HomeMy WebLinkAboutFIN-19-016 - T19-001 Road Improvements, Road Surface Construction, Miscellaneous Asphalt and Concrete WorkREPORT TO:Committee of the Whole
DATE OF MEETING:2019-03-04
SUBMITTED BY:Margaret Fisher,Director of Procurement,519-741-2200 ext. 7214
PREPARED BY:Amy Carr,Buyer,519-741-2200 ext. 7184
WARD (S) INVOLVED:Wards 1, 2, 3, 4, 5, 6, 8, 9and10
DATE OF REPORT:2019-02-19
REPORT NO.:FIN-19-016
SUBJECT:T19-001 Road Improvements, Road Surface Construction,
MiscellaneousAsphalt and Concrete Work
__________________________________________________________________________________________
RECOMMENDATION:
That Tender T19-001Road Improvements, Road Surface Construction, Miscellaneous
Asphalt and Concrete Work, be awarded to Ekum-Sekum o/a Brantco Construction,
Cambridge, Ontario, at theirtendered price of $5,734,513.27,including contingencies of
$250,000.,plus H.S.T. of $745,486.73, for a total of $6,480,000.
BACKGROUND:
The main scope of work under this tender consists of various types of road rehabilitation on pre-
determined city streets.This contract also includesthe placement of surface asphalt on newly
constructed streets coming offtwo-yearmaintenance warranty,larger scaleutility cuts,
community trail rehabilitation, City facility parking lot remediation and miscellaneous asphalt and
concrete work for other departments.
assessment.This tender includes a variety of work and projects spread across the City, but the
works are similar in nature. This approach reduces our staff time and makes the administration
more streamlined.
The workisscheduled to begin April 1, 2019, weather permitting. The anticipated completion
date is October 31, 2019. Attached isa fulllist of projectsto be completed under this tender.
REPORT:
Tenders were advertised publiclyonthe City of Kitchener website. Documents were downloaded
by sixteen (16) interested parties and by the closing date of Wednesday February 13, 2019, five
(5)tenders had been received.
***This information is available in accessible formats upon request. ***
Please call 519-741-2345 or TTY 1-866-969-9994for assistance.
1.ii - 1
The following tenders were received:
Bid Price
Brantco ConstructionCambridgeON$6,480,000.00*
Steed and Evans LimitedSt. JacobsON$7,602,888.60
Coco Paving Inc. PetersburgON$ 7,665,920.01
Capital Paving Inc. Guelph ON$ 8,643,200.19
E.& E. Seegmiller LimitedKitchener ON$ 8,664,800.45
The tenders were reviewed by R. Trussler, Engineering Construction Project Manager, who
concurswith the above recommendation.
ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN:
The recommendation o
the delivery of core service.
1.ii - 2
FINANCIAL IMPLICATIONS:
In addition to the costs anticipated in this tender, the design and implementation of these types
of projects typically involves city staff and resources from across the corporation. These costs
are included in the line item "Projected Costs: Staff Time/Permitting/Material testing", and will be
itemized when they exceed $125,000. Included in this line item are staff time and expenses for
all city staff in support of the project such as Engineering, Kitchener Utilities, and Transportation
Planning. The line item also includes all regulatory permitting, geotechnical and material testing,
detouring and traffic control, alternate access and parking requirements and any other
miscellaneous costs. Projects utilizing in-house staff will include costs for inspection during
construction and contract administration.
The net cost for this tender (A), is fair and reasonable for a purchase of this scope and the upset
limit is within the budget allowance (B) provided within the budget. Funding for this purchase is
included within the approved capital budget. The estimated surplus (E) will remain within the
project to be used towards the 2020 road resurfacing program.
Tender T19-001
Road Improvement, Road Surface Construction, Misc. Asphalt and Concrete Work
The total budget for all phases of this project is 6,688,986.00
Estimated Cost for this Phase of Work
Tender T19-001 costs, including HST6,480,000.00
less: HST rebate on tender(644,559.01)
Net Cost Being Awarded5,835,440.99 A
Costs Incurred to Date -
Projected Costs: Staff Time253,033.00
Projected Costs: Geotechnical 90,000.00
Total Estimated Cost for this Phase of Work$6,178,473.99 C
Budget for this Phase of Work
WIP -Road Reconstruction -Sanitary Utility962,382.00
WIP -Road Reconstruction -Stormwater Utility481,191.00
WIP -Road Reconstruction -Water Utility648,562.00
WIP Road ReconstructionGeneral Account 1,485.00
Sanitary Utility 38,150.00
Storm Water Utility 48,444.00
Water Utility 94,467.00
Gas Utility 30,883.00
Federal Gas Tax3,601,727.00
Capital Out ofCurrent650,331.00
Development Charges131,364.00
Total Budget for this Phase of Work$6,688,986.00 B
Estimated Surplus/(Deficit) for this Phase of Work (B -C)510,512.01 D
Balance in account, net of encumbrances63,241.44
Total Estimated Surplus/(Deficit) $573,753.45 E
1.ii - 3
COMMUNITY ENGAGEMENT:
INFORM This report has been
council / committee meeting.
ACKNOWLEDGED BY: Jonathan Lautenbach, Chief Financial Officer, Financial Services
Department
1.ii - 4
The following is a tentative list of locations and construction timings that are to comprise the bulk of this Tender.
METHODS OF CONSTRUCTION, STREETS AND STREET LIMITS
A. Full Depth Milling + Binder Asphalt + Surface Asphalt
STREET FROM TO WARD TIMING
1) Appalachian Crescent Kingswwod Drive Kingswood Drive 6 April-June
2) Butler Lane Highland Road Hearth Crescent 8 April-June
3) Doon Village Road Bechtel Drive Pioneer Drive 4 July-September
4) Erinbrook Drive (Phase#1) Rittenhouse Road Hedgestone Crescent 6 April-June
5) Erinbrook Drive (Phase#2) Hedgestone Crescent Tillsley Drive 6 April-June
6) Geneva Crescent Selkirk Drive End 6 April-June
7) Gracefield Crescent Kingswood Drive Kingswood Drive 6 April-June
8) Jay Court Selkirk Drive End 6 April-June
9) Old Carriage Drive Pioneer Drive Old Carriage Court 4 July-September
10) Queenston Crescent Queenston Drive Queenston Drive 1 July-September
11) Raitar Avenue Weber Street West Ellis Avenue 10 July-September
12) Rittenhouse Road (Phase#1) Blockline Road #217 Rittenhouse Road 6 April-June
13) Rittenhouse Road (Phase#2) #217 Rittenhouse Road Erinbrook Drive 6 April-June
14) River Road (Phase#1) Manchester Road Krug Street 1, 2 July-September
15) River Road (Phase#2) Victoria Street North Frederick Street 1, 2 July-September
16) Selkirk Court Selkirk Drive End 6 April-June
B. Full Depth Pulverize + Surface Asphalt Overlay
STREET FROM TO WARD TIMING
1) Alpine Court Alpine Road End 6 June-August
2) Clover Place Fergus Avenue End 2 June-August
3) Grand Crest Place Wilson Avenue End 3 June-August
4) Kevco Place Wabanaki Drive End 3 June-August
5) Pleasant Avenue Stirling Avenue South Glen Road 9 June-August
6) Springdale Drive Lang Crescent End 1 June-August
7) Wilson Avenue Mill Park Drive End 3 June-August
C. Surface Asphalt
STREET FROM TO WARD TIMING
Union / Maple
1) Union Street Lancaster Street West Serada Road 10 April - July
2) Maple Avenue Union Street Arnold Street 10 April - July
1.ii - 5
C.Surface Asphalt - Continued
STREETFROMTO WARD TIMING
Duchess / Marina / Aberdeen
3)Duchess Avenue Dunbar Road Marina Road8 April - July
4)Marina Road Brandon Avenue South End 8 April - July
5)Aberdeen Road Claremont Avenue Glasgow Street 8 April - July
Breithaupt / Major
6)Breithaupt Street St. Leger Street Lancaster Street 10 April - July
7)Major Street Wellington Street Breithaupt Street 10 April- July
8)Dumfries Avenue Krug Street Stirling Avenue 10 April - July
9)Fairfield Avenue Ridgewood Drive Edwin Street 10 April - July
Woodland / Russel
10)Woodland Avenue Russel Street Mill Street 9 April - July
11)Russel Street Spadina Road East Stirling Avenue South 9 April - July
Binscarth / Brant / St. Claire / Pleasant / Glen
12)Brant Crescent Glen Road Glen Road 9 April - July
13)St. Claire Avenue Glen Road 60 meters 9 April - July
14)Glen Road Highland Road West Pleasant Avenue 9 April - July
15)Binscarth Road Pleasant Avenue Barclay Avenue 9
16)Pleasant Avenue Queens Boulevard Perth Road 9
17)Cherry Street West End Strange Street 9 April- July
18)Sheldon Avenue Weber Street East East End 10 July - September
19)Krug Street East Avenue Becker Street 1, 10 July - September
20)Fourth Avenue Kingsway Drive Connaught Street 3 July - September
Belmont Avenue / Edgewood Drive
21)Belmont Avenue Highland Road West Victoria Street South 8 July - September
23)Guelph Street Margaret Avenue St. Vincent Street 1, 10 July September
Alice Avenue / Karn Street
24)Alice Avenue Victoria Street South Karn Street 8 July - September
25)Karn Street Lawrence Avenue Westmount Road West 8 July - September
26)Kehl Street Heiman Street Ottawa Street South 9 July - September
27)Connaught Street Third Avenue Fourth Avenue 9 July - September
1.ii - 6
D.Miscellaneous Asphalt / Concrete work
STREET FROMTO WARD TIMING
1)Random Utility Cuts (TBD) TBDTBD TBDTBD
2)Drainage Improvements TBD TBD TBD TBD
3)Kiwanis Park Kiwanis Park Section #51559 1 May
4)Upper Canada Park Trail Entrance 4 April - May
5)Lions Arena Parking Lot Rittenhouse Rd Upper Parking Lot 6 May - June
6)Auditorium Parking Lot H East AvenueLeft Side Main Entrance 10 May- June
7)Auditorium Parking Lot A East AvenueRight Side Main Entrance 10 May- June
8)#8 Bridge St. E Parking Lot Lancaster StreetBridgeport Road 1 May- June
7)Butler Lane Multi-Use Trail Highland RdExisting Trail 8 April - May
8)Park Trail Williamsburg Rd Wilkins Dr 5 May - August
E.Provisional Streets (Not Included in the tendered Quantities)
STREET FROMTO WARD TIMING
1)Bonfield Place Chandler Drive End 6
2)Leacrest Court Chandler Drive End 6
3)Sunset Place Union Street End 10
4)Woodfern Court Chandler Drive End 6
5)Stirling Avenue South Mill Street Courtland Ave East 9
1.ii - 7