REPORT TO: Committee of the Whole
DATE OF MEETING: 2017-02-27
SUBMITTED BY: Michelle Palmer, Director of Supply Services
519-741-2200 ext. 7214
PREPARED BY: Ryan Scott, Buyer, 519-741-2200 ext. 7216
WARD(S) INVOLVED: Ward 1
DATE OF REPORT: 2017-02-13
REPORT NO.: FCS-17-033
SUBJECT: T17-037 Lyle Hallman Pool – Air Handler Replacement
___________________________________________________________________________
RECOMMENDATION:
That Tender T17-037 Lyle Hallman Pool – Air Handler Replacement, be awarded to
Carters Refrigeration Inc, St Thomas, Ontario, at their tendered price of $443,347.,
plus H.S.T. of $56,635.11, for a total of $500,982.11.
BACKGROUND:
Lyle Hallman Pool has been in operation for 26 years. Current air handlers (2) which
condition air in the main pool natatorium are in poor condition due extensive corrosion
influenced by naturally occurring chloramines within the natatorium atmosphere inherent
in pool operations. The condition of these units is starting to impact the air quality of the
pool natatorium by extension; impacting staff work environment and patron user
experience. These original units are inefficient and becoming very difficult and costly to
maintain.
This tender will replace the two current air handling units with a single energy efficient
unit which will provide more fresh air with heat recovery, air conditioning and
dehumidification. This initiative will enhance patron experience and staff workplace
safety. The work will be completed during the regular two week maintenance shutdown
in September 2017 to minimize patron disruption.
REPORT:
Tenders were advertised publicly in the Daily Commercial News, on the City of
Kitchener website and the internet through the Ontario Public Buyers Electronic
*** This information is available in accessible formats upon request. ***
Please call 519-741-2345 or TTY 1-866-969-9994 for assistance.
1. iii. - 1
Tendering Information System. Documents were downloaded by eighteen (18)
interested parties and by the closing date of Thursday February 9, 2017, six (6) tenders
had been received.
The tenders were reviewed by A. Berg, MNE Engineering Incorporated, the City’s
Consultant for the project, P. Christner, Building Operator and R. Scott, Buyer who
concur with the above recommendation.
The following tenders were received:
Bid Price
Carters Refrigeration Inc. St Thomas ON $500,982.11*
CJ’s Express Plumbing & Electrical Ltd. Cambridge ON $508,500.00
DNA Mechanical Inc. Vaughan ON $557,090.00
Brenner Mechanical Inc. Waterloo ON $571,220.65
Velocity Mechanical Inc. Kitchener ON $604,392.93
Rainbow Mechanical Services Limited Concord ON $637,757.20
ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN:
The recommendation of this report supports the achievement of the city’s strategic
vision through the delivery of core service.
FINANCIAL IMPLICATIONS:
The net cost for this tender (A), is fair and reasonable for a project of this scope and the
upset limit is within the funding available (B) for this project. Funding for this project is
included within the approved capital budget. The estimated surplus (D) will remain
within the account to fund other HVAC priorities at city facilities.
Financial Summary for Tender T17-037
Lyle Hallman Pool Air Handler Replacement
Estimated Cost
Tender T17-037 costs, including HST 500,982.11
less: HST rebate on tender (49,832.20)
Net Cost Being Awarded 451,149.91 A
Costs Incurred to Date -
Estimated Cost $451,149.91 C
Budget for this work:
Lyle Hallman Pool - HVAC 460,000.00
Total Budget: $460,000.00 B
Estimated Surplus (B - C) 8,850.09 D
1. iii. - 2
COMMUNITY ENGAGEMENT:
INFORM – This report has been posted to the City’s website with the agenda in
advance of the council / committee meeting.
PREVIOUS CONSIDERATION OF THIS MATTER:
Not applicable
ACKNOWLEDGED BY: Dan Chapman, Deputy CAO & City Treasurer, Finance and
Corporate Services
1. iii. - 3