HomeMy WebLinkAboutCAO-20-008 - 2020 Business Plan Year-End Progress Report and 2021 Business Plan Recommended Project ListREPORT TO:Council
DATE OF MEETING:December 14, 2020
SUBMITTED BY:KarenCooper, Manager, Strategic and Business Planning,
519-741-2200ext. 7817
PREPARED BY:LaurenBurr, Corporate Planning Analyst,519-741-2200ext. 7059
WARD(S) INVOLVED:All Ward(s)
DATE OF REPORT:December 9, 2020
REPORT NO.:CAO-20-008
SUBJECT:2020 Business Plan Year-End Progress Report and
Recommended 2021 Business Plan Project List
RECOMMENDATION:
That the City of Kitchener 2021 Business Plan Project List outlined in Appendix B to
report CAO-20-008 be approved, subject to budget deliberations.
REPORT HIGHLIGHTS:
This report presents the 2020 Business Plan Year-End Progress Report (Appendix A)
and the Recommended 2021 Business Plan Project List(Appendix B)
Progresswas made on 38 strategic and business plan projectsin 2020, with 10projects
completed overall.
The Recommended 2021 Business Plan Project List includes all 25 Strategic Plan
actions and15business plan projects continuing from 2020.
REPORT:
2020 Business Plan Year-End Progress Report
2020 was an unprecedented year as Kitchener responded to the COVID-19 pandemic. The
City placed the safety of citizens and staff as a top priority through its pandemic response
and recovery efforts, while also supporting the economic sustainability of businesses and
employers. To achieve these priorities, staff took complementary and innovative approaches
to modernize service delivery and improve efficiencies. This included enabling staff to work
from home, providing more services online, offering existing programs in new virtual formats,
providing training and supports to local businesses and establishing centralized service
counters at city hall. While some of the service delivery changes are only temporary to
address the pandemic restrictions, many will remain post-pandemic and provide long-term
benefits.
*** This information is available in accessible formats upon request. ***
Please call 519-741-2345 or TTY 1-866-969-9994 for assistance.
2 - 1
redeployed to emergency operations and other functions. Up to 945 staff (42%) were on
declared emergency leave during
staffing impacts, as well as a pause on non-critical hiring from March to August, affected the
dates for 24 projects are included in this report. Through this challenging time, staff
demonstrated resiliency and made progress on 2020 Business Plan projects, with 10
projects completed. Council can beproud of how staff adapted to the challenges of the
pandemic andcontinued to deliver on the community priorities outlined in the Strategic Plan.
Of the 47 projects includedin the 2020 Business Plan, 29 werescheduled to be completed
in 2020. As of December 31,10projects have been completed, including 4strategic plan
projects.
Figure1:Year-EndStatusof the 2020 Business Plan
CompletedOn TrackDelayed or Not Started
ЊЉ ƦƩƚƆĻĭƷƭ
Б ƦƩƚƆĻĭƷƭЋВ ƦƩƚƆĻĭƷƭ
ΛЋЊіΜ
ΛЊАіΜ ΛЏЊіΜ
Strategic Projects
The City made considerableprogress in the projects committed to under the five goals of
the Strategic Plan. The following fourstrategic plan projects were completedin 2020:
Cycling and Trails Master Plan Update-In October, Council approved the updated
Cycling and Trails Master Plan, a long-
cycling facilities into a city-wide network. More than 3,000 residents provided feedback
during the development of the plan. Recommendations for the next 10 years include the
development of 43 km of on-street active transportation facilities, 13 km of off-street multi-
use trails, and improvements to walkways and trails that connect neighbourhoods.
2 - 2
Make It Kitchener 2.0 Strategy -In October, Council approved this bold, ambitious plan
to support business recovery, to create a future where everyone can make a difference,
and to propel our community forward.This 10-year plan will guide economic development
and community initiatives in the city and allow Council to invest up to an additional $110
million, without relying on a tax rate increase. The plan will puta spotlight on pandemic
recovery in our community and address affordable housing and new issues that have
emerged throughout the pandemic.
Housing Strategy As a key action from the 2019-2022 Strategic Plan, Housing for All,
gy has been recommended to Council. With a human rights-
based approach and a commitment to lived experience collaboration, the strategy
outlines city actions to help end homelessnessandhelp secure community, affordable
rental and affordable ownership housing, through advocacy, aligning policies, processes
and use of city land to facilitate more affordable housing, filling data gaps and effective
monitoring and accountability. Working collaboratively with our Advisory Committee, the
Region of Waterloo, members of the public, community partners and the development
industry, Housing for All is a made-for-Kitchener blueprint for an even more equitable and
caring community.
Reduce Social Stigma through Staff Training -An anti-stigma learning program for
City staff was launched in the fall 2020 learning catalogue, with greater focus given to
addressing both the topics of mental health and addiction. Anti-stigma training will now
become a core learning program with ongoing evaluation and customization as required
to meet the diversity of staff needs throughout the organization and to ensure the
content is relevant to evolving community needs.
Additional strategic plan progress includes:
Conversion ofGaukel Street into a community space with patio tables, lighting and
Indigenous art.
Approximately 7 kilometres of new multi-use trails.
Lighting at the Civic District Garage converted to LEDs.
648new trees planted.
2 - 3
Business Plan Projects
The City also made considerable progress on business plan projectswhich are additional
Council priorities.Thefollowing sixbusinessplan projects were completedin 2020:
Close the Loop with Citizens successfully
introduced close the loop emails for 15 parking case types and 15 property standard case
types, providing automated updates to customers when cases are created and when
assigned or closed.The project was further expanded in the fall to include 15 property
standard case types.
Indigenous Competency Training for Staff -Kitchener launched a four-part learning
program for staff in partnership with the Region of Waterloo, City of Waterloo and City of
Cambridge in the fall of 2020, with a Phase Two planned for 2021.The sessions covered
original cultures, history of settlement and allyship with Indigenous Peoples and targeted
priority staff in areas relating to senior leadership roles andthose responsible for land-
based work and community development. The course will be adopted as a core learning
program and will be evaluated and enriched as needed to ensure that it fulfills the intent
of the Truth and Reconciliation Commission and effectively supportsemployees in
delivering service to Indigenous communities. This sought-after learning opportunity was
delivered to 80 participants over a four-weekperiod. The course was highly rated by
participants for both the acquisition of new knowledge and delivery of difficult content.
Civic Innovation Lab at Communitech Guided by the award-winning Digital Kitchener
strategy, the achievements of the Lab led the City of Kitchener to be recognized
internationally as a leading smart city and further solidified partnerships with local tech and
academic communities. Over the last three years, the Lab has successfully explored
emerging technologies such as Internet of Things (IoT), artificial intelligence, machine
learning, and augmented reality to support City service delivery transformation. The final
year of the Civic Innovation Lab pilot was a busy one with significant advancements in the
development and use of design sprints and rapid prototyping of ideas and technologies.
Staff developed a plan to integrate continuing the Digital Kitchener Innovation Lab
activities leveraging existing staff resources within the division. An update on the activities
of the Lab and our go-forward approach was presented to Council in December.
E-Tendering Vendors can now self-identify for interested commodities, access bid
documents and submit submissions electronically for solicitation opportunities at the City.
2 - 4
Development Services Review -Two Lean process reviews were completed, resulting in 18
distinct improvement projects that led to implementation of 34 improvements to the site plan
review and approval process and 9 improvements to public engagement processes. Highlights
include:an intuitivemap-based tool for finding information on development applications across
the City;aworkshop that attracted over 30 community members duringits first
offering;procurement of a video series to help explaincomplex planning concepts and
processes;reimaginedhighly visual and more accessible public notices;and establishing a
representativevolunteer group of citizens toassist staff by providing insight and feedback on
a variety of development services processes, improvements,projects,and policies.The
improvements will result in enhanced collaboration, better communication,streamlined and
more inclusive processes, increased accountability, and a continuous improvement culture.
Electronic Reimbursement Implementation A successful implementation to automate
employees expense reimbursements, the SAP Concur implementation is a Win/Win/Win for
our organization. It provides a simplified and automated system for staff to submit expenses
of SAPapplications. This project was a great example of collaboration between Accounting,
SAP Business Systems and our TIS teams and will serve the corporation for years to come.
Recommended 2021 Business Plan Project List
Given the significant financial and operational impactsof the COVID-19 pandemic, the
proposed 2021 Business Plan project list contains only projects continuing from 2020.
The 15continuing business plan projects are:
Budd Park Strategy
Cameron Heights Pool Feasibility Study
Southwest District Pool Business Case
Ice Demand Study
Transformation and Relaunch of Kitchener.ca
Indigenous Competency Training for Staff Phase 2
Electronic Agenda Management
Mobile Time Entry
Development Charge (DC) and Community Benefits Charge (CBC) Studies
Long Term Financial Plan Implementation
Point of Sale and Expansion of Payment Options
Implementation of the Federal Disaster Mitigation and Adaptation Fund (DMAF)
Facilities Infrastructure Program
Implementation of Significant Parks Projects
Rehabilitation of City Hall Outdoor Spaces Construction Phase 1
2 - 5
The Recommended 2021 Business Plan Project List is presented in AppendixB. Subject to
Council approval, including any adjustments that may result from budget decisions, the list
will be incorporated into the City of Kitchener 2021 Business Plan document, along with
updated core service and departmental profiles. The final 2021 Business Plan will be
STRATEGIC PLAN ALIGNMENT:
build an innovative, caring and vibrant Kitchener.
FINANCIAL IMPLICATIONS:
The business plan and the budget are developed in parallel through an iterative process of
review and revision that keeps the allocation of resources in sync with the planned work of
the organization as outlined in the strategic plan. Resources to completethe work identified
in Appendix B, Recommended 2021 Business Plan Project List, are currently provided in
the proposed 2021 budget as outlined in reports FIN-20-066 and FIN-20-068.
COMMUNITY ENGAGEMENT:
INFORM This report has been posted to the City
the council / committee meeting.
CONSULTIn 2018, Compass Kitchener consulted the public on developing community
priorities for the 2019-2022 Strategic Plan, which informed preparation of the 2021 Business
Plan project list.
PREVIOUS REPORTS/AUTHORITIES:
CAO-19-0132020 Business Plan Project List
CAO-20-0042020 Business Plan Progress Report and Compass Kitchener Strategic
Plan Evaluation Guide
APPROVEDBY:Dan Chapman, Chief Administrative Officer
ATTACHMENTS:
AppendixA2020 Business Plan Year-End Progress Report -December 31, 2020
AppendixBRecommended 2021 Business Plan Project List
2 - 6
1
2 - 7
334782
131315182125272728313233
......
...............
..............
................
.........................................................
..................
........................................
........................
.........................
....................................................
............................
.............................
................................
................................
................................
................................
................................
................................................................................................
................................
................................................................
................................
................................
................................................................
................................
................................
................................
................................
................................
................................
................................
................................................................................................
................................
................................................................
................................
................................
................................................................
................................
................................
................................
................................
................................
................................
................................
................................................................................................
................................
................................................................
................................
................................
................................................................
................................
................................
................................
................................
................................
................................
................................
................................................................................................
................................
................................................................
................................
................................
................................................................
................................
................................
................................
................................
................................
................................
................................................................................................
................................
................................................................
................................
................................
................................................................
................................
19 On the 2020 Business Plan
................................
-
rvices
Friendly Transportation
-
................................
ess Plan Projects
Impact of COVIDPeopleEnvironmental LeadershipVibrant EconomyCaring CommunityGreat Customer ServiceCommunity ServicesCorporate ServicesDevelopment ServicesFinancial SeInfrastructure Services
2022 Strategic Plan Evaluation Criteria2022 Strategic Plan Actions
--
Contents IntroductionStatus of the 2020 Business Plan20192020 Business Plan Completions20192020 Busin
2 - 8
3
p
the
. U
delivery
as a top
improve
is described
t the year.
and staff
project
other functions
the service
This report contains
Each
term benefits.
nesses and employers in the
-
modernize service delivery and
to
lan and other key priorities. These projects form
p
ogress on strategic and business plan projects. Revised
pandemic and provide long
-
trategic
s
the economic sustainability of busi
staff adapted to the challenges of the pandemic and continued to
ing
how
19 pandemic. The City placed the safety of citizens
-
2022 Strategic Plan, as well as 22 business plan projects.
mentary and innovative approaches
-
le
. Through this challenging time, staff demonstrated resiliency and made progress on
We are proud of
leave
recovery efforts, while also support
are included in this report
enabling staff to work from home, providing more services online, offering existing programs in new virtual formats,
d
lan, which is developed alongside the budget to ensure resources are aligned to complete the work.
including anticipated timing for completion. Regular progress is reported to Council and the public throughou
p
19 On the 2020 Business Plan
-
for 24 projects
include
and
its pandemic response and
-
This
usiness
dates
b
March
business plan,
end update on progress made in 2020.
-
Introduction Each year, Kitchener City Council approves a list of projects that implement the current the annualin the The 2020 Business Plan includes all 25 actions from the 2019year
Impact of COVID 2020 was an unprecedented year as Kitchener responded to the COVIDpriority throughmunicipality. To achieve these priorities, staff took compefficiencies. providing
training and supports to local businesses and establishing centralized service counters at city hall. While some ofchanges are only temporary to address the pandemic restrictions, many
will remain postBetweento 945 staff (42%) were on declared emergency pause on noncompletion 2020 Business Plan projects, with 10 projects completed.deliver on the community priorities
outlined in the Strategic Plan.
2 - 9
4
.
, including 4
of projects and their
chart
full
are expected to complete in the
The
, the City will have achieved an overall
%) are delayed, on hold, or not started
(62%)
62
29 projects
As of December 31
Delayed or Not Started
projects (
9
(66%)
2
.
19 projects
Of the 19 delayed 2020 projects, 5
.
Delayed
and one is expected to complete in 2022.
(17%)
2020. As of December 31, 10 projects (21%) have been completed
8 projects
completed
end
-
On Track
projects
(34%)
10 projects
were scheduled to be completed in 2020.
usiness Plan
.
Completed
34
-
0 out of the 29
13
ness Plan
(21%)
i
47 projects to be undertaken in
10 projects
with 1
%) are on track to meet their scheduled end dates
of the 2020 Bof the 29 Projects Scheduled for Completion in 2020
17
Completed
are expected to complete by 2021 year
for 2020,
comprises
3
StatusStatus
%
1
4
projects (,
8
in the 2020 Business Plan, 29
.
EndEnd
--
YearYear
:
statuses is included on pages
1:2
d
en
-
Status of the 2020 Bus The 2020 Business Plan strategic projects Figure Of the 47 projects completion rate of 3first quarter of 2021year Figure
2 - 10
5
Adaptation Fund
&
Construction Phase 1
Implementation
Review
Significant Parks Projects
Financial Plan
Tendering
-
Budd Park StrategyCameron Heights Pool Feasibility StudyIce Demand StudyTransformation and Relaunch of Kitchener.caElectronic Agenda ManagementCommunity Benefit Charge StudyLong Term
Point of Sale and Expansion of Payment OptionsMobile Time Entry
Southwest District Pool Business CaseImplementation of Federal Disaster Mitigation Implementation of Rehabilitation of City Hall Outdoor Spaces
Close the Loop with CitizensIndigenous Competency Training for StaffCivic Innovation Lab at CommunitechDevelopment Services Electronic Reimbursement ImplementationE
business plan projects
9 business plan projects
4 business plan projects
6
:
including
1
Use Trails and
:
-
, including
delayed into 202
are
eserve Fund
Working Space Network
-
:
Round Maintenance of Multi
-
include
er Service Portal Development
projects
First Street Plan for Gaukel Street
-
Kitchener 2.0 Strategy
Language Interpretation Support
-
scheduled for completion in 2020
Owned Property Review
-
completed
Cycling and Trails Master Plan UpdateMake It Affordable Housing StrategyReduce Social Stigma through Staff Training
Connectivity and YearPathwaysLeverage the Energy Efficiency RTree Planting Elimination BacklogIncubator, Accelerator and CoPedestrianCommunity Climate Action Plan Tree Canopy TargetCityEquity,
Diversity and Inclusion StrategyMill Courtland Community Centre Expansion Business CaseMultiCustomer Satisfaction ProgramOnline Custom
10
projects
strategic plan projects
projects are on track for their scheduled end date
8
49 strategic plan projects
4 strategic plan projects
The 81
2 - 11
6
.
issues. Going
.
3
as planned
is delayed until 2023.
. Online Business Licensing
begin in 2021
delayed into 202
is
will
Market
Facilities Infrastructure Program
and not included in future business plans
:
1 business plan project
Owned Property Brought to including
-
CityProtected Cycling Network Connected to the Downtown
delayed into 2022
did not start as planned as government relations focused on responding to pandemic
will be considered core service
are
Set and Communicate Service Levels and Customer Experience Program
scheduled for completion in 2022
Strategy
scheduled for completion in 2021
Government Relations and Advocacy
Bikeshare ProgramWaste Diversion StrategyHuron Brigadoon Area School/ Community Centre ConstructionOpen Space Arts and Culture Plan
strategic plan projects
projects
6
One strategic plan project scheduled for completion in 2020 7One strategic plan project Two strategic plan projects Work on forward Government Relations and Advocacyis on hold, as software
upgrades are needed in order to proceed.
2 - 12
7
At the
inning in 2021.
004.
-
20
-
oward achieving the community vision and in
Strategic Plan
Appendix B of report CAO
p
through the
2022 Strategic Plan:
-
(24%).
for the 2019
tion Criteria
2022 Strategic Plan can be found in
provides advice to Council on
/measures
-
have been completed
inable Development Goals (SDGs)
the Susta
identifies community priorities for action, and monitors progress t
Advisory Committee
n criteria for the 2019
Citizen
Compass Kitchener
2022 Strategic Plan Evalua
-
Overall Implementation of the Strategic PlanOverall Implementation of Implementation of Strategic Plan GoalsImplementation of Strategic Plan Actions
Compass Kitchener
2019 The participation. implementing the Strategic Plan. Compass Kitchener has 4 levels of evaluation criteriaOne evaluation metric has been proposed for each of the 25 Strategic Plan
actions. These metrics will be tracked by staff begend of 2020, 6 out of the 25 strategic plan actions
2 - 13
---
8
new issues
strategic
the next 10 years include the
affordable housing and
Cycling and Trails Master Plan, a long
updated
year plan will guide economic development and
the pandemic.
-
street active transportation facilities, 13 km of off
-
out
n the city and allow Council to invest up to an additional $110
approved the
More than 3,000 residents provided feedback during the
the five goals of the Strategic Plan. The following four
use trails, and improvements to walkways and trails that connect
-
Council
In October, wide network. development of the plan. Recommendations fordevelopment of 43 km of onstreet multineighbourhoods.
In October, Council approved this bold, ambitious plan to support business recovery, to create a future where everyone can make a difference, and to propel our community forward. This
10community initiatives imillion, without relying on a tax rate increase. The plan will put a spotlight on pandemic recovery in our community and address that have emerged through
:
in 2020
Completions and Achievements
progress in the projects committed to under
Projects
Plan
ake It Kitchener 2.0 Strategy
Cycling and Trails Master Plan UpdateM
1. 2.
2020 Business Plan Strategic The City made considerable plan projects were completed
2 - 14
9
-
se
u
ecure
s
and a
and the
and
eet the
Working
wnership
Kitchener
-
elp
o
unity.
Housing for
h
.
for
m
-
, the strategy
and
, filling data gaps
was launched in
rocesses
pproach
p
a
ffordable
ousing
a
is a made
h
ccountability
olicies, a
ased
ollaboration
p
b
c
-
s
community partners
omelessness
,
for City staff
h
2022 Strategic Plan,
ning
-
ight
r
ffordable
nd
lig
a
e
ental and
, a
r
xperience ore
elp
Housing for All
e
h
m
,
uman
h
onitoring and
dvocacy
ived
m
a
l
ffordable
acilitate
a
f
With a
stigma learning program
, through
ffective
-
and to
l
ity
c
ousing
As a key action from the 2019
ommitment to ommunity,
An antithe fall 2020 learning catalogue, with greater focus given to addressing both the topics of mental health and addiction. Antistigma training will now become a core learning program
with ongoing evaluation and customization as required to mdiversity of staff needs throughout the organization and to ensure the content is relevant to evolving community needs.
Council. coutlines city actions tochof and ecollaboratively with our Advisory Committee, the Region of Waterloo, members of the publicdevelopment industryblueprint for an even more vibrant
and caring com
Housing Strategy
Reduce Social Stigma through Staff Training
3. 4.
2 - 15
10
--
the
ontent.
providing automated
based work and community
-
the fall to include 15 property
e Online Customer Service Portal Development
part learning program for staff in partnership
-
lighting and Indigenous art.
delivering service to Indigenous communities. This sought
emails for 15 parking case types in the spring of 2020,updates to customers when cases are created and when assigned or closed. The project was further expanded instandard case types.
Kitchener launched a fourwith the Region of Waterloo, City of Waterloo and City of Cambridge in fall of 2020, with a Phase Two planned for 2021. The sessions covered original cultures,
history of settlement and allyship with Indigenous Peoples and targeted priority staff in areas relating to senior leadership roles and those responsible for landdevelopment. The course
will be adopted as a core learning program and will be evaluated and enriched as needed to ensure that it fulfills the intent of the Truth and Reconciliation Commission and effectively
supports employees in after learning opportunity was delivered to 80 participants over a fourweek period. The course was highly rated by participants for both the acquisition of new
knowledge and delivery of difficult c
Language Interpretation Support and th
-
use trails.
-
:
s
include
progress
Projects
ndigenous Competency Training for Staff
The conversion of Gaukel Street into a community space with patio tables, Approximately 7 kilometres of new multiLighting at the Civic District Garage converted to LEDs.648 new trees
planted. Close the Loop with CitizensI
1.2.
Other strategic plan Completion of the Community Climate Action Plan, Multiare anticipated in early 2021. Business Plan
2 - 16
11
on Lab
forward
-
.
.
st three years, the Lab has successfully
ng existing staff resources within the
The final year of the Civic Innovati
identify for interested commodities, access bid
-
winning Digital Kitchener strategy, the achievements
-
at the City of Kitchener
Vendors can now selfdocuments and submit submissions electronically for all solicitation opportunities
Guided by the awardof the Lab led the City of Kitchener to be recognized internationally as a leading smart city and further solidified partnerships with local tech and academic communities.
Over the laexplored emerging technologies such as Internet of Things (IoT), artificial intelligence, machine learning, and augmented reality to support City service delivery transformation.
pilot was a busy one with significant advancements in the development and use of design sprints and rapid prototyping of ideas and technologies. Staff developed a plan to integrate
continuing the Digital Kitchener Innovation Lab activities leveragidivision. An update on the activities of the Lab and our goapproach was presented to Council in December
Tendering
-
Civic Innovation Lab at CommunitechE
3.4.
2 - 17
12
ain better
based tool
-
will serve the
our suite of SAP
itive map
allows us to g
it
staff, which
is a Win/Win/Win for our
,
it enriches
example of collaboration between
launch
and
,
great
and processes; reimagined highly visual and implified and automated system for staff to
a s
o come.
and awareness
provides
This project was a
. It
ts, and policies. The improvements will result in enhanced
Two Lean process reviews were completed, resulting in 18 distinct improvement projects that led to implementation of 34 improvements to the site plan review and approval process and
9 improvements to public engagement processes. Highlights include: an intufor finding information on development applications across the City; a during its first offering; procurement
of a video series to help explain complex planning concepts more accessible public notices; and establishing a representative volunteer group of citizens to assist staff by providing
insight and feedback on a variety of development services processes, improvements, projeccollaboration, better communication, streamlined and more inclusive processes, increased accountability,
and a continuous improvement culture. A successful implementation to automate employees expense reimbursements, the SAP Concur organizationsubmit expenses and managers to approveapplications.Acco
unting, SAP Business Systems and TIS corporation for years t
Implementation
Electronic Reimbursement
Development Services Review
6.
5.
2 - 18
13
here.
egion. Due to the
a bikeshare
R
ikeshare feasibility study
b
Progress Update
design work is currently 60%
wide
-
egion
R
Completed in 2019.Read Complete Streets Kitchener A was approved that recommends a collaborative approach to program throughout the pandemic, the finalization of the bikeshare program
will likely be delayed until 2022.The detailed complete, with community engagement ongoing. A report to Council is anticipated in December 2020. The report will present the plan and
recommend an installation schedule.
20212022
--
23
Complete
Timeline to
Completed20192020 New date: 2022 2020 New date: 20
Project
Manager
Barry Cronkite Transportation Services Barry Cronkite Transportation Services Darren Kropf Transportation Services
.
ch
town by 2022
Connected to
cent
Project
ikeshare service in whi
b
made available for shared use
Actions
hare Program
Complete StreetsƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЊВ͵Bikes Implement abicycles are to the public in an effort to addrmiledetermine the most appropriate system.Protected Cycling Networkthe Downtown
Install a continuous and protected cycling network that connects adjaneighbourhoods to the down
.
Friendly Transportation
Transform how people move through the city by making the transportation network safe, convenient, comfortable and connected.
-
2022
cent
Statement
2022 Strategic Plan
-
PeopleGOAL:
town by
Strategic Plan Action
Develop a set of Complete Encourage and incentivize Install a continuous and
1.
1.1 Streets (safe and comfortable) guidelines and an associated evaluation scorecard by 2020 to apply to roadway construction projects.1.2 alternative modes of transportation by developing
and subsidizing a bikeshare program by 2021.1.3 protected cycling network that connects adjaneighbourhoods to the down
2019
2 - 19
14
Use Trails have been
-
Progress Update
.
The Cycling and Trails Master Plan was presented to and approved by Council in October 2020. Read the Cycling and Trails Master Plan hereApproximately 7 km (5 km Regional, 1.8 km City)
of new Multicompleted. Some work has been delayed due to the pandemic.Gaukel Street was closed to traffic during the pandemic and will continue to remain closed as a passive pedestrian
space. Indigenous art has been installed. Staff continue to work on a more formal plan.
2022
-
Complete
Timeline to
Completed202020202020 New Date: 2021
Project
Manager ace Design
Liz Christensen Transportation Services Liz Christensen Parks & Open Sp& Development Darren Kropf Transportation Services
-
-
and
use trails and
Round
-
-
Trails and
road cycling et Plan for Gaukel
-
se
road trails U
--
education and
Project
connectivity and year
First Stre
-
Use Trails and Pathways
include on
-
, in one comprehensive plan
with an initial target of year
,
the 2010 Cycling Master Plan
e
Cycling and Trails Master Plan UpdateConnectivity and YearPedestrian
athways
1.4.1 Updatthe 2012 MultiMaster Plan to facilities, as well as offinfrastructurethat also addresses wayfinding.1.4.2 Maintenance of MultiP Prioritize actions,round maintenance to multipathways
through the Cycling and Trails Master Planround access to a minimum of an additional 3 km of existing trails by 2022.1.5.1 Street Develop plans to prioritize pedestrians over other
travel modes on Gaukel Street.
.
City
o
round access to
-
first streets
-
Statement
use trails and pathways
-
round maintenance t
-
Strategic Plan Action
Improve connectivity and Develop a plan to create
minimum of an additional 3
1.4 yearmultias prioritized through the Cycling and Trails Master Planwith an initial target of providing yeara km of existing trails by 2022 1.5 pedestrianbetween Victoria Park andHall
and between the ION and Kitchener Market by 2022.
2 - 20
15
.
here
sources.
Progress Update
Progress Update
Work to begin in 2021
Project completed in 2019. Read the Corporate Climate Action Plan
2022
-
Complete
Timeline to
2021
ompleted
Complete
Timeline to C2019
-
Project
Manager
Darren Kropf Transportation Services
Project
Manager
Claire Bennett AdministrationDevelopment Services
et Plan for
Reporting
͵
Project
First Stre
-
Project
Market
Pedestrian
nually on greenhouse gas emission
1.5.2 Kitchener ƚƩƉ Ʒƚ ĬĻŭźƓ źƓ ЋЉЋЊ
Corporate Climate Action PlanƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЊВ͵anreduction will continue until 2026.
Statement
Statement
Environmental Leadership
Achieve a healthy and livable community by proactively mitigating and adapting to climate change and by conserving natural re
Strategic Plan Action
Launch and implement a
Strategic Plan Action
2.
2.1 Corporate Climate Action Plan by 2019 to achieve an absolute greenhouse gas emission reduction of at least 8% by 2026.
Goal:
2 - 21
16
-
project with similar
Progress Update
are planning to undertake engagement
retrofit the remaining lighting at the
Originally the 2020 capital energy reserve project was to Kitchener Operations Facility (KOF). Due to COVID19 safety concerns the project was switched to outfitting Civic District Garage
to LEDs.The KOF project is on hold until 2021 and will be reassessed if it or another payback will take its place.The community climate action plan will be presented to council early
in the first quarter of 2021. Staff provided an update to Council in November 2020 and through Winter 2020/2021 as well as Spring 2021.
2022
-
Complete
Timeline to 20202020 New Date: 2021 2020 New Date: 2021
--
Project
Manager
Claire Bennett AdministrationDevelopment Services Claire Bennett AdministrationDevelopment Services Dave Schmitt Forestry & Natural Areas Management
The
Project 2020.
availability, quality of
Tree Canopy Target
to LEDs in
Leverage the Energy Efficiency Reserve Fund Retrofit the remaining lighting at Aud Community Climate Action Plan Complete the 80x50 Community Climate Action Plan.2.4.1 Review the current
canopy cover and set an achievable target based on best practices as well as constraints such as land soil, etc. in order to guide ongoing and future investment in tree planting, protection
and maintenance.
ies and
canopy
.
ciency Reserve
i
Statement
.
ergy Eff
arting in 2019, leverage
.
StDevelop a Community Implement the
Strategic Plan Action
2.2 the EnFund and other resources to reduce consumption and emission at our facilitin our operations 2.3 Climate Action Plan with partner organizations by 2020 2.4 Sustainable Urban
Forest Strategy with a focus on establishing a tree target by 2020 and eliminating the current (2018) tree planting backlog by 2022
2 - 22
17
Progress Update
rt. However, increased access to recycling and
648 trees were planted in the fall. Planning has started for 2021 planting and will require approval of capital budget.Due to the pandemic, large public events were cancelled, and this
project is postponed until events restaorganics diversion across public facilities and spaces has been provided.
20222021
--
Complete
Timeline to 20202020 New Date: 2022
-
Project
Manager
Adam Buitendyk Forestry & Natural Areas Management Claire Bennett AdministrationDevelopment Services
acklog
B
Project
lanting
2022.
P
run events with large
-
ion
Tree
iminat
2.4.2 El Plant at least 750 trees in 2020, with the goal of reaching 2,500 trees and eliminating the current backlog by the end of Waste Diversion Strategy: Increase Waste Diversion
in Our Public Spaces and Events Expand the Waste Diversion Station to all Cityvolunteer involvement, and evaluate expanded waste diversion stations at events, parks and public facilities.
Statement
.
diversion programs at
Reduce waste diverted to
Strategic Plan Action
2.5 landfills by implementing new our facilities and events by 2021
2 - 23
18
.
here
Progress Update
about this project
Completed 2019.Read the Urban Design Manual here.Completed 2019. Learn
ng arts and culture, and great places
dd
Complete
Timeline to Complete2019Complete2019
Project
Manager
Dayna Edwards Planning Cory Bluhm Economic Development
Project
Buildout of 44 Gaukel
Urban Design ManualƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЊВ͵3.2.1 ƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЊВ͵
-
tech
wide
-
-
h/med
2021 for the food
-
Build a vibrant city by making strategic investments to support job creation, economic prosperity, thrivi
Vibrant Economy
Strategic Plan Action Statement
Complete a new Urban Design Manual Foster the creation of a city
3.
3.1 by 2019 that expresses city building and design expectations to ensure vibrant new development throughout Kitchener.3.2 network of incubators, accelerators and coworking spaces by
completing the buildout of 44 Gaukel in 2019, advancing work on a Creative Hub and undertaking business cases in 2019manufacturing and healtindustries.
GOAL:to live.
2 - 24
19
2020. Strategy
.
Because of the
October
investigating
here
Progress Update
are
owned space and with
-
Staffopportunities for incubators within Citypotential partners. Business cases will be prepared and presented in late 2020 and 2021.The strategy was approved by Council in implementation
will commence.Read the Make It Kitchener 2.0 Strategy Initial focus has been on supportive housing. Due to the pandemic, finalization of the review is delayed until 2021.pandemic and
urgent need around affordable housing and Make It Kitchener, components of the review commenced in 2020. Comprehensive review and completion anticipated in 2021.
2021
-
Complete
Timeline to 2020Completed 20202020 New date: 2021
msky &
u
Project
Manager
Cory Bluhm Economic Development Lauren Chlumsky Economic Development Lauren ChlRob Morgan Economic Development
-
-
ubators.
eview
Project
Accelerator and Co
ties by 2020 to determine
tech industry inc
comprehensive review of city
-
Owned Property R
-
3.2.2 Incubator, Working Space Network Lease all spaces in the Creative Hub, explore the potential to facilitate a Food Incubator with a business case pending, and explore partnerships
for the development of manufacturing and health/med Make It Kitchener 2.0 Strategy Develop the Make it Kitchener 2.0 Strategyby 2020 with a focus on transformative actions to ensure
the attraction, success and retention of diverse businesses, talent, and arts/culture across the city.City Complete aowned properhow they could be effectively used to advance city strategic
objectives.
Kitchener 2.0
owned properties by 2020 to
Strategic Plan Action Statement
Develop the Make it Complete a comprehensive review of
-
3.3 Strategy by 2020 with a focus on transformative actions to ensure the attraction, success and retention of diverse businesses, talent, and arts/culture across the city.3.4 citydetermine
how they could be effectively used to advance city strategic objectives.
2 - 25
20
a
s
this step
.
3
City and Business
Progress Update
Through Make It Kitchener,
date of 202
-
Make It Kitchener 2.0 provideland disposition framework. Due to the pandemic, disposition of a key property will be delayed until 2021. The Improvement Area will develop a new Downtown
Strategic Plan in 2021.City Council emphasized a need to develop a vision through comprehensive community engagement for each site prior to disposition. Undertaking will result in the
revised project endWork to begin in 2021.Work to begin in 2021.
1
2022022
--
3 0
Complete
Timeline to 2020 New date: 202 2022021
Project
Manager
Brian Bennett Economic Development Cory Bluhm Economic Development Cory Bluhm Economic Development
͵
Project
owned property brought to
-
Owned Property Brought to
-
Innovation District (Bramm Yards) Civic District Master Plan
arket
3.5.1 CityM Develop a vision for downtown Kitchener and continue to position downtown Kitchener as a leading destination for redevelopment opportunities, with at least one new citymarket
by 2020.3.5.2 Master Plan Finalize the Innovation District (Bramm Yards) Master Plan by 2022.3.5.3 ƚƩƉ Ʒƚ ĬĻŭźƓ źƓ ЋЉЋЊ
-
an by 2021 and
ision for downtown
Strategic Plan Action Statement
Develop a v
3.5 Kitchener and continue to position downtown Kitchener as a leading destination for redevelopment opportunities, with at least one new cityowned property brought to market by 2020.
Finalize the Innovation District (Bramm Yards) Master Plthe Civic District Master Plan by 2022.
2 - 26
21
s
is
ork
&
made
Council
s
The w
to be
August 2020
is
Given delay
roup
in
tegy
one interviews and
-
on
-
19 pandemic, the work of
-
ded to June 30th, 2021.
n
Housing Stra
an Equity Office
to be hired in 2021.
dedicated working g
7
Progress Update
by
s been exte
committees continued to meet and actively
-
recommended
31, 2020 and staff were directed to continue
that will make up
nd the sub
Equity, Diversity and Inclusion resumed regular meetings and collaboratively developed a workplan focused on work is being advancedup of representatives from the larger task force.approved
the creation of and associated staffing due to the onset of the COVIDthe task force haThe Draft Housing Strategy was delivered to Council on August working towards the final Housing
Strategy. Public feedback was obtained on the Draft Housing Strategy through virtual focus groups, onean Engage Kitchener Survey. The Advisory Committee awork on their mandates. Staff
also presented on the preliminary feasibility analysis on Inclusionary Zoning to Council and were subsequently directed to continue thwork. The presented to Council in December 2020.
date:
Complete
Timeline to 2020 New 2021 Completed 2020
-
er
Project
Manag
Elin Moorlag Silk AdministrationCommunity Services Andrew Ramsaroop Planning
.
industry
Strategy
represented
-
Project
f Waterloo,
nity groups and the
o
reate an Equity, Diversity
Equity, Diversity and Inclusion Strategy Cand Inclusion focused on better engaging and serving marginalized and underpeople, as well as creating a more inclusive City workplace.Affordable
Housing Strategy Create an Affordable Housing Strategy for Kitchener by 2020 in collaboration with the Region commudevelopment
.
f
o
.
nclusion
I
nity groups and
industry
Statement
Diversity and
Caring Community
,
Strategic Plan Action
Create a comprehensive Create an Affordable Housing
4.
4.1 EquityStrategy by 2020 to combat systemic barriers to full economic and social participation in the city 4.2 Strategy for Kitchener by 2020 in collaboration with the Region Waterloo,
commuthe development
GOAL:supporting our diverse populations & helping to make housing affordable.
2 - 27
22
redeployed to
launched in the
-
was
Q1 of 2021.
in
.
here
program was re
Progress Update
gma training will now become a core
anticipate starting
sti
-
but
,
stigma learning
-
An antiIncreasing our Understanding of Mental Health and the topics of mental health and addiction through this course. Antilearning program with ongoing evaluation and customization
as required to meet the diversity of staff needs throughout the organization and to ensure the content is relevant to evolving community needs. Project Completed 2019. Learn about this
project Staff resource supporting this project run summer programs and services. Staff resources have not been available to reconvene this work
d
e
Complete
Timeline to Completed 2020Complet20192020 New date: 2021
ood
er
Project
Manag
Paula Dunn Human Resources Mark Hildebrand NeighbourhPrograms & Services
tigma
S
raining
ocial
for Safe
T
S
respond
needs
Business Case
Project taff
S
Reduce Support Mill Courtland
4.3.1 through Provide staff with the resources toeffectively to changing community demographics. 4.3.2 Consumption and Treatment FacilitiesƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЊВ͵4.4.1 Community Centre
Expansion Complete a assessment and business case to determine the requirements for an addition to the Mill Courtland Community Centre.
.
d an Open
resources
and support
an
ers,
Statement
Strategic Plan Action
Reduce social stigmas Better utilize existing facilities,
4.3 experienced by those living with mental illness and addiction in our community through staff training and supporting the creation of appropriate safe consumption and treatment facilities
in Kitchener 4.4 provide relevant programming at community centthe equitable distribution of leisure programs and across neighbourhoods. Start work on the Mill Courtland Community Centre
expansion by 2020 and the Rosenberg Community Centre by 2021. Complete the Huron Brigadoon Community CentreSpace Strategy by 2021.
2 - 28
23
.
vacancies in the Parks
Progress Update
approved. Application to the Province for
Project to start in 2021Detailed design has been completed. Building permits have been approval of design and budget have been submitted by Waterloo Region District School BoardProgress
has not been possible as a result of pandemic response priorities and staffing Design and Development section.
20212021
--
Complete
Timeline to 20212020 New date: 2022 2020 New date: 2022
er
Project
Manag
Mark Hildebrand Neighbourhood Programs & Services Mark Hildebrand Neighbourhood Programs & Services Niall Lobley Parks & Cemeteries
͵
/ Community
Rosenberg
Project
New Huron Brigadoon Open Space Strategy
function, are planned,
4.4.2 Community Centre/SchoolBusiness CaseƚƩƉ Ʒƚ ĬĻŭźƓ źƓ ЋЉЋЊ 4.4.3 Area School Centre Construction Construct a joint school/community centre in the Huron Brigadoon area, in partnership
with the Waterloo Region District School Board.4.4.4 Develop an open space strategy to explore the value of open spaces, how they maintained, and managed, and including a review of
permitted uses in parks.
Statement
Strategic Plan Action
2 - 29
24
and
is scheduled for
eference
r
pandemic. Support for
-
erms of
he t
Progress Update
ists and cultural organizations will be
he appropriate time to commence
Waterloo for stakeholder consultation,
T
Developed partnership with the Region of Waterloo and the City of research and analysis. Tplanning for stakeholder consultation late 2020.community engagement is postprofessional art
2021
-
Complete
Timeline to 2020 New date: 2022
er
Project
Manag
Emily Robson Economic Development
cultural
-
Project
engaging a broad
section of the
-
Arts and Culture Plan Develop a new and inclusive Arts and Culture Plan by crosscommunity including the arts and creative industry sector and multicommunities.
section
-
Statement
cultural communities to
-
Strategic Plan Action
Engage a broad cross
4.5 of the community including the arts and creative industry sector and multidevelop an inclusive arts and culture Plan by 2021.
2 - 30
25
n
2020
Progress Update
project is expected to complete in 2021.
The
ivery channels, with feedback collection across
Staff are working with the selected vendor to finalize the contract for this service. A more limited implementatioof this service, with key frontline users including Bylaw, Revenue,
Corporate Contact Centre and Community Centres, is scheduled to be complete by the end of with additional roll out to more staff in early 2021.The program has been adjusted to reflect
current service delmultiple channels starting in late 2020. Additional service channels will be incorporated into the program as they open.
Complete
Timeline to
2020 New date: 2021 2020 New date: 2021
Project
Manager
Jana Miller Corporate Customer Service Christine Baker Corporate Customer Service
-
-
-
person
-
7 on
-
language
r Satisfaction
-
24
an organization
Project
Language
-
ulti
MInterpretation Support Implement a demand multiinterpretation support for telephone and ininquiries to enable staff in all facilities to ensure a more consistent and equitable experience
for all customers.Customer Satisfaction Program Implement wide CustomeProgram that enables realtime feedback, monitoring and reporting of satisfaction data to drive service improvements.
of real
wide
-
collection
demand customer .
-
Great Customer Service
Provide onIntroduce a corporate
5.
Strategic Plan Action Statement
5.1 service support in many languages through the Corporate Contact Centre by 2020 5.2 Customer Satisfaction Program that will allow for the time feedback from customers accessing city
facilities, programs, and services by 2020.
GOAL:
2 - 31
26
endor in the
v
y the
. The public will be able to test the
Progress Update
2021
launch will take place once the feedback from the
Project to start in 2021Project to start in 2021
The project had been on track to launch in December 2020 with a soft (beta/test) version of the new website and MyKitchener portal to be available to the public. At the time of this
update, exact timing for this launch is being reviewed because of delays bdevelopment of some of the functionality. It is likely to launch early in functionality of the portal during
the beta testing and we will make improvements based on their feedback. The official public beta version has been reviewed and final changes to the website and portal have been made.
20222022
--
Complete
Timeline to
2020 New date: 2021 20212021
Project
Manager
Jana Miller Corporate Customer Service Jana Miller Corporate Customer Service Jana Miller Corporate Customer Service
on
-
services in
-
ugh a
Project
a centralized online
Development
aunch
Online Customer Service Portal Lservice portal where citizens can access their eone place thropersonalized, single signaccount. Set and Communicate Service LevelsƚƩƉ Ʒƚ ĬĻŭźƓ źƓ ЋЉЋЊ͵Customer
Experience ProgramƚƩƉ Ʒƚ ĬĻŭźƓ źƓ ЋЉЋЊ͵
.
by 2022
and allowing financial
,
es, including: tree
Enhance customer experience Set clearly communicated and Implement a comprehensive
Strategic Plan Action Statement
5.3 online by delivering customized information, providing easy access to servicestransactions by 2021.5.4 specific service levels for frequently asked about or accessed City servicmaintenance,
parking, property standards complaints, snow clearing and grass cutting 5.5 Customer Experience Review Program to help ensure services are easy and convenient to access from
2 - 32
27
closure
terms of reference for
January 2020. Terms of
p the
.
in
o
ce.
due to focus on reopening
Progress Update Terms of reference for consultant services was drafted in March 2020. Work pausedfacilitiesConfirmed involvement of Waterloo Region District School Board to assist with
the study reference for consultant services was drafted in February 2020. Work paused due to teacher strike, pandemic and retirement of key staff resourPlanning is underway to develthe
pool business case.Work was paused due to closure of facilities and the impacts on ice sport organizers
2021
-
Timeline to Complete 2020 New date: 2021 2020 New date: 2021 20202020 New date: 2021
Project Manager Kim Kugler Sport Kim Kugler Sport Kim Kugler Sport Jeremy Dueck Sport
relocate
e
Feasibility Study
Pool Business Cas
Community Services Budd Park Strategy Identify potential sites and estimated costs to the recreational assets at Budd Park and compare the costs to the economic benefits of using the
Budd Park for employment lands.Cameron Heights Pool Collaborate with the Waterloo Region District School Board to determine the renovations and estimated costs to isolate the pool operation
from the school operation to preserve a recreational asset in the downtown.Southwest District Engage community residents/stakeholders in a needs assessment and business case to determine
the elements to be included in the new pool.Ice Demand Study Evaluate ice user needs and trends for ice time to determine the timing of a new arena.
BP02BP03BP04BP05
2020 Business Plan Projects
2 - 33
28
-
ck, the
portal to be available to
portal and website
-
version has been reviewed and final changes
providing automated updates to customers when
further expanded in the fall to include 15 property
Progress Update Completed 2020close the loop emails for 15 parking case types in the spring of 2020,cases are created and when assigned or closed. The project was standard case types.
so that the entire online experience
likely be early in 2021. The public will be able to test the
Timeline to Complete Completed 2020
is delayed
Progress Update The project had been on track to launch in December 2020 with a soft (beta/test) version of the new website and MyKitchenerthe public. At the time of this update, exact
timing for this launch is being reviewed because of delays by the vendor in the development of some of the portal functionality. Although the website portion of this project is on tralaunch
launches at the same time. This will provide the most complete user experience that meets our customer's expectations for this project. The adjusted beta launch date willfunctionality
of the website and portal during the beta testing and we will make improvements based on their feedback. The official launch will take place once the feedback from the public beta to
the website and portal have been made.
Project Manager Jana Miller Corporate Customer Service
Timeline to Complete 2020 New date: 2021
ing
Project Manager Nicole Amaral Corporate Communications & Market
notifications to enable citizens to
-
the
first designed
-
have
to
Community Services Close the Loop with Citizens Expand email autoreceive email notifications for all parking complaints.Corporate Services Transformation and Relaunch of Kitchener.ca
Relaunch Kitchener.ca as a usersite that is easy for residents to quickly find any information they are looking for, as well as interested in delivered to them.
BP06 BP07
2 - 34
29
19 health and economic
-
staff curriculum as a
that it fulfills the intent of the
Cambridge in the Fall of 2020. The sessions
community development. A prioritization
part learning program in partnership with the Region of
-
based work and
-
Provincial governments are focused on COVID
Progress Update Kitchener launched a fourWaterloo, City of Waterloo and City of covered original cultures, history of settlement and allyship with Indigenous Peoples and targeted priority
staff in areas relating to senior leadership roles as well as those responsible for landframework to identify key staff has been developed for application to training throughout 2021
and beyond. The course will be adopted as a core learning program and will be evaluated and enriched as needed to ensure Truth and Reconciliation Commission and meets the needs of employees
in delivering service to Indigenous communities. Initial training for council will be deployed in December 2020 and can be expanded if needed using the foundation for future learning.
Staff working on other Government Relation issues related to pandemic response and support, e.g. emergency operating funding from federal and provincial government. Federal and impacts/priorities,
which change regularly; staff have been advocating about local impacts.
2021
-
Timeline to Complete Completed 20202020
Project Manager Paula Dunn Human Resources Paul Grivicic Office of the Mayor & Council
-
-
l
members
indigenous staff
-
Corporate Services Indigenous Competency Training for Staff Implement training for staff to improve customer service and increase capacity of nonand council across the organization to
develop respectful relationships with indigenous peoples.Government Relations & Advocacy Plan 20202021 Work collaboratively with Council to determine and priorities for the 20202021
advocacy period with the federal/provinciagovernment.
BP08BP09
2 - 35
30
pected completion by December 2020.
Progress Update The contract for the new system was awarded in September 2020. Implementation and configuration are currently underway with an exBeta user testing is set to begin in
December 2020 with a phased in launch occurring in early 2021.Designs and plans for online platform are complete within Licensing Services. Moving to online public portal is dependent
on AMANDA 7 and online payment options. This project is on hold until these system upgrades are complete.
TBD
-
Timeline to Complete 2020 New date: 2021 2020
Project Manager Jeff Bunn Legislated Services Helen Fylactou Legislated Services
through
Corporate Services Electronic Agenda Management Create, prepare, approve and publish meeting agenda packages and minutes in a more efficient, collaborative, streamlined manner.Online
Business Licensing Bring applying and paying for a business license online, available to the public the AMANDA Public Portal.
BP10BP11
2 - 36
31
cember
technologies.
De
-
2019 to the end of 2020
tee on Dec 7th.
-
led initiatives into corporate capital
-
continuous improvement opportunities were identified, which will help
forward approach will be presented to commit
-
; and, piloting ways to leverage resident
Progress Update Four new improvement projects were completed between September 2020: leveraging AMANDA to report measures of success in the site plan process; improving file management
accountability in development processes; developing a new urban design scorecard that will streamline the requirement for an urban design briefprojects. A final report highlighting
improvements from midwill be shared with Council in early 2021. Throughout the development services review, manyinform and operationalize future continuous improvement workplans.
Progress Update The final year of the lab pilot has been a busy one with significant advancements in the development and use of design sprints and rapid prototyping of ideas and Staff
have developed a plan to integrate continuing the Digital Kitchener Innovation Lab activities leveraging existing FTEs within the division. An update on the activities of the Lab and
our go
Timeline to Complete Completed 2020
Timeline to Complete Completed 2020
Project Manager Margaret Love Administration Development Services
Project Manager Dan Murray Technology Innovation & Services
a review of our
year pilot.
-
enters its final year
Development Services
the 3
Corporate Services Civic Innovation Lab at Communitech Focus on bringing the knowledge gained and products developed out of the Lab and operationalize them within the City as the Labof
Development Services Review Undergodevelopment services to bring greater focus, coordination and accountability to our development functions.
BP12 BP13
2 - 37
32
has
delayed
is
nt Charges study
live November 2020. Training for
went
for the end of November/beginning of
. The Point of Sale part of the project
Progress Update Provincial legislation proclaimed in Fall 2020. Planning to combine this review with a Developmeupdate starting in Q1 2021.December Capital Variance report planned to
go to Council in Q1 2021. Other 2020 LTFP actions (e.g. policy updates) will be delayed until 2021.SAP Concur Expense staff is scheduled December. Cutover plan communicated to the
organization.Expansion of Payment Options part of the project starteduntil 2021.
Timeline to Complete 2020 New date: 2021 2020 New date: 2021 Completed 20202020 New date: 2021
Project Manager Ryan Hagey Financial Planning Ryan Hagey Financial Planning Brenda Johnson Accounting Saleh Saleh Revenue
us
past
ified
.
ptions
xpense
based forms.
-
paper
Implementation
corporate credit card,
Term Financial Plan
-
payment options for vario
g
benefit charge study to support
lan
ansion of Payment O
recommended actions ident
P
xp
inancial
, and expand
F
.
erm
T
Financial Services
ong
eimbursements to eliminate
Community Benefit Charge Study Complete a communityestablishing a charge under the new Bill 108 framework L Implement/consideras 2020 items in the Lon Electronic Reimbursement Implementation
Consolidate all employee travel and ereimbursements includingmileage, parking, conference and petty cash r Point of Sale and E Replace the existing Point of Sale system, which is its
life cycleservices.
BP14BP15BP16BP17
2 - 38
33
by
off
-
at the City of
September. Project kick
-
identify for interested commodities,
-
mid
-
.
2020, build Q1 2021 and roll out to initial groups
end
spring.
-
-
Completed 2020
Progress Update Agreement signed scheduled for November 2nd with Kronos Team. Initial estimated milestones include workshops completed yearmid Vendors can now selfaccess bid documents
and submit submissions electronically for all solicitation opportunitiesKitchener
Progress Update Progress is ongoing although somewhat delayed (6 months) due to recruitment delays during the pandemic. As this project is projected to be completed in March 2028, is
expected that the delays will not impact overall project.
2028
-
Timeline to Complete 2020 New date: 2021 Completed 2020
Timeline to Complete 2020
Project Manager Jason Winter Asset Management & Business Solutions Ryan Scott Procurement
Project Manager Nick Gollan Sanitary & Stormwater Utilities
based timesheets.
-
and submit tenders,
,
tendering module to enable vendors to
-
bile time entry for operations,
execute stormwater management
identify for interested commodities, access bid
Infrastructure Services
Financial Services
-
Tendering
-
Implement mo
Implementation of the Federal Disaster Mitigation and Adaptation Fund (DMAF)Plan and infrastructure projects across the city to leverage the DMAF grant funding and advance the implementation
of the 2016 Integrated Stormwater Management Master Plan.
Mobile Time Entry eliminating the need for paper E Implement an eselfdocuments and drawingsproposals and quotations electronically.
BP18BP19 BP20
2 - 39
34
f
2021 period. By end o
-
ld. RFP issued for a number
plementation of a decision
deliverables are being rescheduled to align with the 2022
Progress Update The project was delayed due to the pandemic, with a key member of the team supporting facility recovery preparation. Finalbudget. Work has progressed on supporting data
work, including Building Condition Assessments, a municipal comparator survey, and an industry benchmarking review; as well as the continuing pilot imsupport software (Assetic Predictor)
to assist in developing capital projections.Schlegel Phase 1 is completed. Phase 2 has been tendered and awarded and is on schedule for late summer 2021 completion.Survivor Garden is
currently on hoof park rehabilitations to start in 2021. Additional scope of work to address site and facility conditions and other areas of work was approved by Council in October
2020. Winter work approved for 20202020, waterproofing insulation and granular fill will be completed for Phase 1. Phase 1 will be completed by end of Q3 2021.
202120212021
- --
Timeline to Complete 2020 New date: 2022 20202020
Project Manager Beatrice Powell Facilities Management Niall Lobley Parks & Cemeteries Lynda Stewart Facilities Management
Park;
; and
on Carl Zehr
capital
RBJ Schlegel
r Spaces
ing
ss the infrastructure
urvivor Garden
focus
,
Program
term maintenance and
-
comprehensive review of facility
construction associated with the rehabilitation
Infrastructure Services
Facilities Infrastructure Conduct ainfrastructure needs that will incorporate building condition assessments, sustainability opportunities, and accessibility needs to identify current
gaps and inform longimprovement strategies to addredeficit.Implementation of Significant Parks Projects Complete Phase 2 design work for plan, design and construct the Scomplete the
upgrade to Westwood Park.Rehabilitation of City Hall OutdooConstruction Phase 1 Begin of City Hall Outdoor spacesSquare and College Street.
BP21BP22BP23
2 - 40
2019-2022 Strategic Plan Actions
1.PEOPLE-FRIENDLY TRANSPORTATION
GOAL: Transform how people move through the city by making the transportation network
safe, convenient, comfortable and connected.
Strategic Plan Action Project Project Timeline to
Manager Complete
1.1 Develop a set of Complete Streets Complete Streets Barry Cronkite Completed
(safe and comfortable) guidelines and an ƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЊВ͵ Transportation in 2019
associated evaluation scorecard by 2020 Services
to apply to roadway construction
projects.
1.2 Encourage and incentivize Bikeshare Program Barry Cronkite 2020-2022
alternative modes of transportation by Implement a bikeshare service in which Transportation
developing and subsidizing a bikeshare bicycles are made available for shared use to Services
program by 2021.
determine the most appropriate system.
1.3 Install a continuous and protected Protected Cycling Network Connected to Darren Kropf 2020-2023
cycling network that connects adjacent the Downtown Transportation
neighbourhoods to the downtown by Install a continuous and protected cycling Services
2022. network that connects adjacent
neighbourhoods to the downtown by 2022.
1.4 Improve connectivity and year-round 1.4.1 Cycling and Trails Master Plan Update Liz Christensen Completed
maintenance to multi-use trails and ƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЋЉ͵ Transportation in 2020
pathways as prioritized through the Services
Cycling and Trails Master Plan with an
initial target of providing year-round
access to a minimum of an additional 3
km of existing trails by 2022.
1.4.2 Connectivity and Year-Round Liz Christensen 2020-2022
Maintenance of Multi-Use Trails and Parks & Open
Pathways Space Design &
Prioritize actions, connectivity and year-Development
round maintenance to multi-use trails and
pathways through the Cycling and Trails
Master Plan, with an initial target of year-
round access to a minimum of an additional
3 km of existing trails by 2022.
1.5 Develop a plan to create pedestrian-1.5.1 Pedestrian-First Street Plan for Gaukel Darren Kropf 2020-2021
first streets between Victoria Park and Street Transportation
City Hall and between the ION and Develop plans to prioritize pedestrians over Services
Kitchener Market by 2022. other travel modes on Gaukel Street.
1
2 - 41
Strategic Plan Action Project Project Timeline to
Manager Complete
1.5.2 Pedestrian-First Street Plan for the Darren Kropf 2021-2022
Kitchener Market Transportation
Develop plans to prioritize pedestrians over Services
other travel modes between the Kitchener
Market ION station and Kitchener Market.
2.ENVIRONMENTAL LEADERSHIP
GOAL: Achieve a healthy and livable community by proactively mitigating and adapting to
climate change and by conserving natural resources.
Strategic Plan Action Project Project Timeline to
Manager Complete
Corporate Climate Action Plan Claire Bennett Completed
2.1 Launch and implement a Corporate
ƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЊВ͵ Reporting Administration- in 2019
Climate Action Plan by 2019 to achieve
annually on greenhouse gas emission Development
an absolute greenhouse gas emission
reduction will continue until 2026. Services
reduction of at least 8% by 2026.
Leverage Energy Efficiency Reserve Fund Claire Bennett 2020-2022
2.2 Starting in 2019, leverage the
Leverage the fund to undertake energy Administration-
Energy Efficiency Reserve Fund and
efficiency retrofit projects on City of Development
other resources to reduce consumption
Kitchener assets and capture and reinvest Services
and emission at our facilities and in our
the operating savings to pay for capital
operations.
costs.
2.3 Develop a Community Climate Community Climate Action Plan Claire Bennett 2020-2021
Action Plan with partner organizations Complete the 80x50 Community Climate Administration-
by 2020. Action Plan. Development
Services
2.4 Implement the Sustainable Urban 2.4.1 Tree Canopy Target Dave Schmitt 2020-2021
Forest Strategy with a focus on Review the current canopy cover and set Forestry &
establishing a tree canopy target by an achievable target based on best Natural Areas
2020 and eliminating the current practices as well as constraints such as land Management
(2018) tree planting backlog by 2022. availability, quality of soil, etc. in order to
guide ongoing and future investment in
tree planting, protection and maintenance.
2.4.2 Tree Planting Backlog Elimination Adam Buitendyk 2020-2022
Plant at least 750 trees in 2020, with the Forestry &
goal of reaching 2,500 trees and Natural Areas
eliminating the current backlog by the end Management
of 2022.
2
2 - 42
Strategic Plan Action Project Project Timeline to
Manager Complete
2.5 Reduce waste diverted to landfills Waste Diversion Strategy: Increase Waste Claire Bennett 2020-2022
by implementing new diversion Diversion in Our Public Spaces and Events Administration-
programs at our facilities and events by Expand the Waste Diversion Station to all Development
2021. City-run events with large volunteer Services
involvement, and evaluate expanded
waste diversion stations at events, parks
and public facilities.
3.VIBRANT ECONOMY
GOAL: Build a vibrant city by making strategic investments to support job creation, economic
prosperity, thriving arts and culture, and great places to live.
Strategic Plan Action Project Project Timeline to
Manager Complete
Urban Design Manual Dayna Edwards Completed in
3.1 Complete a new Urban Design
ƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЊВ͵ Planning 2019
Manual by 2019 that expresses city
building and design expectations to
ensure vibrant new development
throughout Kitchener.
3.2.1 Buildout of 44 Gaukel Cory Bluhm Completed in
3.2 Foster the creation of a city-wide
ƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЊВ͵ Economic 2019
network of incubators, accelerators
Development
and co-working spaces by completing
the buildout of 44 Gaukel in 2019,
advancing work on a Creative Hub and
undertaking business cases in 2019-
2021 for the food manufacturing and
health/med-tech industries.
3.2.2 Incubator, Accelerator and Co-Cory Bluhm 2020-2021
Working Space Network Economic
Lease all spaces in the Creative Hub, Development
explore the potential to facilitate a Food
Incubator with a business case pending,
and explore partnerships for the
development of manufacturing and
health/med-tech industry incubators.
3.3 Develop the Make it Kitchener 2.0 Make It Kitchener 2.0 Strategy Lauren Chlumsky Completed in
Strategy by 2020 with a focus on ƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЋЉ͵ Economic 2020
transformative actions to ensure the Development
attraction, success and retention of
diverse businesses, talent, and
arts/culture across the city.
3
2 - 43
Strategic Plan Action Project Project Timeline to
Manager Complete
3.4 Complete a comprehensive review City-Owned Property Review Lauren Chlumsky 2021
of city-owned properties by 2020 to Complete a comprehensive review of city-& Rob Morgan
determine how they could be owned properties by 2020 to determine Economic
effectively used to advance city how they could be effectively used to Development
strategic objectives. advance city strategic objectives.
3.5 Develop a vision for downtown 3.5.1 City-Owned Property to Market Brian Bennett 2021-2023
Kitchener and continue to position Develop a vision for downtown Kitchener Economic
downtown Kitchener as a leading and continue to position downtown Development
destination for redevelopment Kitchener as a leading destination for
opportunities, with at least one new redevelopment opportunities, with at
city-owned property brought to market least one new city-owned property
by 2020. Finalize the Innovation District brought to market by 2020.
(Bramm Yards) Master Plan by 2021
and the Civic District Master Plan by
2022.
3.5.2 Innovation District (Bramm Yards) Cory Bluhm 2020-2021
Master Plan Economic
Finalize the Innovation District (Bramm Development
Yards) Master Plan by 2021.
3.5.3 Civic District Master Plan Cory Bluhm 2021-2022
Finalize the Civic District Master Plan by Economic
2022. Development
4.CARING COMMUNITY
GOAL:
community spaces and programs; better engaging, serving and supporting our diverse
populations and helping to make housing affordable.
Strategic Plan Action Project Project Manager Timeline to
Complete
Equity, Diversity and Inclusion Strategy Elin Moorlag Silk 2020-2021
4.1 Create a comprehensive Equity,
Create an Equity, Diversity and Inclusion Administration-
Diversity and Inclusion Strategy by 2020 to
Strategy focused on better engaging and Community Services
combat systemic barriers to full economic
serving marginalized and under-
and social participation in the city.
represented people, as well as creating a
more inclusive City workplace.
4.2 Create an Affordable Housing Strategy Affordable Housing Strategy Andrew Ramsaroop Completed
for Kitchener by 2020 in collaboration with ƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЋЉ͵ Planning in 2020
the Region of Waterloo, community
groups and the development industry.
4
2 - 44
Strategic Plan Action Project Project Manager Timeline to
Complete
4.3 Reduce social stigmas experienced by 4.3.1 Reduce Social Stigma through Paula Dunn Completed
those living with mental illness and Staff Training Human Resources in 2020
addiction in our community through staff ƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЋЉ͵
training and supporting the creation of
appropriate safe consumption and
treatment facilities in Kitchener.
4.3.2 Support for Safe Consumption Completed
and Treatment Facilities in 2019
ƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЊВ͵
4.4 Better utilize existing facilities, 4.4.1 Mill Courtland Community Centre Mark Hildebrand 2020-2021
provide relevant programming at Expansion Business Case Neighbourhood
community centres and support the Complete a needs assessment and Programs & Services
equitable distribution of leisure programs business case to determine the
and resources across neighbourhoods. requirements for an addition to the Mill
Start work on the Mill Courtland Courtland Community Centre.
Community Centre expansion by 2020 and
the Rosenberg Community Centre by
2021. Complete the Huron Brigadoon
Community Centre and an Open Space
Strategy by 2021.
4.4.2 New Rosenberg Community Mark Hildebrand 2021
Centre/School Business Case Neighbourhood
With the Catholic School board, Programs & Services
complete a needs assessment and
business case to determine the
requirements for a joint community
centre/school in the Rosenberg area.
4.4.3 Huron Brigadoon Area School / Mark Hildebrand 2020-2022
Community Centre Construction Neighbourhood
Construct a joint school/community Programs & Services
centre in the Huron Brigadoon area, in
partnership with the Waterloo Region
District School Board.
4.4.4 Open Space Strategy Niall Lobley 2020-2022
Develop an open space strategy to Parks & Cemeteries
explore the value of open spaces, how
they function, are planned, maintained,
and managed, and including a review of
permitted uses in parks.
4.5 Engage a broad cross-section of the Arts and Culture Plan Emily Robson 2020-2022
community including the arts and creative Develop a new and inclusive Arts and Economic
industry sector and multi-cultural Culture Plan by engaging a broad cross-Development
communities to develop an inclusive arts section of the community including the
and culture Plan by 2021. arts and creative industry sector and
multi-cultural communities.
5
2 - 45
5.GREAT CUSTOMER SERVICE
GOAL:
easy and convenient services.
Strategic Plan Action Project Project Timeline to
Manager Complete
5.1 Provide on-demand Multi-Language Interpretation Support Jana Miller 2020-2021
customer service support in Implement a 24-7 on-demand multi-language Corporate
many languages through the interpretation support for telephone and in-person Customer
Corporate Contact Centre by inquiries to enable staff in all facilities to ensure a Service
2020. more consistent and equitable experience for all
customers.
5.2 Introduce a corporate-Customer Satisfaction Program Christine Baker 2020-2021
wide Customer Satisfaction Implement an organization-wide Customer Corporate
Program that will allow for Satisfaction Program that enables real-time Customer
the collection of real time feedback, monitoring and reporting of satisfaction Service
feedback from customers data to drive service improvements.
accessing city facilities,
programs, and services by
2020.
Online Customer Service Portal Development Jana Miller 2020-2021
5.3 Enhance customer
Launch a centralized online service portal where Corporate
experience online by
citizens can access their e-services in one place Customer
delivering customized
through a personalized, single sign-on account. Service
information, providing easy
access to services, and
allowing financial
transactions by 2021.
5.4 Set clearly Set and Communicate Service Levels Jana Miller 2021-2022
communicated and specific Set clearly communicated and specific service levels Corporate
service levels for frequently for frequently asked about or accessed City services, Customer
asked about or accessed City including: tree maintenance, parking, property Service
services, including: tree standards complaints, snow clearing and grass
maintenance, parking, cutting by 2022.
property standards
complaints, snow clearing
and grass cutting by 2022.
5.5 Implement a Customer Experience Program Jana Miller 2021-2022
comprehensive Customer Implement a comprehensive Customer Experience Corporate
Experience Review Program Review Program to help ensure services are easy Customer
to help ensure services are Service
easy and convenient to perspective by 2022.
perspective by 2022.
6
2 - 46
2021 Business Plan Projects
Community Services Project Timeline to
Manager Complete
BP01 Budd Park Strategy Kim Kugler 2020-2021
Identify potential sites and estimated costs to relocate the recreational Sport
assets at Budd Park and compare the costs to the economic benefits of
using the Budd Park for employment lands.
BP02 Cameron Heights Pool Feasibility Study Kim Kugler 2020-2021
Sport
Collaborate with the Waterloo Region District School Board to determine
the renovations and estimated costs to isolate the pool operation from the
school operation to preserve a recreational asset in the downtown.
BP03 Southwest District Pool Business Case Kim Kugler 2020-2021
Sport
Engage community residents/stakeholders in a needs assessment and
business case to determine the elements to be included in the new pool.
BP04 Ice Demand Study Jeremy Dueck 2020-2021
Evaluate ice user needs and trends for ice time to determine the timing of a Sport
new arena.
Corporate Services Project Timeline to
Manager Complete
Transformation and Relaunch of Kitchener.ca 2020-2021
BP05 Nicole Amaral
Relaunch Kitchener.ca as a user-first designed site that is easy for residents
Corporate
to quickly find any information they are looking for, as well as to have the
Communications
& Marketing
BP06 Indigenous Competency Training for Staff Phase 2 Paula Dunn 2021
Review the learning program developed under Phase 1 (2020) to ensure it is
Human
comprehensive and fulfills the learning objectives of the Calls to Action.
Resources
Pilot the existing learning program to address the urgent need for staff
training and to collect more feedback on the suitability of the program in
different areas of the organization.
BP07 Electronic Agenda Management Jeff Bunn 2020-2021
Legislated
Create, prepare, approve and publish meeting agenda packages and
Services
minutes in a more efficient, collaborative, streamlined manner.
7
2 - 47
Financial Services Project Timeline to
Manager Complete
BP08 2020-2021
Mobile Time Entry Jason Winter
Implement mobile time entry for operations, eliminating the need for Asset
paper-based timesheets. Management &
Business
Solutions
BP09 2020-2021
Development Charge (DC) & Community Benefits Charge (CBC) Studies Ryan Hagey
development charges study and investigate whether the Financial
City should prepare a community benefits charge study. Planning
BP10 2020-2021
Long Term Financial Plan Implementation Ryan Hagey
Implement/consider recommended actions identified as 2020 items in the Financial
Long-Term Financial Plan. Planning
BP11 2020-2021
Point of Sale and Expansion of Payment Options Saleh Saleh
Replace the existing Point of Sale system, which is past its life cycle, and Revenue
expand payment options for various services.
Infrastructure Services Project Timeline to
Manager Complete
BP12 Facilities Infrastructure Program Beatrice Powell 2020-2022
Conduct a comprehensive review of facility infrastructure needs that will Facilities
incorporate building condition assessments, sustainability opportunities, Management
and accessibility needs to identify current gaps and inform long-term
maintenance and capital improvement strategies to address the
infrastructure deficit.
BP13 Rehabilitation of City Hall Outdoor Spaces Construction Phase 1 Lynda Stewart 2020-2021
Complete construction associated with the rehabilitation of City Hall Facilities
Outdoor spaces, focusing on Carl Zehr Square and College Street. Management
BP14 Implementation of Significant Parks Projects Niall Lobley 2020-2021
Complete Phase 2 design work for RBJ Schlegel Park; plan, design and
Parks &
construct the Survivor Garden; and undertake design and tender
Cemeteries
preparation for Westwood Park.
BP15 Implementation of the Federal Disaster Mitigation and Adaptation Fund Nick Gollan 2020 -2028
(DMAF)
Sanitary &
Plan and execute stormwater management infrastructure projects across Stormwater
the city to leverage the DMAF grant funding and advance the Utilities
implementation of the 2016 Integrated Stormwater Management Master
Plan.
8
2 - 48