HomeMy WebLinkAboutFCS-15-156 - T15-081 Permeable Paver Demonstration Project -Trillium Dr REPORT TO: Committee of the Whole DATE OF MEETING: 2015-10-26 SUBMITTED BY: Michelle Palmer-Novakovic, Director of Supply Services 519-741-2200 ext. 7214 PREPARED BY: Laurie Stecho, Supervisor of Purchasing 519-741-2200 ext. 7089 WARD(S) INVOLVED: Ward 5 DATE OF REPORT: 2015-10-13 REPORT NO.: FCS-15-156 SUBJECT: T15-081 Permeable Paver Demonstration Project 801 Trillium Drive (Huron Natural Area Parking Lot) ___________________________________________________________________________ RECOMMENDATION: That Tender T15-081 Permeable Paver Demonstration Project - 801 Trillium Drive (Huron Natural Area Parking Lot), be awarded to Seawaves Development Services Inc., Hamilton, Ontario at their tendered price of $118,586., including provisional items and contingencies of $20,600., plus H.S.T. of $15,416.18, for a total of $134,002.18. BACKGROUND: A Federal Grant has been approved up to the amount of $175,000. for this project. The City is on schedule to complete construction of a 17 parking spot permeable parking lot in November 2015. This stormwater demonstration project will take place at Huron Natural Area (HNA), a 107 hectare municipal site located at 801 Trillium Drive on the south side of Kitchener. The proposed parking lot is required to accommodate a growing number of visitors to the natural area. This site provides an excellent opportunity to educate the large number of visitors to the park about stormwater management and the role it plays in habitat protection. Through this study, the City of Kitchener aims to better understand the role that new innovative stormwater technologies can play in protecting our water resources. This study will provide a basis for comparison of new innovative technologies to traditional approaches in stormwater management. Recommendations from this study will be used *** This information is available in accessible formats upon request. *** Please call 519-741-2345 or TTY 1-866-969-9994 for assistance. 1.iv. - 1 to inform recommendations that are currently being developed through the Stormwater Master Plan study. REPORT: Tenders were advertised publicly in the Daily Commercial News, on the City of Kitchener website and the internet through the Ontario Public Buyers Electronic Tendering Information System.Documents were picked up by eleven (11) interested parties and by the closing date of Thursday October 8, 2015, five (5) tenders had been received. The tenders were reviewed by M. Wilson, Design & Construction Project Manager and N. Gollan, Manager of Stormwater Utility who concur with the above recommendation. The following tenders were received: Bid Price Seawaves Development Services Inc. Hamilton ON $134,002.18 * Cambridge Landscaping Cambridge ON $151,222.93 Gateman Milloy Kitchener ON $193,900.00 Steed and Evans St. Jacobs ON $199,774.22 CSL Group Ltd. Ancaster ON $227,007.68 ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN: The recommendation of this report supports the achievement of the City’s strategic vision through the delivery of core service. FINANCIAL IMPLICATIONS: In addition to the costs anticipated in this tender, the design and implementation of these types of projects typically involves City staff and resources from across the corporation. These costs are included in the line item "Projected Costs: Staff Time/Permitting/Material testing", and will be itemized when they exceed $125,000. Included in this line item are staff time and expenses for all City staff in support of the project such as Engineering, Kitchener Utilities, and Transportation Planning. The line item also includes all regulatory permitting, geotechnical and material testing, detouring and traffic control, alternate access and parking requirements and any other miscellaneous costs. Projects utilizing in-house staff will include costs for inspection during construction and contract administration. The net cost for this tender (A), is fair and reasonable for a purchase of this scope and the upset limit is within the budget allowance (B) provided within the budget. Funding for this purchase is included within the approved capital budget. There is expected to be no estimated surplus/(deficit) (E). 1.iv. - 2 Tender T15-081 Permeable Paver Demo Project at Huron Natural Area The total budget for all phases of this project is: $ 175,000.00 Estimated Cost for this Phase of Work Tender T15-081 costs, including HST 134,002.18 less: HST rebate on tender (13,329.06) Net Cost Being Awarded 120,673.12 A Costs Incurred to Date - Projected Costs: Staff Time/Monitoring/Feasibility Study 54,326.88 Total Estimated Cost for this Phase of Work 175,000.00 C Budget for this Phase of Work Federal Grant 175,000.00 Total Budget for this Phase of Work 175,000.00 B Estimated Surplus/(Deficit) for this Phase of Work (B - C) 0.00 D Estimated Surplus/(Deficit) from previous phases - Total Estimated Surplus/(Deficit) 0.00 E COMMUNITY ENGAGEMENT: INFORM – This report has been posted to the City’s website with the agenda in advance of the council / committee meeting. PREVIOUS CONSIDERATION OF THIS MATTER: Not applicable ACKNOWLEDGED BY: Dan Chapman, Deputy CAO & City Treasurer, Finance and Corporate Services 1.iv. - 3