HomeMy WebLinkAboutFCS-17-074 - E17-012 Consultant Serv - Hoffman St Reconstruction REPORT TO: Committee of the Whole DATE OF MEETING: 2017-04-24 SUBMITTED BY: Michelle Palmer, Director of Supply Services 519-741-2200 ext. 7214 PREPARED BY: Adam Buchholtz, Buyer, 519-741-2200 ext. 7217 WARD(S) INVOLVED: Ward 9 DATE OF REPORT: 2017-04-06 REPORT NO.: FCS-17-074 SUBJECT: E17-012 Consultant Services - Hoffman Street (Ottawa Street South to East End) Reconstruction ___________________________________________________________________________ RECOMMENDATION: That Expression of Interest E17-012 Consultant Services - Hoffman Street (Ottawa Street South to East End) Reconstruction, be awarded to Meritech Engineering, Cambridge, Ontario, at their estimated fee of $151,615.41, including contingencies of $13,783.22, plus H.S.T. of $19,710., for a total of $171,325.41, based on a satisfactory contract being negotiated and an upset fee being established. BACKGROUND: The Hoffman Street (Ottawa Street South to east end of cul-de-sac) reconstruction project (approximately 250 metres) has been initiated to address the infrastructure issues that currently exist. The infrastructure along Hoffman Street has reached the end of its useful life and requires full replacement. The project includes the reconstruction of all underground services (sanitary sewer, storm sewer and watermain) as well as sanitary and water service connections to the property line. The asphalt roadway will be reconstructed as well as sidewalks and curbs. This phase of the project is for consulting services to complete the preliminary design, final design, tendering, as well as contract administration and inspection. Construction is expected to occur in 2019. *** This information is available in accessible formats upon request. *** Please call 519-741-2345 or TTY 1-866-969-9994 for assistance. 1. ii. - 1 REPORT: In accordance with Chapter 170 of the Municipal Code pertaining to the Selection of Professional Services/Consultants, a Consultant’s Review Committee was established consisting of L. Costa, Design & Construction Project Manager, B. Garcia, Engineering Construction Project Manager, S. Morris, Engineering Graphics Technologist and A. Buchholtz, Buyer. Expressions of interest were advertised publicly on the City of Kitchener website and on the internet through the Ontario Public Buyers Association Electronic Tendering Information System relative to this project. Documents were downloaded by thirteen (13) interested parties and by the closing date of March 9, 2017, six (6) responses had been received. The review committee met on Friday March 17, 2017, to review the submissions and a shortlist of three (3) candidates* were selected for further interviews. The Committee met on Friday March 24, 2017 to interview the shortlisted candidates. The Committee recommends awarding the project to Meritech Engineering, Cambridge, Ontario. The Committee rated consultants on the following criteria: Evaluation of Proposed Project Manager Completeness of the Proposal Qualifications/Expertise Past Performance Knowledge of the City (re: this area) Amount of City Work Completed in the Past Proposed Project Team Effect of Interview Cost of Consultant's Fees Variety & Quality of Disciplines In House/In Consortium Effectiveness of work plan A listing of the responding parties follows for your reference: CIMA Mississauga ON IBI Group Waterloo ON * LEA Consulting Ltd. Markham ON Meritech Engineering Cambridge ON* MTE Consultants Inc. Kitchener ON* WSP Canada Inc. Markham ON *Shortlisted candidates 1. ii. - 2 ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN: The recommendation of this report supports the achievement of the city’s strategic vision through the delivery of core service. FINANCIAL IMPLICATIONS: In addition to the costs anticipated in this expression of interest, the design and implementation of these types of projects typically involves city staff and resources from across the corporation. These costs are included in the line item "Projected Costs: Staff Time/Permitting/Material testing", and will be itemized when they exceed $125,000. Included in this line item are staff time and expenses for all city staff in support of the project such as Engineering, Kitchener Utilities, and Transportation Planning. The line item also includes all regulatory permitting, geotechnical and material testing, detouring and traffic control, alternate access and parking requirements and any other miscellaneous costs. Projects utilizing in-house staff will include costs for inspection during construction and contract administration. The net cost for this Expression of Interest (A), is fair and reasonable for a purchase of this scope and the upset limit is within the budget allowance (B) provided within the budget. Funding for this purchase is included within the approved capital budget. The estimated surplus (E) will remain in the account and be used towards the construction phase of the project. Expression of Interest E17-012 Hoffman Reconstruction The total budget for all phases of this project is 1,533,431.00 Estimated Cost for this Phase of Work Expression of Interest E17-012 costs, including HST 171,325.41 less: HST rebate on Expression of Interest (17,041.56) Net Cost Being Awarded 154,283.85 A Projected Costs: Staff Time/Material Testing 66,974.00 Total Estimated Cost for this Phase of Work $221,257.85 C Budget for this Phase of Work AIRP - Sanitary Utility 107,712.00 AIRP - Storm Water Utility 53,856.00 AIRP - Water Utility 72,588.00 Total Budget for this Phase of Work $234,156.00 B Estimated Surplus for this Phase of Work (B - C) 12,898.15 D Estimated Surplus from previous phases 2,935.87 Total Estimated Surplus $15,834.02 E 1. ii. - 3 COMMUNITY ENGAGEMENT: INFORM – This report has been posted to the City’s website with the agenda in advance of the council / committee meeting. PREVIOUS CONSIDERATION OF THIS MATTER: Not applicable ACKNOWLEDGED BY: Dan Chapman, Deputy CAO & City Treasurer, Finance and Corporate Services 1. ii. - 4