stage of this project involves pouring a slab within the frost level. In order for the slab to cure properly, 28 days of good conditions is required. Winter /frost conditions are not ideal and extra measures and potential extra curing time would be needed as we get further into the fall. The proposed phasing of the project is intended to get the slab poured before frost season. This proposal will require setting the foot print of the building, as services need to be placed as part of the slab pour. There will not be an option to reduce the size or configuration of the building once the slab is poured. As time continues to pass, there may be a need to heat a slab that is poured. Staff was also asked to review "less expensive" building materials to get the project completed. The intention is to reduce the cost of the overall construction project, even if we have to "phase in" heritage aspects or compromise durability /increase operating and ongoing maintenance. 8 a. -1 REPORT: Staff enlisted the design consultant to review the following ideas, which do not affect the foot print of the building and corresponding services within the building: Component Potential Benefit Risk(s) Saving • eliminate $25,000 Cost savings for • will require heritage review entrance porch the construction • removes skate changing area project • will be more costly to add later • redesign of remaining roof would be required • installing asphalt $3,000 - $5,000 Cost savings for walkway verses the construction concrete project walkway • install asphalt $13,000 Cost savings for • may not meet heritage shingles, instead the construction requirements of cedar project • future cost to add later • substitute brick $4,100 Cost savings for • may not meet heritage OR the construction requirements project • put siding $47,700 Cost savings for • will not meet standards for instead of brick the construction durability as a park building. A on the building project residential type of construction requires changing is not suitable for a public the wall assembly building where the intended use to typical is washrooms. Commercial residential not construction is required to commercial ensure longevity of the asset construction and reduced liability to the City (siding, stud, for its function. insulation, drywall) • will result in increased maintenance and capital repair Typically, fixtures costs. ie a drywall are hung from interior /exterior siding will not block walls for stand up to graffiti removal, ease of wear and tear, vandalism. Staff maintenance. will incur regular repairs, Staff will need to replacements, rebuilds of walls ensure residential and finishes. grade walls are Anticipated additional annual reinforced properly Costs for Security, Pest Control to handle this type and Maintenance Response: of construction $15,000 labour and materials (which will add above the regular anticipated cost) costs. The estimate is based on monthly response to replace/rebuild portions of the 8a. -2 Because these changes would result in "significant alteration of original scope ", staff are faced with the following challenges: 1. The new design will require Heritage Kitchener Committee Approval, with the following timelines: • October 25th — Heritage Permit Application submission deadline, • November 17th — Staff Report on HPA is due to Manager /Director, • November 19th — Heritage Kitchener agenda setting, • December 3rd — Heritage Kitchener meeting Staff could take the re- scoping of this project to the Heritage Kitchener Meeting on Nov 5th for general discussion (no formal HPA but to receive first impressions /comments on possible alternatives), the deadline for information to be included in the agenda is October 22nd 2. One new quotation package (installation of the slab) and one new tender package (specifications and drawings) will need to be developed and full tender process introduced. This work will come with additional costs. Quotation: Installation of the slab • October 8th- October 18th — confirmation of specifications and drawings for services and building foot print • Oct 21- 24 — 3 quotations received and quotation finalized /awarded • Oct 25 -Nov 29 — permits, locates and installation of the services & slab • Month of Dec: slab to cure (frost season, slab will need to be heated) Tender for re- scoped building • October 8 -25th ; drawings and specifications revised and finalized • October 28th: begin approval processes: 8a. -3 building or finishes. Standard graffiti removal processes will not work as well on siding /drywall vs brick /block and will degrade the material faster. Drywall construction is susceptible to mold and pest/rodent infestation vs brick /block construction and not recommended for commercial washroom construction. • will require Building and Fire approval • will not meet heritage requirements • we will not be able to "add heritage aspects" at a later date as this is a completely different wall construction ie we would only be able to add brick veneer not true brick in the future. Because these changes would result in "significant alteration of original scope ", staff are faced with the following challenges: 1. The new design will require Heritage Kitchener Committee Approval, with the following timelines: • October 25th — Heritage Permit Application submission deadline, • November 17th — Staff Report on HPA is due to Manager /Director, • November 19th — Heritage Kitchener agenda setting, • December 3rd — Heritage Kitchener meeting Staff could take the re- scoping of this project to the Heritage Kitchener Meeting on Nov 5th for general discussion (no formal HPA but to receive first impressions /comments on possible alternatives), the deadline for information to be included in the agenda is October 22nd 2. One new quotation package (installation of the slab) and one new tender package (specifications and drawings) will need to be developed and full tender process introduced. This work will come with additional costs. Quotation: Installation of the slab • October 8th- October 18th — confirmation of specifications and drawings for services and building foot print • Oct 21- 24 — 3 quotations received and quotation finalized /awarded • Oct 25 -Nov 29 — permits, locates and installation of the services & slab • Month of Dec: slab to cure (frost season, slab will need to be heated) Tender for re- scoped building • October 8 -25th ; drawings and specifications revised and finalized • October 28th: begin approval processes: 8a. -3 • Regional Heritage review (may be required — will depend on the significance of changes to the design) • Heritage Kitchener Dec 3, 2013 • Building /Fire • CPTED • Tender let following Dec 3 Heritage meeting (assuming we meet all requirements and no revision or re- reviews are required) • Tender closes Jan 2 • Tender review and report to Council week of Jan 6th • Tender to Council Jan 13th • Permits, insurance, bonding begins week of Jan 14th • Contractor mobilizes week of Jan 20th • Construction period approximately 6 -7 weeks to comply with CIIF. This timeline is not realistic as the original construction period following the slab curing was 3.5 -4 months Overall risks of the phased approach: • High risk that the tenders /quotes will come in higher than expected because of timeline • Unrealistic timeline to complete the building • Winter construction will lead to higher cost and could lead to schedule delays • The City may accomplish phase 1 (the slab pour), may not receive a tender within the allocation and then will be left with having to complete project regardless of cost. • High risk that the project will not be completed by the CIIF timeline and the City will lose grant funding anyway. • High risk the City may find itself in the role of the constructor in order to complete the project • High risk that warranties will be convoluted in a phased approach ie will have contractors install dependent components in a piece meal manner • Site safety and security will fall to the City between phases at an cost and risk of liability A phased approach to this project will not work, as the risks listed above are too great, the timelines are not realistic and will likely jeopardize a quality long term product. In order to achieve the intended goal of the proposed phased approach, which is to accomplish a project and retain at least some of the CIIF allocation, staff see only a couple of options; 1. Work with the lowest bidding firm on the tender on the complete project. 2. Move the start date of the project to the spring, following a re- tendering of the entire project. We have no guarantee that costs will be any different or that we will retain any funding from the CIIF program. The other option is to 3. Cancel project and reintroduce into capital forecast in a later year. There may be future funding opportunities to which the City could apply. ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN: Through a public engagement process, the need for dedicated public washrooms was affirmed and endorsed by Council. COMMUNITY ENGAGEMENT: 8a. -4 The concept and design for this project was reviewed through a consultation process with the Victoria Park working group, Heritage Kitchener and Grand River Accessibility Advisory Council (GRAAC). ACKNOWLEDGED BY: Pauline Houston, Deputy CAO- Infrastructure Services 8a. -5