HomeMy WebLinkAboutINS-16-064 - Battler Snow Storage Disposal Facility (SSDF) Funding Increase
REPORT TO: Special Council
DATE OF MEETING: August 8, 2016
SUBMITTED BY: Dan Locke, Interim Associate Director (Operations), (519)741-
2600 ext. 4517
Hans Gross, Director of Engineering, (519)741-2200 ext. 7410
PREPARED BY: Dan Locke, Interim Associate Director (Operations), (519)741-
2600 ext. 4517
WARD(S) INVOLVED: All
DATE OF REPORT: July 19, 2016
REPORT NO.: INS-16-064
SUBJECT:Battler Snow Storage Disposal Facility (SSDF) Funding
Increase
____________________________________________________________________________________
RECOMMENDATION:
That additional funding of $_______, be allocated to the Battler Snow Storage
Disposal Facility (SSDF) capital project from the Development Charge Recovery
reserve.
BACKGROUND:
Staff have previously identified the need for a permanent Snow Storage Disposal
Facility (SSDF) to meet provincially legislated minimum maintenance standards for
snow removal. The City has been using a leased location at 75 Ardelt Place, but has
been informed by the property owner that it will no longer be available as a snow
disposal site. As such, the City requires a new snow disposal site.
Through consideration of multiple sites outlined in previous staff reports, and with public
feedback from dedicated Public Information Centres (PICs), Council has approved the
construction of a permanent SSDF at 1585 Battler Road. The total approved budget for
all phases of the project is $2,400,000. This report is seeking an increase to the project
budget of $660,000 in order to award the construction tender that has come in higher
than the approved budget. The revised budget ($3,060,000) is still within the estimated
cost range ($2,448,500 to $3,106,500) noted in report INS-15-044 of September 2015.
REPORT:
Tenders for the construction of the Battler Road SSDF closed on July 18, 2016 with all
submitted bids being above the approved budget for this phase of the project. Through
the design and approvals process for the Battler Road SSDF, additional items were
*** This information is available in accessible formats upon request. ***
Please call 519-741-2345 or TTY 1-866-969-9994 for assistance.
7. - 1
required by various agencies to be added to the project (e.g. additional environmental
protections required by the Grand River Conservation Authority for runoff and silt,
increased height of noise walls from one metre to two metres to meet noise restrictions).
Additional application fees and studies were also required given the scope of work
being considered for the SSDF. The addition of these components, as well as the low
bid price which is approximately 7% above the pre-tender estimate has resulted in a
tender price that is higher than the estimate prepared in September 2015.
Staff have fully explored options and determined there are not viable alternatives to
awarding the construction tender for the Battler Road SSDF. Temporary snow disposal
sites are not available, and the Battler site is the highest ranked location for a
permanent snow storage disposal facility. Further, pursuing any other permanent
location would take up to three years to study, apply for approvals, design, and
ultimately construct a permanent snow storage disposal facility. By awarding the Battler
Road SSDF tender in August, it allows adequate time to have the new permanent
location operational by December 2016.
Staff have reviewed the Battler Road SSDF tender, and suggest two items that could be
removed from the contract which would result in a reduced cost of up to $80,000.
Council is requested to select one of the following four Options for inclusion as part of
the recommendation contained herein:
Option A – additional funding of $660,000, which represents no reduction in the
scope of work.
Option B – additional funding of $600,000, which represents the removal of the
washroom facility from the scope of work.
Option C – additional funding of $640,000, which represents the removal of the
landscaping along Battler Road from the scope of work.
Option D – additional funding of $580,000, which represents the removal of both
the washroom facility and the landscaping along Battler Road from the scope of
work.
ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN:
Strategic Priority: Effective and Efficient Services
Strategy: 5.2 – Improve the design and delivery of city services so that they provide
what citizens want in the most reliable, convenient and cost efficient way.
Strategic Action: 91 Snow Disposal Site
7. - 2
FINANCIAL IMPLICATIONS:
Based on the low bid received through a competitive tendering process, a maximum
budget increase of $660,000 is required to award the Battler Road SSDF construction
contract. It is proposed this funding come from the Development Charge (DC)
Recovery reserve. The DC Recovery reserve is the primary funding source for this
project and there is projected to be sufficient room within the reserve to fund an
additional $660,000 for the Battler Road SSDF.
COMMUNITY ENGAGEMENT:
INFORM – This report has been posted to the City’s website with the agenda in
advance of the council / committee meeting.
CONSULT and COLLABORATE – At the public information centre (PIC) held on
th
October 20 participants had the opportunity to raise any concerns regarding the SSDF
project and the possible impact on their neighbourhood. A second PIC was held on
June 22, 2016 which showed the final proposed design to the participants and gave
them the opportunity to raise any concerns.
In advance of both PIC’s, a letter regarding the PIC was mailed out to the residents
living within a 0.5 km radius of the proposed SSDF site at 1585 Battler Road informing
them of the PIC and how to participate.
PREVIOUS CONSIDERATION OF THIS MATTER:
Report INS-15-044, Snow Disposal Site Selection Report taken to Council on
September 21, 2015. Consideration of the recommendation as outlined within the report
was deferred to allow for the completion of a PIC with residents.
Report INS-15-091, Snow Disposal Site Public Consultation taken to Council on
November 2, 2015, included public input as a result of a PIC held on October 20, 2015.
CONCLUSION:
The City requires a snow disposal site in order to meet legislated requirements and the
expectations of residents. A permanent location at 1585 Battler Road has been
approved by Council, but has a higher cost than expected. In the absence of any viable
alternatives, an increased budget for construction of the Battler Road SSDF should be
approved.
ACKNOWLEDGED BY: Cynthia Fletcher and Justin Readman, Interim Executive
Directors of Infrastructure Services
7. - 3