HomeMy WebLinkAboutDSD-20-060 - 2021 Sidewalk Infill Through Roadway ReconstructionREPORT TO:Community and Infrastructure Services Committee DATE OF MEETING:September 28, 2020 SUBMITTED BY:Barry Cronkite,Director, Transportation Services 519-741-2200 x7738 PREPARED BY:Lou Slijepcevic, Traffic Project Coordinator, 519-741-2200 x7153 WARD(S) INVOLVED:Wards 2, 8, and 10 DATE OF REPORT:September 4, 2020 REPORT NO.:DSD-20-060 SUBJECT:2021Sidewalk Infill through Roadway Reconstruction ___________________________________________________________________________ RECOMMENDATION: That the following streets be approved for sidewalk infillin 2021/2022as per the Sidewalk Infill Policy MUN-STR-2004, approved by Council June 1, 2015: Rossford Crescent, Boehmer Street, Thaler Avenue/Windom Road; BACKGROUND: On June 1, 2015 Council approved MUN-STR-2004Sidewalk Infill Policy.TheInfillPolicy defines the framework around the installation of new sidewalk locations where sidewalk currently does not exist.Generally speaking, the policy confirms the City’s commitment to an improved sidewalk network on existing roadways to support a more pedestrian friendly environment.It also defines priority levels for sidewalk infill locations and provides a framework for community and Council input onproposed installations when sidewalk infill is not pre-approved through the policy. The policy requires Council approval for somesidewalk infill locations. This report outlines locations of sidewalk that are recommended to be built in conjunction with upcoming road reconstruction projectsin 2021/2022andprovides recommendations for the application of the policy in these areas. REPORT: The Sidewalk Infill Policy stipulates that planned sidewalk infill locations must be presented to Council for approval at least one year in advance of implementation. Accordingly, staff has reviewed locations for sidewalk infill through 2021/2022 reconstructionprojects, as follows; *** This information is available in accessible formats upon request. *** Please call 519-741-2345 or TTY 1-866-969-9994 for assistance. 3 - 1 Rossford Crescent Location: Rossford Crescent: On the even numberside of Rossford Crescentfrom Markwood Driveto Markwood Drive; Priority: Priority 2 (36 to62points) S core: 60pts Rossford CrescentPoint Summary Within 200m of a bus stop(Hazelglen Drive @ Chopin Drive)10 Within 800m of an elementary school(AR Kaufman Public School)25 Within 400m of a commercial zone(Hazelglen Drive @ Chopin Drive)5 Within 400m of community programs facility or park(Gzowski Park)10 Within 400m of a type 1 or 2 trail(Gzowski Parktail network)10 Total Points60 Implementation Year: 2021 Length of Sidewalk Infill: 1100m Priority 2is defined as: Sidewalks shall be required on both sides of the roadway; however, an exemption may only be authorized by Council should staff not be able to reasonably mitigate constraints such as, but not limited to; cultural heritage impacts, site specific impacts, environmentally sensitive impacts and maintenance impacts. Locations thatscore less than 62 points are considered priority 2. Transportation Services surveyed area residents within the identified study area regarding sidewalk infill along the identified sections of roadway. The results of the survey are as follows: Directly AffectedRossford CrescentResidents: In Favour2of 24 (8%) Opposed21of 24 (88%) Indifferent1 of 24(4%) Total responses of Directly AffectedResidents 24out of 66 surveyed (36%) Area Residents: In Favour22of 35(63%) Opposed8 of 35 (23%) Indifferent5 of 35 (14%) Total responses of Area Residents 35out of 344surveyed (10%) *** This information is available in accessible formats upon request. *** Please call 519-741-2345 or TTY 1-866-969-9994 for assistance. 3 - 2 Total Residents(directly affected + area residents): In Favour24 of 59 (41%) Indifferent29of59 (49%) Opposed6 of 59(10%) Total responses 59out of 400surveyed (15%) The installation of the sidewalkon the evennumber side (along the outsideof the crescent) will require the removal of some private landscapingthat has been installed on public property, and the removal of two mature trees.The proposed sidewalk provides access to an existing trail connection,Gzowski Parkand the Victoria Hills Community Centre. Rossford Crescent:Proposed sidewalk infill location Legend: Study Area Proposed Sidewalk Infill Existing Sidewalk *** This information is available in accessible formats upon request. *** Please call 519-741-2345 or TTY 1-866-969-9994 for assistance. 3 - 3 BoehmerStreet LocationBoehmerStreet: On the west side of BoehmerStreet between Elmwood Avenueand Fairfield Avenue. Priority Priority 2 (36 to62points) Score 50pts BoehmerStreetPoint Summary Within 800m of an elementary school (Prueter Public School)25 Within 400m of a commercial zone (Margaret Ave @ Fairfield Ave)5 Within 400m of community program facility of park (Breithaupt Centre)10 Within 400m from a place of worship(St Teresa’s Catholic Church)5 Completion of Link5 Total Points50 Implementation Year2021 Length of Sidewalk Infill75m Directly Affected BoehmerStreet Residents: In Favour10of 13 (77%) Indifferent1of 13 (15%) Opposed2of 13 (8%) Total responses of Directly Affected Residents 13out of 51surveyed (25%) Area Residents: In Favour34 of 48(71%) Indifferent9of 48(17%) Opposed5of 48(13%) Total responses of Area Residents 48out of 260surveyed (18%) Total Residents(directly affected + area residents): In Favour44of 61(72%) Indifferent10of 61(11%) Opposed 7of 61(16%) Total responses 61out of 311surveyed (20%) The installation of the sidewalkis not anticipated to have any impact to private landscaping, or require mature tree removal.The proposed sidewalk will fill in the last link in the existing sidewalk network and provide a safe pedestrian path to Prueter Public School. *** This information is available in accessible formats upon request. *** Please call 519-741-2345 or TTY 1-866-969-9994 for assistance. 3 - 4 BoehmerStreet:Proposed sidewalk infill location Legend: Study Area Proposed Sidewalk Infill Existing Sidewalk *** This information is available in accessible formats upon request. *** Please call 519-741-2345 or TTY 1-866-969-9994 for assistance. 3 - 5 Thaler Avenue LocationThaler Avenue On the southside of Thaler Avenuebetween Fairway Road Northand Windom Road. Priority Priority 1 (greater than 62 points) Score 85 points Thaler AvenuePoint Summary Within 200m of a Bus Stop (Fairway Rd N @ Thaler Ave)10 Within 450m of a Bus Stop (Fairway Rd N @ Thaler Ave)5 Within 800m of an Elementary School (Howard Robertson Public School)25 Within 400m of a Place of Worship (Christ the King United Church)5 Within 400m of Type 1 or 2 trail(Dom Cardillo Trail)10 Within 400m of a commercial zone (Fairway Rd N @ River Rd E)5 Within 400m of a mixed usecorridor (Fairway between King Street & Morgan Ave)20 Completion of a link5 Total Points85 Implementation Year2021 Length of Sidewalk Infill175m Priority 1 is defined as: Sidewalks shall be required on both sides of the roadway as they connect to a significant number of pedestrian origins and destinations. Windom Road LocationWindom Road On the westside of Windom Roadbetween Thaler Avenue and the end of the roadway; On the east side of Windom Road between Southill Drive and the end of the roadway. Priority Priority 1 (greaterthan 62 points) Score 80pts WindomRoadPoint Summary Within 450m of a Bus Stop (Fairway Rd N @ Thaler Ave)5 Within 800m of an Elementary School (Howard Robertson Public School)25 Within 400m of a Place of Worship (Christ the King United Church)5 Within 400m of Type 1 or 2 trail(Dom Cardillo Trail)10 Within 400m of a community program facility or park (Centreville Chicopee 10 Community Centre) *** This information is available in accessible formats upon request. *** Please call 519-741-2345 or TTY 1-866-969-9994 for assistance. 3 - 6 Within 400m of a mixed use corridor (Fairway between KingStreet& Morgan Ave)20 Within 400m of a commercial zone (Fairway Rd N @ River Rd E)5 Total Points80 Implementation Year2021 Length of Sidewalk Infill265m Directly Affected Thaler Avenue and Windom RoadResidents: In Favour8 of 15 (53%) Opposed7 of 15 (47%) Total responses of Directly Affected Residents 15 out of 146 surveyed (10%) Area Residents: In Favour20of 27(74%) Indifferent1 of 27(4%) Opposed6 of 27(22%) Total responsesof Area Residents 27out of 327surveyed (8%) Total Residents(directly affected + area residents): In Favour28of 42(67%) Indifferent6of 42(14%) Opposed 8of 42(19%) Total responses 42out of 473surveyed (9%) The installation of the sidewalkis not anticipated to have any impact to residential landscaping, or require mature tree removal.The proposed sidewalk will provide direct access to Howard Robertson Public School. *** This information is available in accessible formats upon request. *** Please call 519-741-2345 or TTY 1-866-969-9994 for assistance. 3 - 7 Thaler Avenue & Windom Road:Proposed sidewalk infill location Legend: Study Area Proposed Sidewalk Infill Existing Sidewalk *** This information is available in accessible formats upon request. *** Please call 519-741-2345 or TTY 1-866-969-9994 for assistance. 3 - 8 ALIGNMENT WITH CITY OF KITCHENER STRATEGIC PLAN: The recommendation of this report supports the achievement of the city’s strategic vision through the delivery of core service. FINANCIAL IMPLICATIONS: The cost of sidewalk installation is funded through the Water Infrastructure Program (WIP) in the 2020capital budget for these projects. COMMUNITY ENGAGEMENT: INFORM – This report has been posted to the City’s website with the agenda in advance of the council / committee meeting.Residents were notified regarding this report to recommend the implementation of sidewalk through upcoming reconstruction projects. CONSULT – Transportation Services initiated public consultation through a survey/questionnaire for: Boehmer Street – January 10, 2020 Thaler Avenue/Windom road – January 10, 2020 Rossford Crescent – January 10, 2020 The Engineering Division leadspublic engagement for roadway reconstruction projects. Transportation Planning staff support these engagement efforts todiscuss and answer questions regarding sidewalk infill, and other transportation impacts. ACKNOWLEDGED BY: Justin Readman, General Manager, Development Services Department *** This information is available in accessible formats upon request. *** Please call 519-741-2345 or TTY 1-866-969-9994 for assistance. 3 - 9