HomeMy WebLinkAboutINS-13-090 - Margaret Ave Bridge Replacement - Project Timelines
REPORT TO:
Community and Infrastructure Services Committee
DATE OF MEETING:
October 21, 2013
SUBMITTED BY:
Barbara Robinson, Director, Engineering Services, x
PREPARED BY: Steve Allen, Manager Engineering Design and Approvals,
x7584
WARD(S) INVOLVED:
10
DATE OF REPORT:
October 15, 2013
REPORT NO.:
INS-13-090
SUBJECT:
Margaret Avenue Bridge Replacement – Project Timelines
RECOMMENDATION:
Information Only
BACKGROUND:
The City received a Draft Evaluation of the Margaret Avenue Bridge on June 13, 2013, which
recommended that the bridge be closed immediately. The bridge was closed within the hour.
Due to the significance
On June 26 staff received the Final Evaluation Report from AECOM.
of the recommendation, the City retained the services of a second structural
engineering consultant, Morrison Hershfield, to review and confirm AECOM’s
recommendations.
The Peer Review Report was received in July 2013. Morrison Hershfield concurred with
AECOM’s recommendations regarding the design and construction of the bridge, and the
possibility of abrupt failure. It also supported the decision to shut down the bridge to traffic and
pedestrians. Their final report was received in August.
On September 9, 2013, staff presented report INS-13-076 to the Committee and Infrastructure
Services Committee. It was resolved:
“That the recommendation to remove the existing Margaret Avenue Bridge in the near term and
initiate an Environmental Assessment to replace it, be approved, as outlined in Infrastructure
Services Department report INS-13-076; and,
That the reallocation of funds from existing federal gas tax sources for the removal of the
existing Margaret Avenue Bridge ($250,000) and the initiation of an Environmental Assessment
and predesign to replace it ($150,000), be approved, as outlined in Infrastructure Services
Department report dated INS 13-076; and,
5 - 1
That staff be directed to work towards identifying funding sources for a new bridge during the
2014 budget process; and,
That the Chief Administrative Officer or designate, be delegated the authority to approve the
tender for the removal of the Margaret Avenue Bridge, with a report to be provided on this
award at the next regularly scheduled Council meeting; and further,
That staff be directed to report back to the October 21, 2013 Community and Infrastructure
Services meeting, on a proposed project timeline and identified areas where processes can be
expedited to advance the construction schedule for the new bridge”.
The tender for the demolition of the bridge was advertised on September 18, 2013 and closed
October 3, 2013. Staff awarded the contract to Bel-Air Excavating and Grading on October 9,
2013. The demolition is scheduled to begin October 21, 2013 and be complete by December 2,
2013. The total cost of the award is $499.064.50 of which $107,350.00 is for the temporary gas
main support system.
REPORT:
In order to replace the Margaret Avenue, there are several distinct steps that are required.
1) Environmental Assessment & Preliminary Design
The Municipal Class Environmental Assessment document provides guidance on the
appropriate selection of the EA class. The class of EA required is largely dependent on the
bridge’s age and the cultural heritage value of the bridge. The appropriate selection of the class
is also a function of the complexity of the project and it is up to the proponent (the City) to
determine the appropriate class based on the specifics of the project.
The bridge is over 40 years old (constructed in 1959) and therefore meets the criteria of age to
trigger a schedule ‘B’ EA, however preliminary evaluations of the cultural heritage attributes
suggests that the structure does not have a high degree of heritage value. This suggests a
schedule ‘A’ Class EA is appropriate.
Staff intend to complete the EA as a schedule ‘A+’ which has more public notification
requirements than an ‘A’ (which has no public notification requirements). EA related
requirements can be completed in conjunction with the detailed design, therefore there is no
additional time required for an Class ‘A+’ project.
As with all EAs, there is a minimal risk that during the early stages of design, information may
surface which determines that a schedule ‘B’ EA is more appropriate. Should this happen, there
would be a moderately longer period of time to complete the EA prior to starting detailed design
activities. However this risk is considered low and there may be opportunities to avoid the EA
schedule change by completing additional steps without affecting the project schedule,
depending on the source of the issue.
5 - 2
2) Detailed Design
Once the preliminary design is complete, the detailed design can be initiated. The activities
involved in this would include geotechnical testing for the foundation design, detailed design of
the bridge, liason with public, utilities and railway. The time required to complete the detailed
design should be approximately 4-6 months. There may be limited opportunities to keep the
design period to the shorter end of this projection. The City should procure these services with
a specific timeline (4 months) and rely on the industry to determine how best to meet the
expedited timelines most cost effectively. It should be noted that there would likely be a
premium on the cost for the expedited design services. Due to the time required to procure the
design services, the City can explore completing work that the consultant would need to
complete. For example, if geotechnical work is required, the City could complete this under a
separate ongoing contract during the procurement process.
3) Construction
Construction can be initiated once the tender has been awarded, permits are obtained and the
appropriate pre-construction documentation has been completed (executed contract, bonding,
insurance etc). Current estimates on the length of construction are approximately 8-12 months.
This is largely dependent on the complexity of the design and the time of year. Construction
through the winter will be slower than in summer months and likely cost more (in the order of
25%). Options for expedited construction can be explored during the detailed design work. As
with the design services, any expedited construction methods will likely increase the cost of
construction.
Proposed Schedule
ACTIVITY TIMELINE
Advertise for consultant services October 22, 2013
Award consultant services November, 2013
EA Commencement NA – Schedule A+
EA Completion NA – Schedule A+
Detailed Design November 2014 – April 2014
Tendering May 2014
Construction Start June 2014
Construction End Winter/Spring 2015
Summary of Expedited Measures
These following expedited measures will be utilized or reviewed further:
Complete the project as a Schedule A+ Environmental Assessment
Thorough, but shorter public input process
5 - 3
City explore options to complete preliminary work during the consultant procurement
process
City explore designs that are quicker to construct as well as expedited construction methods
Alternatives for Cyclists and Pedestrians
The closure of the Margaret Avenue Bridge has presented transportation issues around the
bridge particularly with cyclists and pedestrians. Staff have worked with the Cycling Advisory
Committee to mitigate the impact of the closure on cyclists. The main concern is how to safely
and efficiently re-route cycling traffic around the structure. To accomplish this, it is proposed
that special signage will be installed on Margaret Avenue, in advance of the closure, to re-route
cyclists and pedestrians along Wellington Street to either Lancaster Street or Duke Street
depending on the approximate destination. For example, travelling public heading south
towards the bridge on Margaret Avenue, and heading downtown would be re-routed along
Wellington toward Duke. For destinations including the Public Library and Centre in the Square,
traffic would be re-routed along Wellington towards Lancaster. The detour route would be
clearly marked with customized signs and will be complimented by “Share the Road” signs
along the routes.
Similarly, pedestrians will be directed along Wellington to either St. Ledger or Weber Street,
depending on the destination, which represent the shortest ways around the structure.
ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN:
The replacement of the Margaret Avenue Bridge will continue to contribute to Quality of Life for
residents in the City, by investing in infrastructure that will support our future growth.
FINANCIAL IMPLICATIONS:
Demolition Tender Update
The tender for the demolition of the bridge was advertised on September 18, 2013 and closed
October 3, 2013. Staff awarded the contract to Bel-Air Excavating and Grading on October 9,
2013. The contract was awarded through the CAO as per council resolution.
The total cost of the award is $499,064.50, including HST of which $107,350.00 is attributable to
the temporary gas main support system.
Five (5) bids were received by the City as follows (includes HST);
Bel-Air Excavating and Grading 499.064.50
Budget Environmental 504,940.50
McLean-Taylor 508,632.21
5 - 4
Tri-Phase 728,312.11
Facca Inc. 873,490.00
Bel-Air Excavating and Grading Limited has completed several demolition contracts
successfully with other municipalities. Bel-Air has completed work for the City in the past and is
currently completing the Schneider Creek Rehabilitation project with satisfactory results.
Reference checks of Bel-Air were contacted and no major concerns were noted. It is staff’s
opinion that Bel-Air can successfully complete this project.
The start of construction has been scheduled for Monday, October 21, 2013, subject to weather
and railway approvals.
Staff are awaiting the necessary railway permits and are confident that the required approvals
st
will be in-place by October 21.
COMMUNITY ENGAGEMENT:
NA
ACKNOWLEDGED BY:
Pauline Houston, Deputy CAO
Infrastructure Services Department
5 - 5