HomeMy WebLinkAboutINS-16-088 - New Dundee Road, PO Extension REPORT TO: Finance and Corporate Services DATE OF MEETING: December 5, 2016 SUBMITTED BY: Hans Gross, Director, Engineering 519-741-2200 x7410 PREPARED BY: Chris Spere, Manager, Engineering Construction, 519-741- 2200 x 7412 WARD(S) INVOLVED: Ward 4 DATE OF REPORT: October 26, 2016 REPORT NO.: INS- 16-088 SUBJECT:Sanitary System, Sanitary Forcemain and Watermain Installation Contract New Dundee Road (Dodge Dr. to Robert Ferrie Drive) – Contractor P.O. Extension ____________________________________________________________________________________ RECOMMENDATION: That an extension of the purchase order issued to Regional Sewer and Watermain for construction services related to the construction of the linear works associated with the new Doon South Sanitary Pumping Station located on New Dundee Road in the amount of $ 37,344.00, be approved. BACKGROUND: To provide sanitary servicing to new developments in the south end of Kitchener, the need and location for a new sanitary pumping station was determined through the completion of an Environmental Assessment, completed in 2009. The tender for the Construction for the new pumping station was released in late 2014. At the same time, under a separate tender, the ancillary support works (forcemain and sewer) for the pumping station was also tendered. The pumping station, and associated discharge forcemain, was included in the DC Background Study. To bring the pumping station online prior to the planned date shown in the DC Background Study, funding was provided by a Developer through a Credit for Service agreement. The Credit for Service agreement included the construction of the pumping station, forcemain and water service. In December of 2014, the City retained Regional Sewer and Watermain to complete the construction of the trunk sanitary sewer, the forcemain, and water service. The Council approved fees for Regional Sewer and Watermain for this project were $ 4,166,626.90 plus applicable taxes. *** This information is available in accessible formats upon request. *** Please call 519-741-2345 or TTY 1-866-969-9994 for assistance. 3 - 1 REPORT: Regional Sewer and Watermain completed the construction of the works included in tender T14-093 in September of 2015 and subsequently received final payments for their work in January of 2016. As a result of a year-end financial audit by Regional Sewer and Watermain, a quantity discrepancy in the amount of sewer pipe was discovered and confirmed by the City. Specifically, the installation required 12.11 metres more sewer than what was indicated in the contract documents. ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN: The recommendation of this report supports the achievement of the city’s strategic vision through the delivery of core service. FINANCIAL IMPLICATIONS: None. Funding will be provided from the Doon South project account. The fee increase is based on final audited and measured quantities. COMMUNITY ENGAGEMENT: INFORM – This report has been posted to the City’s website with the agenda in advance of the council / committee meeting. CONCLUSION: Staff has reviewed the request and recommend that the existing purchase order to Regional Sewer and Water be increased to reflect the final cost of the works completed. ACKNOWLEDGED BY: Justin Readman, Interim Executive Director, Infrastructure Services Department 3 - 2