HomeMy WebLinkAboutCSD-13-104 - Planning Around Rapid Transit Stations (PARTS) Phase 1
REPORT TO:
Planning & Strategic Initiatives Committee
DATE OF MEETING:
December 2, 2013
SUBMITTED BY:
Alain Pinard, Director of Planning
PREPARED BY:
Sarah Coutu, Policy Analyst (519-741-2200 ext. 7069)
Natalie Goss, Senior Planner(ext. 7067)
Tina Malone-Wright, Senior Planner (ext. 7765)
Garett Stevenson, Planner (ext. 7070)
Brandon Sloan, Manager of Long Range & Policy Planning
WARD(S) INVOLVED:
All Wards
DATE OF REPORT:
November 22, 2013
REPORT NO.:
CSD-13-104
SUBJECT:PLANNING AROUND RAPID TRANSIT STATIONS
(PARTS) PHASE 1: PROJECT PLAN AND
BACKGROUND REPORT
RECOMMENDATION:
That staff proceed with Planning Around Rapid Transit Stations (PARTS), as informed by
the Phase 1: Project Plan and Background Report, generally in accordance with the
sequence and timing outlined in Appendix B to report CSD 13-104 and subject to
business planning and purchasing processes.
BACKGROUND:
The Planning Around Rapid Transit Stations (PARTS) project was introduced to Council through
report CSD-12-150which was presented at the November 12, 2012 Council Strategy Session.
Phase 1 of the project was identified in the 2013 Business Planning Priorities (Report CAO-12-
044) and later ranked as a high priority Corporate Project. The PARTS Phase 1: Project Plan
and Background Report represents completion of this phase of work.
REPORT:
The Region of Waterloo, in association with a consortium to be selected, is designing and
constructing the ION light rail and adapted bus rapid transit line and station stops through
Kitchener, Waterloo and Cambridge. Currently, there are twelve (12) station stops identified in
Kitchener (one future light rail station stop is shared with Cambridge). The intent is to begin
adapted bus rapid transit (aBRT) between Fairview Park Mall and Cambridge within two years
andto commence light rail transit (LRT) service in Kitchener and Waterloo in 2017.
LRT has the potential to be a major factor in the long-term growth and continued economic
prosperity of our area. With it, comes the potential for continued change in areas close to the
stations. In order to help ensure and confirm there is a proper framework to guide growth and
stability in these locations, the cities of Kitchener and Waterloo are now embarking on the
detailed planning for the future of land and infrastructure within a ten (10) minute walk of each
LRT station stop. The intent is to
Community Building Strategy and to complete as much detailed planning as possible in time for
the opening of LRT.
3 - 1
In Kitchener, the detailed planning initiative is referred to as Planning Around Rapid Transit
Stations (PARTS). Among other things, PARTS will investigate and confirm land use,
engineering and community infrastructure, streetscapes, urban design, transportation
implications and transportation demand management techniques,etc. within walking distance of
station stops. This project is being undertaken with certain givens.The scope of the PARTS
project does not include discussion on the merits of rapid transit,the location and design of the
actual rapid transit line or stations, municipal or other agency infrastructure requirements or
relocations within the rapid transit alignment and several other matters. The City is actively
participating in technical discussions regarding the construction of LRT through other forums.
PARTS Phase 1: Project Plan and Background Report
Planning around each of the station stops in Kitchener will be a comprehensive, multi-year
process involving various stakeholders and a significant amount of community engagement.
Before beginning this extensive work it would be beneficial to develop an overall project plan
including an investigationof existing conditions and background information, identifying the
study areas and the scope of work and prioritizing a future work plan. Planning staff, with the
assistance of several other business units in the City along with representatives from the Region
and other agencies, conducted numerous tasks in Phase 1 of PARTS which have culminated in
the preparation of a Project Plan and Background Report. The key components include:
Compilation of existing condition data and background information
Confirmation of recommended station study areas
Preparation of overall goals to guide the creation of the Station Study Area Plans
Identification of the primary work,project teams andkey deliverables for future phases
Development of an overall work program for Phase 2 and the prioritization andtiming for
the Station Study Area Plans
In order to proceed with PARTS, it was important to understand which land required further
study in the next few years. Based on the analysis conducted in Phase 1, there are six
recommended station study areas as illustrated in Appendix A. Some of the station study areas
include a grouping of multiple station stops. Confirmation andrefinement of the limits of the
station study areas (including the focus and influence areas) will occur as part of the preparation
of each Station Study Area Plan. A draft station study area is also recommended for land in
Kitchener that is near the Sportsworld/Cambridge future LRT station stop.
Given the magnitude of work that is anticipated in PARTS Phase 2 and the individual station
study area plans,along with other staff resource priorities, it is not feasible to undertake all of
this work at the same time. With the goal of completing the most important Station Study Area
Plans by2017, this requires the prioritization and appropriate sequencing of work. Based on the
analysis conducted in Phase 1,it is recommended that the plans be undertaken in the sequence
andgeneral timeframes outlined in Appendix B to this report.
The PARTS Phase 1:Project Plan and Background Report (attached as Appendix C) provides a
summary of the above information, includes a volume with more detailed existing conditions and
background information and outlines how best to proceed with future Planning Around Rapid
Transit Stations in Kitchener.
3 - 2
PARTS Phase 2: Corridor-wide Initiatives
Through PARTS Phase 1 it was determined that some of the key work required is best prepared
for all of the Kitchener Station Study Areas at once. As a result, PARTS Phase 2 is
recommended to consist of five corridor-wide initiatives:
Interim Direction
Communications Approach
Urban Design Guidelines
Sanitary Sewer Capacity Analysis
Transportation Demand Management
These initiatives are further described in the Phase 1: Project Plan and Background Report and
are summarized in Appendix B.
PARTS: Station Study Area Plans
Once the corridor-wide initiatives in PARTS Phase 2 are nearing completion, it is recommended
to begin the Central Stations Study Area Plan; which is the highest priority. It is expected that
the deliverable may include: refinement of the study area boundaries, a preferred future
development concept, 3D modeling/visualization, potential land use changes for the
recommended focus area , built form plans/guidelines,
connectivity plans, transportation demand management and parking strategies, cultural heritage
resource conservation, sustainability plans,public art considerations and recommendations for
any related infrastructure or streetscape improvements that may be required in the future.
The proposed sequencing andtiming for the station study area plans is outlined in Appendix B.
ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN:
The PARTS Phase 1 project most directly aligns with the Community Priorit
FINANCIAL IMPLICATIONS:
Approximately $25,000 from the Planning Studies Growth (Capital DC) account was utilized
for Phase 1. Through significant staff efforts this equates to about one third of the budgeted
amount. The costs savings will be carried over to Phase 2 and transferred to the Study Area
Plans which will require more detailed technical review. The upset budget limit for all of the 5
initiatives in Phase 2 is $70,000. This amount can be allocated from existing funds in the same
Planning Studies account and from a Transportation Demand Management account.
At this time, an early estimate of the preparation and technical review of the Central Stations
Study Area Plan is in the range of approximately $150,000-200,000, depending upon the depth
of the community engagement approach that is selected. The preparation of a detailed Terms of
Reference in 2014 will further refine this cost estimate. These costs would primarily be funded
through Capital/Development Charges and other potential partnerships and would continue to
be subject to budget and purchasing processes.
Eventually, it is expected that each Station Study Area Plan may recommend actions, such as
prioritizing a specific streetscape or sanitary sewer improvement, that should be considered in
future Capital Budget, and where appropriate Development Charge, programming.
3 - 3
COMMUNITY ENGAGEMENT:
along with a Your Kitchener article to signify the commencement of the upcoming projects.
One of the recommended initiatives for PARTS Phase 2 is to further develop a communications
approach for engaging stakeholders and the broader community in each of the Station Study
Areas.An update report will be provided in March/April 2014. Formal notice and consultation
will be required for the interim direction initiative in PARTS Phase 2 and additional engagement
may occur for other Phase 2 initiatives.
CONCLUSION:
The PARTS Phase 1: Project Plan and Background Report provides a significant amount of
contextual information about areas around the station stops that, combined with work prepared
by the Region, forms a good baseline to begin with Kitchener-specific initiatives and Station
Study Area Plans. Certain station study area plans and sequencing of work are recommended
in order to balance resources with the intent to complete the station study area plans by the time
LRT is operational.
The recommended approach will allow for a framework to be developed to guide transit-
supportive development and investment in areas within walking distance of the ION rapid transit
system. Proceeding with comprehensive studies at this time will help ensure that there is a
common blueprint to follow for the future. These areas will continue to evolve over the next 5-,
10-, 20-, 50+ years. As such,staff is recommending to proceed with the Planning Around Rapid
Transit Stations (PARTS) projects generally in accordance with the timing outlined in Appendix
B. Any project prioritization, resourcing and financial implications continue to be subject to
business planning, budgeting and purchasing processes.
ACKNOWLEDGED BY:
Michael May, Deputy CAO
Community Services Department
Attachments
Appendix A - PARTS Recommended Station Study Areas
Appendix B - PARTS Recommended Work Program
Appendix C - PARTS Phase 1: Project Plan and Background Report (Volumes 1 and 2)
3 - 4
PARTSRecommendedStationStudyAreas
AppendixA
3 - 5
Appendix B (CSD-13-104)
Planning Around Rapid Transit Station (PARTS)
Recommended Work Program
Phase 1: Project Plan and Background Report
2013
Phase 2: Corridor-wide Initiatives
Interim Direction
Communications Approach
Urban Design Guidelines
Sanitary Sewer Capacity Analysis
Transportation Demand Management
2014
Central Midtown Rockway Fairway Block Line
Stations Station Stations Station Station
Study Study Study Study Study
Area Plan Area Plan Area Plan Area Plan Area Plan
2014-2015 2015-2016 2015-2016 2016-2017 2016-2017
3 - 6
PARTS Phase 2: Corridor-wide Initiatives
There are 5 independent initiatives that are required to be completed for all of the Kitchener Station
Study Areas, preferably in advance of each subsequent plan. Each initiative will go through a review
process by others and will require project support.
Project Manager: Manager of Long Range and Policy Planning
Interim Direction
It is anticipated that there will be continued redevelopment interest in properties that are in proximity
to station stops before each station study area plan can be completed. In order to provide some
guidance for development proposals to meet, or not prejudice, the objectives for these transit-
supportive locations it may be necessary to implement some interim direction utilizing one or more
options/tools. A number of options are outlined within the PARTS Phase 1: Project Plan and
Background Report. A public process to consult stakeholders is required before any formal interim
direction, such as an amendment to the existing Official Plan and/or Zoning By-law, can be applied.
The deliverable is a staff report to Committee of Council outlining a recommendation for interim
direction.
Working Team: Senior Planner (Policy Section)-Lead, Planner (Development Section)
Communications Approach
PARTS Phase 1 identified that community engagement for the station study area plans will be
important and could occur via a wide range of methods and tools. Further investigation and
discussion is required in order to determine the preferred communications approach that balances
engagement with resources and timing. The deliverable is a staff report to Committee of Council in
March or April 2014.
Working Team: Senior Planner (Policy Section)-Lead, Communications Staff, Deputy CAOs input
Urban Design Guidelines
The preparation of corridor-wide urban design guidelines will provide efficiencies considering the
likelihood that similar design principles will be expected in each of the station study areas. It is
anticipated that a similar approach to the Mixed Use Corridor Design Guidelines will be utilized
(overall objectives and guidelines followed by area specific guidelines). It is expected that the
content from these guidelines will become part of an updated design brief .
Working Team: Senior Planner (Urban Design)-Lead, Planner (Development Section), Urban
Designer
Sanitary Sewer Capacity Analysis
Further assessment of future sanitary sewer capacity is recommended. The City has a model of our
system and the current estimated capacity. Various scenarios have been considered if future
development was to occur under current zoning conditions. A high level review was considered as
part of PARTS Phase 1 which did not identify any major known issues with the system should future
growth occur in the immediate term. As part of PARTS Phase 2, a range of general density numbers
will be explored in concert with the sanitary model. It is expected that with each station study area
plan a more detailed review of sanitary impacts will be explored for development scenarios. It is
important to consider the connected system and not each area in isolation.
Working Team: Senior Planner (Policy Section)-Lead, Engineering Technologist, GIS Technician
Transportation Demand Management (TDM) Strategy
Similar to the Urban Design Guidelines, there are likely common approaches to TDM that can be
further explored and proposed. Each subsequent station study area plan could then add direction or
recommendations that are specific to that context.
Working Team: TDM Coordinator-Lead, Planner (Development Section), Policy Analyst
3 - 7
Appendix C
PARTS Phase 1: Project Plan and Background Report (Volumes 1 and 2)
Please Note: Appendix C can be viewed online at:
http://www.kitchener.ca/en/livinginkitchener/Planning-Around-Rapid-Transit.asp
3 - 8