Loading...
HomeMy WebLinkAboutFCS-16-008 - T15-098 Fairfield Avenue Road Reconstruction REPORT TO: Committee of the Whole DATE OF MEETING: 2016-01-25 SUBMITTED BY: Michelle Palmer-Novakovic, Director of Supply Services 519-741-2200 ext. 7214 PREPARED BY: Laurie Stecho, Supervisor of Purchasing 519-741-2200 ext. 7089 WARD(S) INVOLVED: Ward 10 DATE OF REPORT: 2016-01-12 REPORT NO.: FCS-16-008 SUBJECT: T15-098 Fairfield Avenue (Ridgewood Avenue to Edwin Street) Road Reconstruction ___________________________________________________________________________ RECOMMENDATION: That Tender T15-098 Fairfield Avenue (Ridgewood Avenue to Edwin Street) Road Reconstruction, be awarded to Terracon Underground, Brantford, Ontario, at their tendered price of $1,038,315.94, including provisional items and contingencies of $77,566.80, plus H.S.T. of $134,981.07, for a total of $1,173,297.01. BACKGROUND: Engineering Services is proceeding with the road reconstruction of Fairfield Avenue (Ridgewood Avenue to Edwin Street). The services were originally constructed in the 1950’s and are in need of replacement. The project involves the replacement of the roadway, curb and gutter and sidewalk and all underground services and surface works. The administration, design and tendering of this project has been completed by Meritech Engineering, the construction administration and inspection of this project will also be completed by Meritech Engineering. Full funding for this project has been approved by Council as part of the 2016 budget process.The project is scheduled to begin April 11, 2016, weather permitting. *** This information is available in accessible formats upon request. *** Please call 519-741-2345 or TTY 1-866-969-9994 for assistance. 1.ii. - 1 REPORT: Tenders were advertised publicly in the Daily Commercial News, on the City of Kitchener website and the internet through the Ontario Public Buyers Electronic Tendering Information System. Documents were picked up by eight (8) interested parties and by the closing date of Thursday December 17, 2015, eight (8) tenders had been received. The tenders were reviewed by N. Litchfield, Meritech Engineering, the City’s Consultant for the project and L. Christensen, Design and Construction Project Manager who concur with the above recommendation. The following tenders were received: Bid Corrected Price Price Terracon Underground Brantford ON $1,173,297.01 * Network Sewer & Watermain Cambridge ON $1,244,272.05 $1,244,269.59 Sousa Concrete Branchton ON $1,255,462.82 J. Weber Contracting Breslau ON $1,285,519.00 Regional Sewer and Watermain Cambridge ON $1,362,836.61 Ersman Construction Inc. Kitchener ON $1,387,470.04 Sierra Construction Woodstock ON $1,412,865.56 Steed and Evans St. Jacobs ON $1,507,612.33 Tender documents were checked for mathematical errors and corrected accordingly. ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN: The recommendation of this report supports the achievement of the city’s strategic vision through the delivery of core service. FINANCIAL IMPLICATIONS: In addition to the costs anticipated in this tender, the design and implementation of these types of projects typically involves city staff and resources from across the corporation. These costs are included in the line item "Projected Costs: Staff Time/Permitting/Material testing", and will be itemized when they exceed $125,000. Included in this line item are staff time and expenses for all city staff in support of the project such as Engineering, Kitchener Utilities, and Transportation Planning. The line item also includes all regulatory permitting, geotechnical and material testing, detouring and traffic control, alternate access and parking requirements and any other miscellaneous costs. Projects utilizing in-house staff will include costs for inspection during construction and contract administration. 1.ii. - 2 The net cost for this tender (A), is fair and reasonable for a purchase of this scope and the upset limit is within the budget allowance (B) provided within the budget. Funding for this purchase is included within the 2016 to 2025 capital budget forecast. The estimated surplus (E) will be returned to the Accelerated Infrastructure Replacement Program (AIRP) general account, and will be used to fund unexpected deficits in other AIRP projects. Tender T15-098 Fairfield Avenue The total budget for all phases of this project is: $ 1,449,621.00 Estimated Cost for this Phase of Work Tender T15-098 costs, including HST 1,173,297.01 less: HST rebate on tender (116,706.66) Net Cost Being Awarded 1,056,590.35 A Costs Incurred to Date Projected Costs: Staff Time/Material Testing 37,176.00 Total Estimated Cost for this Phase of Work $ 1,093,766.35 C Budget for this Phase of Work Sanitary Utility 555,807.00 Storm Water Utility 277,904.00 Water Utility 374,566.00 Intensification Allowance 8,933.00 Total Budget for this Phase of Work $ 1,217,210.00 B Estimated Surplus/(Deficit) for this Phase of Work (B - C) 123,443.65 D Estimated Surplus/(Deficit) from previous phases 17,228.84 Total Estimated Surplus/(Deficit) $ 140,672.49 E COMMUNITY ENGAGEMENT: INFORM – This report has been posted to the City’s website with the agenda in advance of the council / committee meeting. PREVIOUS CONSIDERATION OF THIS MATTER: Not applicable ACKNOWLEDGED BY: Dan Chapman, Deputy CAO & City Treasurer, Finance and Corporate Services 1.ii. - 3