HomeMy WebLinkAboutINS-16-079 - Fourth Ave. Reconstruction - Additional Scope and PO Extension REPORT TO: Community and Infrastructure Services DATE OF MEETING: November 7, 2016 SUBMITTED BY: Hans Gross, P.Eng., Director, Engineering Services, 519-741-2200 x 7410 PREPARED BY: Steve Allen, P.Eng., Manager, Engineering Design & Approvals 519-741-2200 x 7584 WARD(S) INVOLVED: Ward 3 DATE OF REPORT: October 26, 2016 REPORT NO.: INS-16-079 SUBJECT:Fourth Avenue Reconstruction - Consultant Purchase Order Increase ___________________________________________________________________________________ RECOMMENDATION: That an extension of the purchase order issued to Associated Engineering Ltd. for Engineering Consultant services related to the reconstruction of Fourth Avenue between Kingsway Drive and Connaught Street in the amount of $ 50,813.90, be approved. BACKGROUND: Through the Accelerated Infrastructure Renewal Program (AIRP), the reconstruction of Fourth Avenue between Kingsway Drive and Connaught Street was identified as a priority project. Associated Engineering Ltd. was retained by the City through the consultant selection process (E15-084) in November 2015, to complete the design and provide contract administration and inspection services related to the reconstruction of Fourth Avenue. The Council approved fees for Associated Engineering Ltd. are $188,320.00 plus applicable taxes. Construction is expected to occur during the 2017 construction season. REPORT: The Fourth Avenue Reconstruction project is currently in the design phase. City staff is requesting additional tasks be completed by Associated Engineering Ltd. that are outside of the defined scope of work but related to this project. These tasks are related to the design and contract administration of the reconstruction of 90 meters of Connaught Street between Third Avenue and Fourth Avenue which is adjacent to the current project limits. During the detailed design of Fourth Avenue it was identified that due to required pipe sizing changes, some areas of Fourth Avenue cannot be built properly without lowering *** This information is available in accessible formats upon request. *** Please call 519-741-2345 or TTY 1-866-969-9994 for assistance. 4 4 - - 1 1 some of the underground pipe network. In order to do this, some pipe further downstream on Connaught Street will have to be replaced. The infrastructure on Connaught is of similar age and would have otherwise been identified for rehabilitation work in the future. The fee request has been reviewed and compared to the fees for the original Fourth Avenue assignment. Based on this comparison the price for the expanded scope is fair and reasonable. ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN: The recommendation of this report supports the achievement of the city’s strategic vision through the delivery of core service. FINANCIAL IMPLICATIONS: Funding for the purchase order extension will be provided from the Fourth Avenue project account in the 2017 budget. Funding for the construction of Connaught will be provided in the 2017 budget. The source of funding will be the AIRP program. COMMUNITY ENGAGEMENT: INFORM – This report has been posted to the City’s website with the agenda in advance of the council / committee meeting. CONCLUSION: Staff have reviewed the request and recommend that the existing purchase order to Associated Engineering Ltd. be increased to complete the remaining phases of this project. ACKNOWLEDGED BY: Justin Readman, Executive Director, Infrastructure Services 4 4 - - 2 2