HomeMy WebLinkAboutFCS-18-021 - 1st Quarter Audit Status ReportREPORT TO: Audit Committee DATE OF MEETING: March 19, 2018 SUBMITTED BY: Corina Tasker, Internal Auditor, 519-741-2200 ext. 7361 PREPARED BY: Corina Tasker, Internal Auditor, 519-741-2200 ext. 7361 WARD(S) INVOLVED: All DATE OF REPORT: March 12, 2018 REPORT NO.: FCS-18-021 SUBJECT:1st Quarter Audit Status Report ___________________________________________________________________________ RECOMMENDATION: No recommendation required. The following information is being provided as an update and assurance on internal audit matters, in accordance with the Audit Committee Terms of Reference. BACKGROUND: The following report provides a summary of the Internal Audit activities completed during the period of December 2017 to February 2018. The chart below shows the audits contained in this report. Division / Topic Scope Fire Administration Process / capacity review By-law Enforcement, Property Standards Process / capacity review SAP User Access Separation of duties Kitchener Utilities Risk assessment The following items are currently in progress and will be brought forward at a future audit committee meeting: Winter Maintenance, comprehensive audit Use of Consultants / Professional Services, value for money audit *** This information is available in accessible formats upon request. *** Please call 519-741-2345 or TTY 1-866-969-9994 for assistance. 1 - 1 REPORT: 1. Fire Administration, Process / Capacity Review Status: Complete, January 31, 2018 Background Information: The Fire Administration division supports the administrative needs of the Kitchener Fire Department. It consists of five full time staff. They provide a range of services including general administrative support for management, payroll and financial transactions, meeting coordination, program specific support for Direct Detect, training, and fire prevention, and a variety of other tasks. Objectives: Workload has been an ongoing issue in the division. Conducting a workload analysis of the Administration division is 1 of 35 strategic and operational actions in the Fire Master Plan and the catalyst for this Lean process review. The goal of this review was to determine if improvements could be made to streamline processes and increase capacity. A secondary objective was to look at the distribution of tasks between the five administrative roles to ensure the most effective groupings of like tasks and to smooth workload pressures between all staff. Methodology and Scope This review incorporated the following elements: Literature review of current job descriptions Consultation with staff and internal stakeholders (including Fire management, platoon chiefs and assistant platoon chiefs) Workload / capacity assessment with a focus on distribution of tasks across roles Lean process review for seventeen (17) selected administrative processes, which included: o Current state value stream mapping to identify sources of waste, problem statements and root causes o Future state value stream mapping to identify and quantify potential solutions o Implementation planning o Three rapid improvement events to implement identified solutions related to three different processes This project excluded: Lean process reviews for all administrative processes (32 processes were not reviewed due to time constraints) 1 - 2 Lean Process Review Outcomes: The goal of a Lean process review is to eliminate or reduce non-value-add process steps. A non-value-add process step is any step in the process that the customer (internal or external) does not receive value from, is not done right the first time, and / or does not transform the product or service in some way. Through the course of the current state mapping of the 17 selected processes, staff identified 49 problem statements or non-value-add process steps. All of the problem statements were further analyzed to determine root cause and to brainstorm possible solutions and improvements. A total of 139 different solutions were generated and the qualitative and quantitative impacts of each solution were estimated. All potential solutions were then prioritized based on ease of implementation and total impact (qualitative and quantitative) and input to an implementation plan. Three of the processes and associated problem statements and actions were chosen to be implemented immediately during three rapid improvement events. Management is responsible for taking the lead on facilitating additional rapid improvement events to ensure the remaining actions are implemented in a timely fashion, as per the agreed upon implementation plan. One of the main issues that were solved through this process was a lack of clarity around customer expectations. At the outset of the Lean review key stakeholders / customers were interviewed to gain a better understanding of their administrative needs and what service attributes they value. This helped to identify which process steps were not adding value to these internal customers. Also, by having Fire management participate in the rapid improvement events it allowed staff and management to openly discuss service requirements and brainstorm solutions together. The solutions are expected to save approximately 135 hours per year of administrative staff time and they will provide better customer service to Fire staff and management. Staff and management are supportive of this process and are enthusiastic about implementing the improvements. Recommendations: In order for the continuous improvement momentum to be sustained within the Fire Administration division, it is recommended that: •Management regularly monitor the status of the Lean implementation plan and hold themselves and staff accountable for actions assigned to them. •Management communicate with staff regarding progress on the Lean implementation, involve staff in carrying out the plan, assist staff in making time to work on these actions, and explain any barriers to implementation. 1 - 3 • Once the Lean implementation is complete, begin a Lean review on the remaining processes to look for new problems, root causes and solutions to implement. • Recognize staff that embrace the Lean method and encourage a continuous improvement culture. • Share Lean and continuous improvement success stories within the division and with the corporation. Capacity Analysis: One of the deliverables in this review was to analyze the current capacity in the division to determine if changes are required to the distribution of work between the five roles. This included looking at current workload, proposed time savings from the Lean improvements, and actual staff available hours. Data were gathered for the average amount of time required to complete each of the 49 administrative processes and the frequency that each is performed. The total time required was then compared to the time available for each person. This incorporated their regular working hours, statutory holidays and floaters, actual vacation entitlement, and an estimate for sick days. Staff was also asked if they regularly worked overtime to complete their tasks. This provided a picture of current capacity. The estimated savings from the Lean review were then factored in to determine what impact these changes would have on the overall picture. The initial calculations show that overall the section of five full time staff are currently over capacity by 705 hours per year or roughly 0.5 full time equivalents (FTE). This deficit of hours is concentrated mainly in two positions. The staff work, on average, 409 hours of paid overtime per year which equates to $12,800 of extra costs. They also regularly do not take breaks or full lunches in order to accomplish their workload. This is unpaid overtime that equates to 487 hours or $14,900. While the Lean process review did reveal many improvements that could be made to processes to improve customer satisfaction, the 135 hours per year in time savings for administration staff is not adequate to completely address this deficit. Having to regularly work overtime or not take breaks is stressful for staff and affects work/life balance and morale. This is not sustainable in the long term. In addition, the Emergency Management and Public Education programs do not currently have any administrative support. As these programs expand, it is anticipated that at least 260 hours per year of administrative services will be required. There were however, two existing processes which will cease to exist or will require less time in the future. The current capacity less the Lean improvement savings, less the tasks that have been eliminated, plus the additional time required to support Emergency Management and Public Education will put the division in a deficit position of 602.5 hours per year or 1 - 4 roughly 0.4 FTE (assuming no paid or unpaid overtime worked by staff). This equates to a part time position that would work 14 hours per week. Not factored into this calculation are the potential Lean improvement savings for the remaining 32 processes and expected efficiencies from the installation of a new records management system. As mentioned previously, a goal of this review was to smooth out workload between staff. Staff and management worked with the project team to rearrange the distribution of tasks such that the workload is more evenly distributed and tasks are logically grouped together. While this exercise was successful in grouping like tasks and spreading some of the workload to those positions with surplus capacity, it does not erase the fact that there is more work than there are hours to complete it. Recommendations: Although it was not a goal at the outset of this review to recommend more staffing, the current deficit is not sustainable and is affecting staff morale. However, the impacts of the Lean improvements have not been realized yet nor have all processes been reviewed yet. It is therefore recommended that a temporary part time staff be hired for an 18-month period to help alleviate workload, overtime and reduce stress levels in staff in the short term. This resource will also allow staff to continue implementing the Lean improvements and begin work reviewing the remaining 32 processes. Having additional resources will also allow service requirements for Emergency Management and Public Education to be better defined through experience and experimentation. Throughout this time a new records management system will be installed which may lead to additional time savings. During the temporary contract management should not approve any overtime and should also ensure that staff are taking all lunches and breaks. At the end of the temporary contract it is anticipated that this additional resource will no longer be needed as the efficiencies from process improvements, system installations and removal of tasks will make the workload manageable within the existing complement. 1 - 5 Conclusion: This review looked critically at a variety of Fire Administration processes, and the resulting recommendations are focused on enhancing effectiveness and efficiency, reducing waste and increasing capacity. Only a portion of the administrative processes were reviewed and therefore there may be even greater unrealized improvements waiting to be discovered in the future. Staff should embrace the culture of continuous improvement and use the skills learned through this process to continue to improve their processes. 2. By-law Enforcement, Property Standards, Process / Capacity Review Status: Complete, January 31, 2018 Background: The Property Standards team in the By-Law Enforcement division is responsible for inspecting sites, investigating situations and gathering evidence concerning the maintenance and occupancy of lands and buildings within the city, including complaints about the following topics: Property standards Zoning Snow / ice Lot maintenance / grass / weeds Signs / graffiti Sight obstructions Fences Vacant buildings Animals Lack of heat Their service is mostly reactive in response to citizen complaints, although there are a few areas in the City that receive proactive monitoring. Earlier in 2016 Council had taken an interest in exploring the idea of proactive enforcement and had requested a service review be conducted. Prior to starting this review staff had engaged with residents to obtain their feedback on the issue. In report CSD-17-060 staff concluded that additional resident education and changes to the property standards by-law could help better serve citizens and proactive enforcement was not required at this time. Objective: The primary focus of this property standards section review was to conduct a Lean process review to determine existing capacity and calculate the estimated impact on staffing if a more proactive approach was taken. Included in the Lean review was the 1 - 6 goal of identifying and implementing any process improvements which could provide better customer service and / or reduce non-value added tasks, and thereby increase capacity. Methodology and Scope: This project included the following components: Literature review of relevant documents, e.g., job descriptions, standard operating procedures Consultation with By-law Enforcement property standards staff and Council Workload / capacity assessment Lean review including o Current state value stream mapping to identify sources of waste, problem statements and root causes o Future state value stream mapping to identify and quantify potential solutions o Implementation planning This project excluded: All other By-law Enforcement units (noise, trails/school zones, parking) Findings: An important part of this review was to interview members of Council to clarify what was meant by proactive enforcement in order to be able to quantify the resource requirements to implement such an approach. It was found that Council felt By-Law Property Standard Officers were doing a great job enforcing the current property standards by-laws andseven of the eleven councillors feel that the city currently provides the right amount of by-law service. When asked whether they would support a more proactive approach to enforcement, six councillors did not support it, three did, and two only supported it for specific areas such as Downtown or Conestoga College. It can be concluded there is no new work or service level required at this time as Council as a whole is not supportive of investing resources in a proactive approach. Although the majority of Council did not support a patrol based proactive approach to by-law enforcement, many had suggestions of other actions that could be taken to improve the process and service level to citizens. Staff has indicated that they currently are performing these actions in some form or another as listed in the chart below: 1 - 7 Proactive Approach Idea Response 1 Targeted patrol based Already do this in Downtown and Conestoga approach to designated areas College areas like Downtown and Conestoga Already observe adjacent houses in all areas to College see if there are obvious problems Each area has its own ‘neighbourhood watch dogs’ to report activities Staff don’t feel additional patrols are required unless there is an additional problem area that Council would like patrolled 2 More follow-up (weekly basis) Staff do follow-up with repeat offenders, with repeat offenders to however this is not done weekly ensure continued compliance If this was moved to weekly follow-up, it takes time from other files, staff incur extra mileage costs, and there is no time for the offender to bring it into compliance Each of seven officers typically has four or five repeat offenders 3 More education / public Already do this, e.g., Neighbours Day at outreach regarding seasonal community centres, fire station open house, topics such as grass / snow / police week open house, Conestoga College fences etc. house-by-house campaign, booths at big box stores (for fences / decks) New “thank you” campaign through social media to thank people for not parking on the streets Neighbourhood guide Media campaign (radio, print) – sidewalks, parking Pool safety package given with pool permits Radio / news shows on hot topics Walk-abouts with information on rats in problem areas Want to go to more big box stores, but these are done on weekends and require overtime 4 Divert resources from parking Takes away parking revenue to property standards by Increase in parking complaints splitting one parking position Tried before when there was a lull in lot to be focused 50% on parking maintenance work and it did not work (not and 50% on property enough time each day to do both) standards No lull in lot maintenance work anymore 1 - 8 Lean Process Review Outcomes: Staff and management participated in a Lean review of the investigations process which consumes most of the officers’ time. This process is highly regulated and only 4 non- value-add process steps were found. Process improvements were minimal and did not save any time. Since a proactive approach is not recommended, no additional work was required to map out the future state of what that approach would look like. Staff discussed the lack of coverage for absences (i.e. when an officer is off for vacation, training, or sick leave their files or geographic territory are not actioned by other officers in their absence unless it is an emergency). In order to ensure consistent and continual service to citizens staff will be developing an absence coverage model. Capacity Analysis: One of the deliverables in this review was to analyze the current capacity to determine if resources are sufficient to support current and future demand for the next five years. In addition, if any service level enhancements or process improvements were recommended, the associated capacity implications would be calculated. Capacity is a function of service levels, demand for service, and available staff hours. Staff indicated that they try to acknowledge each complaint within 24 – 48 hours. They also try to complete the initial inspection within 24 – 48 hours; however, this may take longer during peak periods. Work is divided between staff based on geography and type of complaint. Therefore, when staff is absent (for vacation, sick time, or other absences) their case load and new calls are on hold until their return. As mentioned previously, service is primarily complaint based with proactive monitoring within two problem areas of Downtown and Conestoga College. There are no recommendations in this report to increase this service level or approach. However, implementing absence coverage will help avoid gaps in service and improve response time. Demand for by-law services has many drivers (such as weather, police presence, by- law education etc.) based on the type of infraction. Many types of violations are driven at least partially by population. As the population grows there will be more citizens who could commit by-law infractions, driving demand for by-law services up over time. Population growth was extrapolated to provide a prediction of future population levels. The total number of complaints was then correlated to population during that same period to show the expected growth in demand. This in turn was used in the future capacity calculations to indicate resources required. 1 - 9 YearPopulationComplaints 2012225,3742,238 2013240,4572,382 2014261,1242,259 2015275,9212,290 2016294,5362,482 2017311,6192,446 2018328,9982,484 2019346,3762,523 2020363,7542,561 2021381,1322,600 FuturePredictions 500,0002,700 2,600 400,000 2,500 300,000 2,400 Population 2,300 200,000 2,200 Population Complaints Complaints 100,000 2,100 2,000 20122014201620182020 In addition to population growth, the increase in communication channels that citizens can use to make complaints to the city (such as the new online portal) will further increase demand for by-law services. Information provided by human resources shows that headcount in this section has only grown by one part-time position over the past five years (6% growth), while population has grown by 38% and number of by-law complaints has grown by 9% during that same period. Population is expected to grow by 22% over the next 5 years and by-law complaints should grow by 6%. A high-level assessment of workload and capacity was undertaken by the project team to provide a baseline estimate of capacity across the section. Data was gathered during the value stream mapping regarding the typical amount of time required to complete each type of by-law complaint from start to finish. Note that every complaint is different and could take more or less than the typical time. Each complaint can take one of four paths, each with a different total time to complete: 1. Complaint is investigated but there is no violation 2. Violation and the citizen complies within the deadline 3. Violation and the citizen appeals (for property standards complaints only) 1 - 10 4. Violation and the citizen does not comply, and the City proceeds with clean-up The time-per-complaint estimate was then multiplied by the total number of complaints or violations as appropriate for each type and each path. The total time required to meet demand was then compared to the time available based on eight staff members in the section. This incorporated their regular working hours, statutory holidays and floaters, actual vacation entitlement, and an estimate for sick days. Staff was also asked if they regularly worked overtime to complete their tasks. Staff typically work between 96 – 225 hours of overtime per year. However, this is largely to respond to after-hours emergencies. The time is banked and taken off at another time, rather than being paid. Some staff claim paid overtime occasionally to catch up on paperwork after absences. This amount is less than $2,000 per year. Capacity Projections: Year 20172018201920202021 Currentavailablestaffhours11,97011,97011,97011,97011,970 Projected#ofcomplaints24462484252325612600 Estimatedtotalhoursrequired18,80319,09519,38619,67719,969 CapacityDeficit6,8337,1257,4167,7077,999 FullTimeEquivalents(FTE's)3.753.914.074.234.40 The analysis shows there is a lack of capacity to complete all required work. This conclusion is further supported by the response time of 24-48 hours. The estimate for 2017 shows a total capacity deficit of 6,833 hours or roughly 3.75 FTEs. This figure grows to 4.4 FTEs by 2021. Given that some of the time estimates may be high since some cases may take less time than the typical amounts used, it is estimated that at least two FTEs are required over the next 5 years in order to maintain current service levels. An analysis of the number of violations by type by year indicates that snow and ice complaints consistently make up 35% or more of all violations. The next largest categories are grass, weeds and lot maintenance at 31%. However, an analysis of the time required to action these calls by type reveals that property standards and zoning complaints consume the most resources, at 28% and 20% respectively. 1 - 11 Category%oftotalhours%oftotalviolations Propertystandards28%12% Zoning20%9% Snow/Ice14%35% Lotmaintenance/grass/weeds10%31% Signs/Graffiti7%9% Sightobstruction6%2% Fence2%1% Vacantbuilding1%1% Animal1%0% Heat1%0% Initialinvestigationtime10% Total100%100% If staff wish to decrease the number of calls and demand for service, they should focus their education efforts in those four areas. Recommendations: In order to maintain current service levels in light of population growth it is recommended that: By-law enforcement management team should request an additional two FTEs, phased in over the next 5 years. This allows staff to keep pace with demand. This will also provide staff more time to follow up with repeat offenders and pro- actively patrol problem areas as desired by Council. If staffing is not increased, their response time will increase to greater than 48 hours. By-law enforcement management team should focus education efforts in the areas that show a high volume of calls and high time spent handling specific types of calls. Conclusion: In conclusion, it was found that minimal improvements can be made to the by-law enforcement investigations process and no time savings have been found. It is not recommended to change the approach or service levels at this time. It is also recommended that additional FTEs be requested to support existing and future demand for services. 1 - 12 3. SAP User Access, Separation of Duties Status: Complete, February 23, 2018 Background: It was noted during the comprehensive review of the Accounting division that several SAP users have full access to all functions within the system. This is a separation of duties conflict and presents the opportunity for fraud or unintended consequences. It was recommended at that time that Internal Audit and the SAP Business Solutions Business Analyst (Finance) work together on a separation of duties analysis of all SAP users, with an initial focus on the users which currently have “ALL” access to determine whether they have a business need to access all SAP functions. Objective: The objective of this audit was to determine the high risk SAP separation of duties scenarios and determine if any users have access that permits these conflicts. Users and their supervisors were then contacted to determine if the access can be removed or whether the corporation will accept the risk and try to mitigate it in some way. High risk is defined as the ability for an individual to use their SAP access to create transactions which would: Allow them to steal funds from the corporation, either individually or in collusion with vendors / suppliers / customers Allow them to misrepresent the corporation’s financial situation Methodology and Scope: A list of high risk scenarios was developed based on the SAP separation of duties matrix, online research related to top SAP separation of duties risks, and prior controls audits in Supply Services, Accounting and Revenue. SAP Business Solutions staff then reviewed all active SAP user ID’s to determine if conflicts exist. The list of conflicts was reviewed with Internal Audit, and users and their supervisors were contacted to determine if access is required in order to do their jobs. Accounting and Supply Services management was consulted regarding existing controls to mitigate any unavoidable scenarios. Findings: “ALL” access has been removed from all users except the SAP Business Solutions and Technology and Innovation staff who need this access in order to be able to trouble shoot and resolve problems. There are however several user ID’s which still have more access than they require for their role. While there is no evidence of fraud, the potential is there if these separation of duty conflicts are not removed or mitigated. In some cases the City has accepted the risk, given that Kitchener is a mid-sized city and unable to have complete separation of duties in all staff roles. For all other cases SAP Business Solutions is working on removing the unneeded access. 1 - 13 Recommendations: Remove all unnecessary access (contact users prior to removing access) Ensure support availability following the removal of the access in case it is found that it is required for other tasks. Run a report semi-annually to ensure that no unauthorized transactions or changes to the system are made Remind and ensure SAP Business Solutions and Technology and Innovation staff who post journal entries to have their journal entries approved by management and file the backup in the Accounting file room Create a process to review required access when users change positions within the corporation. Perform an annual check of system access to ensure no conflicts, or that conflicts are documented with valid rationale and supporting mitigating controls 4. Kitchener Utilities, Risk Assessment Status: Complete, February 20, 2018 Background: Risk is defined as the effect of uncertainty on objectives. The management of risk involves regularly and proactively scanning the organization and the environment to identify, assess, and treat potential risks to ensure the achievement of goals or objectives. The last risk assessment performed in Kitchener Utilities was done in 2010. Objective: To conduct a risk assessment of the Kitchener Utilities division in order to identify and assess current risks that could affect the achievement of goals. This will provide a roadmap for new management as to where to place focus, and identify areas for deeper review. Methodology: This assessment followed these steps: Review of 2010 Kitchener Utilities risk assessment Interviews with a sample of Kitchener Utilities staff and management Interviews with a sample of stakeholders including Revenue, Supply Services, Engineering, GIS, Support Services, and Financial Planning Workshop to jointly assess the likelihood and impact of each risk identified during the interviews Findings: Staff and stakeholders identified and then assessed several distinct risks. The risks were then sorted based on total risk score, which is the multiplication of the likelihood 1 - 14 score by the impact score. The result is a prioritized list of risks which management will now work to create treatment plans for. Treatment can take the form of avoidance, reduction, transference or acceptance of risks. The risks that were identified fall into the seven corporate risk categories, specifically: Service delivery risk – the risk of not meeting customer expectations Employee risk – the risk that employees or contractors at the City will be negatively impacted including physical harm, morale, workload, etc. Public risk - the risk that there will be a negative impact on the public, including physical harm, loss of service, financial, etc. Physical environment risk – the risk that the environment will be damaged Reputation risk – the risk associated with anything that can damage the reputation of the City or undermine public confidence in it Financial risk – the risk related to decisions about assets, liabilities, income, expenses including asset management, capital and operational funding, economic development, theft and fraud Regulatory risk – the risk related to the consequences of non-compliance with laws, regulations, policies, or other rules Two of the largest underlying issues that were identified and which lead to numerous risks or consequences are: 1. Staffing has not kept pace with growth in population and the customer base; and 2. Data that staff relies on to do their work is out of date or incorrect. The data being out of date is also a consequence of the staffing not keeping pace with growth, but in and of itself leads to a host of other risks. If the division can resolve these two issues, a lot of the related risks will diminish in likelihood of happening. It will be up to management to monitor the risks and ensure timely mitigation of the highest risks. ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN: This report supports the achievement of the city’s strategic vision through the delivery of core service. FINANCIAL IMPLICATIONS: There are no financial implications related to this report. COMMUNITY ENGAGEMENT: INFORM – This report has been posted to the City’s website with the agenda in advance of the council / committee meeting. 1 - 15 ACKNOWLEDGED BY:Lesley MacDonald, Acting Deputy CAO, Finance and Corporate Services 1 - 16 Committee 2018 19, Audit March Quarter First 1 - 17 STATUS AUDIT 021 QUARTER 18 ST FCS 1REPORT 1 - 18 for review review audit value duties capacity capacity / of / Services, assessment comprehensive ΑƦƩƚĭĻƭƭ ΑƦƩƚĭĻƭƭ ΑƩźƭƉ Summary ΑƭĻƦğƩğƷźƚƓ Professional / Utilities Access Maintenance, Enforcement User Administration law progress: Fire BySAPKitchenerWinterConsultantsmoney Complete:In 1 - 19 Review ADMINISTRATION Capacity / Process FIRE 1 - 20 five in between processes decrease / item workload capacity the action Objectives staff administrative Plan pressures increase distribute to Master streamline workloadEvenlyadministrativeFire Toorder ••• 1 - 21 6 customers documents and events assessment internal staff planning mapping mapping review with Methodology capacity relevant / state improvement state of process rapid CurrentFutureImplementation3 –––– ReviewConsultation(management)LeanWorkload •••• 1 - 22 Lean them of apply may Review techniques processes they the reviewed Lean be that staff processes to processes of so all yet teach administrative to reviews cover Scope remaining was not selectedprocesses the Goalto 17Did32process •••• 1 - 23 staff not is and , transform it steps prioritized not from does implement process or value to / management Outcomes quantified, to and added receive savings events performed of time, not value service first service Review year does generated, / non the analysis per 49 right improvement Lean customer product customer cause solutionshours i.e.donethe rapid – IdentifiedRoot139 3solutions135Better •••••• 1 - 24 for plan improvement processes 32 support continuous and remaining for progress stories implementation time staff Recommendations Lean staff success reviewing CommunicateProvide MonitorimplementationBeginRecognizeShare •••••• 1 - 25 10 the the to system between and capacity process service of staff workload in Analysis the staff impacts available change service the Capacity future distribute for administrative compareevenlypredict improvements, TodemandTofiveToupgrades ••• 1 - 26 11 to holidays, required sick, (time less Calculation vacation, capacity of work*) include at deficit Capacity work) or hours hours Surplus (Actualcomplete=*Actualfloater 1 - 27 12 FTE 0.5 = year year) year), positions per staff per hours two to hours in through: hours (487 fair 705 Findings or (409 of breaks currently or deficit concentrated overtime lunch sustainable paidno –– OverallDeficitAddressedNot •••• 1 - 28 13 simplify and Waterloo Emergency / to tasks system Come support support implemented Education to identified Public technical statistical programs to management of Changes improvements tasks eliminate recordsimprovementssupport Willother – NewEliminationProcessNewNewManagement ••••• 1 - 29 14 time equivalents(0.4) management processes 32 yearFull records Changes new of Hoursper 131.5(260.0)(602.5) remaining quantified) of from (not installation come: savings Waterloo114.0 to from for Lean still of gained Summary capacity savings improvement support round1 term technicalsupport116.5statisticalsupport Capacity(704.5)(0.5) from ProcessEfficiencies system program Additional•• Current RemoveRemoveSavingsimprovementsAdd Newshort 1 - 30 15 the out months overtime improvements 18 ΑƭƦƩĻğķ for Lean tasks unpaid roles on or like time workload focus paid / part group between stress and Recommendations tasks continued approve temporary not AlleviateAllow –– Do HireRealignworkload ••• 1 - 31 and increasing and efficiency additional waste, for continuous savings enhancing on and Conclusion reducing potential embrace still focused is should effectiveness, ReviewcapacityThereimprovementsStaffimprovement ••• 1 - 32 Review ENFORCEMENT Capacity / LAW Process BY 1 - 33 of citizens obtain to impacts education serve law the by better residents to additional explore with to laws proactive by Background approach to more engaged concluded Council a by to staff report changes law movingfeedbackStaff RequestenforcementByand ••• 1 - 34 19 / zoning, of signs buildings, (noise, impact standards, weeds, unit approach / vacant the units Scope grass property active fences, and explore pro about: Enforcement and heat enforcement more maintenance, a parking) of obstructions, lot law complaintslack capacity sight Standards by ice, Objectives / Scope: other assess Includessnowgraffiti,animals, of • ToimplementingPropertyAlltrails/schools, ––– Objectives:Scope:Out ••• 1 - 35 20 generation Council documents solution map map ͻLƓǝĻƭƷźŭğƷźƚƓƭͼ and and of assessment stream internal stream staff value value review with Methodology capacity relevant identification / state state of process CurrentFutureProblem ––– ReviewConsultationLeanprocessWorkload •••• 1 - 36 21 which of all provide proactive enforcement and of though, form Findings team a service proactive as some supportive in service not improved doing prohibits together for whole work well a already customer ideas Consultation of as are work Severalstaff – StaffexcellentVolumeCouncilenforcement ••• 1 - 37 22 if capacity eliminate in proactive use and of for Objective tasks recommended impact not add process is Review value this quantify as current to non Lean need QuantifyanalysisIdentifypossibleNoapproach ••• 1 - 38 and ΑƓƚ absences minimal process for model found Outcomes were tasks coverage coverage of Review investigations new added lack out improvements regulated value Lean savings develop non MappedHighly4ProcesstimeDiscussedwill •••• • 1 - 39 24 the to in capacity growth Objective of staff impacts available Analysis service the future for Capacity comparepredict TodemandTodemand •• 1 - 40 25 / of vacation level hours areas the 48 24 possible providing specific if of in improve / within Levels coverage hours only 48 exception 24 increase complaintabsence the to / Service monitoring not within coverage with site vacation AcknowledgeVisitProactiveNoDecisionservice,absence ––––– Current:Future: •• 1 - 41 26 in more drive growth will by also cases Service most for channels in years: 5 9%6% driven next in years: 5 6% 38%22% Demand communication demand past complaintsgrowth complaints in in in PopulationBylawHeadcountPopulationBylaw ––––– IncreasepopulationIncreasedemandGrowthExpected • ••• 1 - 42 27 and type each for Time complaint up one compliesappeals complaints required cleans Cycle of # citizencitizenCity time X = complete time to violation NoViolation,Violation,Violation, –––– TimeCycleoutcome •• 1 - 43 28 time overtime. of required year per Capacity minus hours ΑЋЋЎ hours 96 11,97011,97011,97011,97011,97018,80319,09519,38619,67719,969 include not Available Does Year20172018201920202021 AvailablehoursTimerequiredNet(6,833)(7,125)(7,416)(7,707)(7,999) • 1 - 44 29 at calls years will 5 more by time to next estimates, the lead capacity response over turn incorrect in available Analysis added, demand) could required possible not 2017 2021 are add in for in exceeds which staff FTE FTE FTE 2 value 3.754.4 more –– DemandapproximatelyAdjustingleastIfworsen,(non ••• 1 - 45 30 decrease to hours: areas most Analysis violations: the (28%) these most spent in (31%) the time (35%) Standards consumingwith Additional Ice weeds (20%) and / / education PropertyZoningSnowGrass –––– volume CategoryCategoryFocus ••• 1 - 46 high levels: with required service topics effort on years 5 current high efforts next and over calls maintain Recommendations of to staff education 2 order AddFocusvolume –– In • 1 - 47 ACCESS Duties of USER Separation SAP 1 - 48 to with jobs access users their SAP ǒƭĻƩƭ͸ for all of conflict needed uncovered review duties Background than of audit conflicts no access Separation – AccountingmoreRecommendedensure •• 1 - 49 have of statements users if create separation to financial conflicts of SAP determine conflicts ability these risk would: as and Objectives funds high that of permits mitigate defined or theftmisrepresentation that scenarios risk determine AllowAllow –– TodutiesaccessRemoveHightransactions ••• 1 - 50 access if determine L5͸ƭ scenarios user risk SAP conflicts, high are Methodology of active list all there required DevelopReviewWhereis ••• 1 - 51 and required except than users Technology all access and from more Findings with Solutions removed staff users access Business ͻ!\[\[ͼSAPInnovationSeveral •• 1 - 52 job approval transition during changes during access management system access on get annually review to availability to report review entries Recommendations unnecessary required this support process annual journal staff RemoveEnsureSemiAllonCreatechangeRepeat •••••• 1 - 53 UTILITIES Assessment Risk KITCHENER 1 - 54 each of identify to impact 2010 and from assessment Methodology risk staffstakeholders likelihood a and ofof assessment risks assess risk conduct to samplesample current to prior Objective assess InterviewInterviewWorkshop Reviewrisk Objective:and Methodology:•••• 1 - 55 risks score growth risk with several total pace date issues: on of kept Outcomes assessed out not is based and has data underlying risks StaffingSome –– IdentifiedSortedLargest ••• 1 - 56 risks deeper high ensure to for for and used areas accept) be risks or created and Steps will be risks areas will monitor transfer, Next of to focus plans list reduce, mitigation determinereviewTreatmenttimely Prioritized(avoid,Management ••• 1 - 57