HomeMy WebLinkAboutFIN-18-023 - T18-088 Sandrock Greenway Pedestrian Bridge ReplacementREPORT TO:Committee of the Whole
DATE OF MEETING:2018-08-27
SUBMITTED BY:Laurie Stecho,Supervisor of Purchasing,519-741-2200 ext. 7089
PREPARED BY:Steve Rudak,Buyer,519-741-2200 ext. 7213
WARD (S) INVOLVED:Ward7
DATE OF REPORT:2018-08-07
REPORT NO.:FIN-18-023
SUBJECT:T18-088 Sandrock Greenway Pedestrian Bridge Replacement
__________________________________________________________________________________________
RECOMMENDATION:
That Tender T18-088 Sandrock Greenway Pedestrian Bridge Replacement, be awarded to
Engineered ConcreteLimited, Kitchener, Ontario, at their tendered price of $220,120.,
including provisional items and contingencies of $26,500., plus H.S.T. of $28,615.60, for
a total of $248,735.60.
BACKGROUND:
The City of Kitchener owns andoperates 65 pedestrian bridges of various design and conditions
located across the city. The city conducts regular maintenance inspections as well as bi-annual
engineering inspections guided by the Ontario Structure Inspection Manual (OSIM).
Sandrock Greenway Pedestrian Bridge (Bridge ID 863) is a concrete double tee bridge installed
in 1979. The structure was identified for further investigation and monitoring due to observation
of structural concrete cracking. The follow up investigation undertaken overthe fall and winter
of 2017 concluded that based on the age of the structure, the progressive concrete cracking,
present value of the bridge, and short/long term cost-benefit analysis, replacement of the bridge
in its current location is the preferred rehabilitation method.Ultimately, the precast concrete
structure reached the end of its lifespan and is beyond the point of repair.
The bridge was closed immediately for public use in January 2018 in preparation for removal
and replacement in the fall of 2018with the bridge being re-opened October 30, 2018.
***This information is available in accessible formats upon request. ***
Please call 519-741-2345 or TTY 1-866-969-9994for assistance.
1.ii - 1
REPORT:
Tenders were advertised publicly on the City of Kitchener website. Documents were downloaded
by twenty eight (28) interested parties and by the closing date of July 31, 2018, five (5) tenders
had been received.
The following tenders were received:Bid Price
Engineered ConcreteLimitedKitchener ON$248,735.60*
2220742 Ontario Ltdo/a Bronte ConstructionOakville ON$302,444.50
McLean TaylorConstruction Limited$321,941.07
CSL Group LtdAncaster ON$322,163.00
Coco Paving Inc.Hannon ON$326,488.64
The tenders were reviewed by M. Parris, Landscape Architect,who concurswith the above
recommendation.
ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN:
The recom
the delivery of core service.
1.ii - 2
FINANCIAL IMPLICATIONS:
The net cost for this Tender(A), is fair and reasonable for a project of this scope and the upset
limit is within the funding available (B) for this project. Funding for this project is included within
the approved capital budget. The estimated surplus (D) will be used for further bridge repairs
and maintenance across the city.
T18-088
SandrockGreenway Pedestrian Bridge Replacement
Estimated Cost for this Phase of Work
Tender T18-088 costs, including HST248,735.60
less: HST rebate(24,741.48)
Projected Costs: Staff Time/Permitting/Signage-
Total Estimated Cost for this Phase of Work$223,994.12 C
Budget for this Phase of Work
Pedestrian Bridge Capital Account250,000.00
Total Budget for this Phase of Work250,000.00 B
Estimated Surplus/(Deficit) for this Phase of Work (B -C)26,005.88 D
Estimated Surplus/(Deficit) from previous phases-
Total Estimated Surplus/(Deficit) $ 26,005.88 E
COMMUNITY ENGAGEMENT:
INFORM This report has been posted
council / committee meeting.
ACKNOWLEDGED BY: Jonathan Lautenbach, Chief Financial Officer, Financial Services