HomeMy WebLinkAboutFCS-14-123 - T14-057 - Schneider Creek Remediation REPORT TO: Committee of the Whole DATE OF MEETING: 2014-06-30 SUBMITTED BY: Larry Gordon, Director of Supply Services, 519-741-2200 ext. 7214 PREPARED BY: Larry Gordon, Director of Supply Services, 519-741-2200 ext. 7214 WARD(S) INVOLVED: 3 DATE OF REPORT: 2014-06-19 REPORT NO.: FCS-14-123 SUBJECT: T14-057 – Schneider Creek (CN Rail Line to Manitou Drive) Creek Remediation ___________________________________________________________________________ RECOMMENDATION: That Tender T14-057 – Schneider Creek (CN Rail Line to Manitou Drive) Creek Remediation be 560789 Ontario Limited o/a R&M Construction, Acton, Ontario awarded to at their tendered price of $986,343.58, including provisional items and contingencies of $92,000., plus H.S.T. of $128,224.67, for a total of $1,114,568.25. BACKGROUND: An Environmental Assessment (EA) Addendum for the remediation of Schneider Creek between Hayward Avenue and Manitou Drive was completed in the spring of 2012 by the City of Kitchener in partnership with Grand River Conservation Authority (GRCA) and was approved by Council on March 19, 2012. A preferred alternative was determined for the three reaches of creek within the study limits to alleviate the flooding and erosion concerns. Engineering Services is proceeding with the implementation of the preferred alternative for Schneider Creek Reach 3 (CN Rail Line to Manitou Drive). The work includes the grading and excavation of the creek bed and banks, restoration of an ancestral channel, erosion and sediment control, creek bypass and dewatering, placement of rock and granular materials, removal of debris and sediment, clearing and restoration of vegetation along the creek, bioengineering bank stabilization, construction of pools and riffles, armourstone weir installation, armourstone wall construction, live log crib wall construction, wetland restoration, and site restoration. Full funding for this project has been approved by council as part of the 2014 budget process. 1. vii - 1 REPORT: Tenders were advertised publicly in the Daily Commercial News, on the City of Kitchener Website and the Internet through the Ontario Public Buyers Electronic Tendering Information System. Documents were picked up by nineteen (19) interested parties, and by the closing date of Thursday June 5, 2014, six (6) tenders were received. The tenders were reviewed by J. Prince, Ecosystem Recovery Inc., the City’s Consultant for the project, and D. Lupsa, Design & Construction Project Manager who concur with the above recommendation. The following tenders were received: Bid Price 560789 Ontario Limited o/a R&M Construction Acton ON $1,114,568.25 * Bronte Construction Milton ON $1,189,129.51 Cambridge Landscaping Cambridge ON $1,191,519.35 Tervita Environmental Services Burlington ON $1,537,161.16 Hawkins Contracting Services Limited Stouffville ON $1,641,715.42 Bel-Air Construction Cambridge ON $2,101,149.12 ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN: Theme: Financial Management Strategic Direction: Ensure responsible use of public funds within a supportive policy framework. The City of Kitchener’s purchasing policies and practices ensure openness, fairness and transparency in the procurement of goods and services. 1. vii - 2 FINANCIAL IMPLICATIONS: In addition to the costs anticipated in this tender, the design and implementation of these types of projects typically involves city staff and resources from across the corporation. These costs are included in the line item "Projected Costs: Staff Time/Permitting/Material testing", and will be itemized when they exceed $125,000. Included in this line item are staff time and expenses for all city staff in support of the project such as Engineering, Kitchener Utilities, and Transportation Planning. The line item also includes all regulatory permitting, geotechnical and material testing, detouring and traffic control, alternate access and parking requirements and any other miscellaneous costs. Projects utilizing in-house staff will include costs for inspection during construction and contract administration. The net cost for this Tender (A), is fair and reasonable for a purchase of this scope but the upset limit exceeds the budget allowance (B) provided within the budget. Additional funding for this purchase is provided by the existing surplus balance in the account. The estimated surplus (E) will remain within the project to fund construction of Reach 2 (downstream of the Block Line Rd crossing to CN Rail line). Tender T14-057 Schneider Creek Remediation - Reach 3 The total budget for all phases of this project is $ 15,340,400.00 Estimated Cost for this Phase of Work Tender T14-057 1,114,568.25 less: HST rebate on tender (110,864.97) Net Cost Being Awarded 1,003,703.28 A Costs Incurred to Date Projected Costs: Staff time 88,350.00 Total Estimated Cost for this Phase of Work 1,092,053.28 C Budget for this Phase of Work Storm Water Utility 912,658.00 Total Budget for this Phase of Work 912,658.00 B Estimated Surplus/(Deficit) for this Phase of Work (B - C) (179,395.28) D Estimated Surplus/(Deficit) from previous phases 409,962.45 Total Estimated Surplus/(Deficit) 230,567.17 E COMMUNITY ENGAGEMENT: Potential vendors are informed of bid opportunities through the public posting of bid documents as outlined in the City’s Purchasing By-Law. Vendors, local media and the general public are informed of purchasing recommendations to Council through the public reports which are included with the Council agenda the week prior to the Council meeting. ACKNOWLEDGED BY: Jeff Willmer, Chief Administrative Officer 1. vii - 3