HomeMy WebLinkAboutINS-20-005 - City Hall Outdoor Spaces Rehabilitation Update REPORT TO: Special Council DATE OF MEETING: February 24, 2020 SUBMITTED BY: Asad Qureshi, Director Facilities Management 519-741-2600 X 4424 PREPARED BY: Lynda Stewart, Manager Projects & Energy Management 519-741-2600 X 4215 WARD (S) INVOLVED: All Ward(s) DATE OF REPORT: February 10, 2020 REPORT NO.: INS-20-005 SUBJECT: City Hall Outdoor Spaces Rehabilitation Update ___________________________________________________________________________ RECOMMENDATION: That the City Hall Outdoor Spaces Rehabilitation project scope/cost reductions identified in Infrastructure Services Department report INS-20-005 Table 1 be approved; and, That $2.8M be added to the City Hall Outdoor Spaces Rehabilitation Project for a total project budget of $11.8M; and further, That the funding sources for the additional budget be allocated as follows: Parking Capital Reserve - $450,000 Parking Structural Provision Account - $150,000 Tax Capital Reserve - $900,000 Gas Tax Reserve - $1,300,000 BACKGROUND: In September 2016, Council received the City Hall Outdoor Spaces Master Plan, which outlined the existing conditions and how the areas could potentially be redesigned to be more flexible for programming; provide better access to the spaces and replace necessary infrastructure for durability. The following issues related to infrastructure were identified in the master plan: An engineering report identified cracks and leaking of salt and water into the ceiling of the parking garage which increases the costs of garage repairs the longer rehabilitation work is deferred. The waterproofing membrane must be replaced to rectify this situation. Failure to address this issue could result in spalling concrete (concrete dislodged from the soffit) within 2-3 years. *** This information is available in accessible formats upon request. *** Please call 519-741-2345 or TTY 1-866-969-9994 for assistance. The physical design of site features, including the stage, fountain, stairs, ramps and damage to the paving surface present significant accessibility issues. The drainage infrastructure, particularly the trench drains, is in poor condition. Most of the drains through the garage roof slab are actively leaking and this has resulted in deterioration of the concrete directly around the drains. This is an indication that the membrane bond has failed near the drains and this condition will continue to expand each season during periods of freezing temperatures. For this reason, deferring the repairs will result in an escalation in leak locations and concrete deterioration. The design of the drainage should be improved to suit the environmental conditions as required by the Ontario Building Code. In the proposed design, the trench drain capacity will be increased and area drains will be bi-level drains to improve performance and reduce flooding risk. Below the entire concrete surface, a sub-surface drain board will be installed to help direct water towards the drains. Both the ice rink and fountain are original equipment and reaching the end of expected lifecycle. Replacement should be considered, as the fountain and ice rink were rated very favourably in feedback provided during public consultation for the master plan. From a programming perspective, the proposed design would address these concerns: Programming and events at City Hall have grown considerably and are expected to continue to expand in scale and variety of activities. The size and position of the stage and fountain impacts programming, limiting the usable area of the square for events. Draining the fountain for events is a labour and time intensive activity and necessitates blocking off part of the square to prevent trip and fall injuries due to the grade change. The resolution passed by Council recognized critical infrastructure (surface concrete, parking garage membrane and surface drainage) as the first priority; that the refurbishment or replacement of the ice rink, fountain and stage should be considered concurrently with critical infrastructure replacements; and, that other elements would be considered subject to funding availability. Subsequently, a Functional Plan to explore the feasibility of constructing the master plan design was completed in 2017 (INS 17-076 City Hall Outdoor Spaces Functional Design). During budget deliberations in 2019, a capital project was approved based on a 60% completed design submission. In 2019, further work to refine the design continued and a structural engineer specializing in restoration projects was added to the team. A 100% detailed design submission was tendered, closing on December 10, 2019 (T19-177). REPORT: Two tenders were received for the City Hall Outdoor Spaces Rehabilitation Project, both significantly exceeded the project budget, with the lowest being $2.8M over budget. Staff and the consulting team have analyzed the bids to understand the significant variance between the estimated costs used to set the budget and those included in the bids received. Cost Drivers Generally, market conditions have been exerting upward pressure on construction costs over the last several years. The City of Kitchener has seen high demand for construction trades and a number of large projects are underway in Waterloo Region. A pre-qualified bidder withdrew from this tender as the company was awarded another project and would not have the trade capacity to complete both projects. The site conditions for this project, such as limited staging areas; limited site access; the need for off-site storage; and work sequencing requirements are somewhat challenging. These conditions could result in a price premium, but it is difficult to quantify these potential factors. Labour and material costs have also increased significantly in a heated market. Concrete, petroleum-based products, and metal products are showing marked increases. All three materials are required in significant quantities for this reconstruction project. Statistics Canada Construction Price Index reports show a 9% annualized increase for metal products in the period May 2016 to January 2019; in a shorter period from early 2018 to January 2019, concrete products showed a 7.4% annualized increase. A bulletin issued by Statistics Canada in August 20Structural steel framing and concrete products were the main drivers of price The November 2019 bulletin noted a In addition to market and demand considerations, specific to this project there are two key items driving the cost difference between the project budget and the tender bid the waterproofing membrane and the electrical and mechanical components of the ice rink and water feature. Waterproofing Membrane The current waterproofing membrane on the podium deck is a hot rubberized asphalt product and is original to the construction of City Hall in 1993. Transportation Services staff undertake condition assessment surveys of the parking garage on a three year cycle. Recent surveys have noted accelerated deterioration of leaking cracks through the slab which indicates the podium deck waterproofing system is at the end of its effective life. Between 2016 and 2019, the condition assessment noted a 576% increase in the length of leaking soffit cracks in the podium deck. The most recent condition assessment report recommended trench drains and concrete work be undertaken in 2020. Project budget estimates for the podium deck waterproofing system were based on the 2016 condition assessment report which considered a like for like replacement hot rubberized asphalt membrane and pavers as the hardscape. With the expertise of a structural restoration engineer on the team, the design evolved in 2019. Given the maintenance challenges and deterioration of the existing granite and concrete pavers, the hardscape was changed to concrete for more durability. The waterproofing membrane was changed to a cold-applied dual membrane system to align the service life of the waterproofing with the surface concrete and achieve better overall results. The project team investigated alternative products, particularly for the waterproofing membrane application. The structural restoration engineer strongly recommends that a cold-applied dual membrane waterproofing system be used for the following reasons: While a higher capital cost, it has the lowest lifecycle cost providing nearly double the service life as hot rubberized asphalt systems. Repairs could be expected within 20 years and a full replacement of hot asphalt systems within 30 years. The service life of the cold- applied membrane is expected to be 50 years. Poured in place concrete paving will mitigate the damage from salt erosion and snow removal equipment, but it is more difficult to access the waterproofing should repairs be necessary, which is more likely with the hot asphalt system. It is a low odour product with fewer risks. Hot applied systems create noticeable odours and inherently have greater health and safety risks for workers. Redundancy in the membrane and reinforcing components gives added protection and flexibility to accommodate movement and grade changes. Cold-applied membranes can be used in a wider range of environmental and site Cold applied membranes are suitable for all site components, including planters and submerged conditions. Hot asphalt systems would require additional work in these areas. The waterproofing membrane related to the parking garage accounts for 52% of the variance between the project budget and the submitted bid ($1,450,250 of a $2,803,876 variance). Mechanical and Electrical Components The majority of mechanical and electrical components of the project are related to the rink and fountain restoration which are nearing end of life. Piping and electrical work for this project is extensive and restoration work compared to new construction is generally more complex and time-consuming. Specialist contractors are engaged to complete rink and water feature construction and market demands on these trades are high. These factors contribute to a cost premium for this project. As part of the post-tender bid analysis, recent comparable projects were reviewed and found the submitted bid price is similar and reasonable. In evaluating the key drivers of costs specific to the project, it was identified that the project team assumed the reuse of existing penetrations through the slab, where possible, for mechanical and electrical components. However, significant work is required to make either new or existing penetrations waterproof which was not accounted for on the project budget. In addition, stainless steel grating for the water feature drains is necessary in two locations across the square. As noted previously, metal products have seen sharp price increases and is a significant factor here. Electrical and mechanical components related to the ice rink and water feature account for 38% of the variance between the project budget and the submitted bid ($1,070,100 of $2,803,876). Other Items The final design exercise in 2019 identified additional scope items related to accessibility and repairs to the City Hall stone façade. To achieve Accessibility for Ontarians with Disabilities Act (AODA) compliance, several features will need to be upgraded from the original design: Additional railings on stairways and ramps that are currently too wide Realign the ramp on Duke St. to maintain a consistent width along the length Current handrails need to be replaced with rounded handrails placed at correct height GRAAC members requested Tactile Walking Surface Indicators (TWSI) for safe wayfinding on Carl Zehr Square and the Duke Street entrance. Accessibility upgrades and stone façade repairs account for 10% of the variance between the project budget and the submitted bid ($282,526 of $2,803,876). Project Scope/Cost Reductions Staff evaluated potential reductions in scope for the overall project to reduce the cost of the construction works. It is difficult to achieve large-scale scope reductions since the majority of the work is critical infrastructure repair or replacement of the surface paving and drainage and the waterproofing membrane. The extent of the parking garage dictates that work must be performed on all four elevations at city hall. Similarly, the water feature and ice rink infrastructure are nearing the end of lifecycle and this is an opportunity to replace that equipment before concrete is re-poured. Provisional items and alternate pricing for some project elements were identified in the tender bid. Staff are recommending that the items identified in table 1 be removed from the project scope, representing approximately $1.7M reduction in project costs. Table 1 Staff Recommended Project Scope & Cost Reductions Item Description $ Savings Renewal of Upper Terrace Area outside exit doors to King St. & $392,175 Carl Zehr Square terrace across the front nd Renewal of Ramp and Stairs leading to 2 floor from CZS & $458,000 nd Stairs Carl Zehr Square Ramp to 2 floor from area near College St. underpass Site Furnishings Carl Surface mounted furnishings, including $154,460 Zehr Square bike racks, bike repair station, shade canopies, cantilevered benches and waste / recycle stations Site Furnishings - Duke St Surface mounted furnishings, including $37,450 bike racks, benches and waste / recycle stations Alternate item Kitchener Alternate price to provide KITCHENER $161,000 sign lettering sign on southeast corner (Gaukel St.) Base price includes poured in place sign wall Contingency reduction $505,403 from 10% to 5% Total $ 1,708,488 The consequence of removing these items is that the upper terrace, ramp and stairs will need to be waterproofed at a future time. Ideally, this would be done when building envelope replacements are completed to tie that waterproofing into the building to ensure integrity. The site amenities such as benches, shade structures, waste / recycling receptacles and cycling infrastructure are integral to the functionality of the square for events. These items will need to be funded out of other capital accounts however it is anticipated that more competitive pricing would be possible by purchasing these items directly outside of the project scope. FINANCIAL IMPLICATIONS: As noted earlier in the report, the project is overbudget by approximately $2.8M. The proposed funding solution apportions the extra costs between Parking and Tax, which are the original funding sources for the components and are subject to price escalation. The funding split is based on the original proportions used to fund the project. The specific funding sources and amounts are noted in Table 2, and will draw down the unallocated balances in these accounts. Table 2 - Proposed Funding Sources Funding Source $ Amount Parking Capital Reserve $450,000 Parking Structural Provision Capital Account $150,000 Total Parking Contribution $600,000 Tax Capital Reserve $900,000 Federal Gas Tax Reserve $1,300,000 Total Tax Contribution $2,200,000 Total Funding Contribution $2,800,000 Table 3 shows the projected ending balances for each of the reserves over the next five years after making the proposed transfers. It should be noted that the proposed funding transfer from Federal Gas Tax does not utilize the $900,000 closeout made late in 2019 related to Woodside Park. Table 3 - Ending Reserve Balances Reserve 2020 2021 2022 2023 2024 Parking Capital $757,000 $61,000 $16,000 $226,000 $444,000 Tax Capital $1,100,000 $531,000 $139,000 $0 $0 Federal Gas Tax $927,000 $1,013,000 $1,171,000 $2,533,000 $1,189,000 ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN: the delivery of core service. COMMUNITY ENGAGEMENT: INFORM council / committee meeting. PREVIOUS CONSIDERATION OF THIS MATTER: INS 16-066 City Hall Outdoor Spaces Master Plan INS 17-076 City Hall Outdoor Spaces Functional Design 2019 Budget Issue Paper Cap04- Rehabilitating City Hall Outdoor Spaces CONCLUSION: The condition of City Hall outdoor spaces has continued to deteriorate over the past few years and the need to address critical infrastructure, accessibility, flexibility and durability concerns remain. Staff recommend increasing the project budget by $2.8M to complete the required rehabilitation of the City Hall Outdoor Spaces. Delaying this project would result in the loss of the 2020 construction season and increase inflationary costs in future years. Retendering the project provides no guarantee of more competitive bids and is likely to result in higher bids overall. This project addresses several needs: rehabilitating critical infrastructure; making the areas more accessible for patrons; and increasing the flexibility for events and festivals. This is consistent with the strategic objectives to manage assets to be sustainable and dependable; managing storm water; creating vibrant and active public spaces and developing downtown Kitchener and City Hall as the heart of the city. The importance of this project suggests it should not be delayed until future budget years. ACKNOWLEDGED BY: Denise McGoldrick, General Manager, Infrastructure Services