HomeMy WebLinkAboutCAO-2021-2 - 2021 Business Plan April Progress Report REPORT TO: Finance and Corporate Services Committee DATE OF MEETING: April 19, 2021 SUBMITTED BY: Karen Cooper, Manager, Strategic and Business Planning, 519-741-2200 ext. 7817 PREPARED BY: Lauren Burr, Corporate Planning Analyst, 519-741-2200 ext. 7059 WARD(S) INVOLVED: All Ward(s) DATE OF REPORT: April 8, 2021 REPORT NO.: CAO-2021-2 SUBJECT: 2021 Business Plan - April Progress Report RECOMMENDATION: For information REPORT HIGHLIGHTS: This report presents the 2021 Business Plan April Progress Report (Appendix A). The 2021 Business Plan comprises 40 strategic and business plan projects, with 24 to be completed this year. Progress has been made on 28 projects in the first quarter of 2021. The 3 projects completed as of April 30, 2021 include the Online Customer Service Portal Development, Transformation and Relaunch of Kitchener.ca, and Electronic Agenda Management. and vibrant Kitchener. BACKGROUND: As the World Health Organization declared COVID-19 a global pandemic on March 11, 2020, the lives of Kitchener residents and citizens throughout Waterloo Region and around the world dramatically changed. Over the past year, the City placed the safety of citizens and staff as a top priority throughout its pandemic response and recovery efforts, while also supporting the economic sustainability of businesses and employers in the municipality. To achieve these priorities, staff took complementary and innovative approaches to modernize service delivery and improve efficiencies. This included enabling staff to work from home, providing more services online, offering existing programs in new virtual formats, providing training and supports to local businesses and establishing centralized service counters at city hall. While some of the service delivery changes are only temporary to address the pandemic restrictions, many will remain post-pandemic and provide long- term benefits. *** This information is available in accessible formats upon request. *** Please call 519-741-2345 or TTY 1-866-969-9994 for assistance. REPORT: 2021 Business Plan - Overall Status In the context of the continuing pandemic, the 2021 Business Plan comprises 40 strategic and business plan projects, with 24 to be completed this year. Three projects have been completed in the first quarter of 2021. As of April 30, 2021, 25 projects are on track to meet their end dates as scheduled in the 2021 Business Plan. 5 projects are delayed, and 7 projects have not started yet. While this would be a commendable start to any year, the progress made in the first quarter of 2021 is especially noteworthy after a year of living with COVID-19. Figure 1: Status of the 2021 Business Plan as of April 30, 2021 Completed On Track Delayed / Not Started Ќ ƦƩƚƆĻĭƷƭ ЋЎ ƦƩƚƆĻĭƷƭЊЋ ƦƩƚƆĻĭƷƭ ΛБіΜ ΛЏЋіΜ ΛЌЉіΜ Figure 2: Status of Projects Scheduled for Completion in 2021 as of April 30, 2021 Completed On Track Delayed / Not Started Ќ ƦƩƚƆĻĭƷƭ ЊЍ ƦƩƚƆĻĭƷƭА ƦƩƚƆĻĭƷƭ ΛЊЌіΜ ΛЎБіΜ ΛЋВіΜ Strategic Plan Projects Overall Status of Strategic Plan Actions 2021 Completed Projects: Online Customer Service Portal Development On March 1, 2021, the City of Kitchener unveiled its new corporate website along with a leading-edge customer service portal called MyKitchener. Citizen input was the driving force and guiding principle in developing the new online experience. The portal offers a personalized user experience through a secure login. With its ability to create a customized d individual interests, My Kitchener is the first city portal of its kind in North America. With a MyKitchener account, users can: Customize their dashboard with content that is relevant to them View information about multiple properties in one place Receive notifications when new information is available like new skating and swimming events, road closures and school bus delays View and pay property tax and utility bills View news and upcoming events Watch council meetings and download meeting minutes and agendas On Track Projects 18 strategic plan projects are on track for completion by their scheduled end dates, including: 2021 Scheduled End Date Projects Pedestrian-First Street Plan for Gaukel Street Community Climate Action Plan Tree Canopy Target Incubator, Accelerator and Co-Working Space Network City-Owned Property Review Equity, Diversity and Inclusion Strategy Mill Courtland Community Centre Expansion Business Case Multi-Language Interpretation Support Customer Satisfaction Program 2022 Scheduled End Date Projects Bikeshare Program Connectivity and Year-Round Maintenance of Multi-Use Trails and Pathways Pedestrian-First Street Plan for Kitchener Market Leverage the Energy Efficiency Reserve Fund Tree Planting Elimination Backlog Huron Brigadoon Area School / Community Centre Construction Open Space Strategy Arts and Culture Plan 2023 Scheduled End Date Projects Protected Cycling Network Connected to the Downtown Delayed Projects Two strategic plan projects are delayed. The New Rosenberg Community Centre/School Business Case is now planned to start in 2023. Work on the Waste Diversion Strategy: Increase Waste Diversion in Our Public Spaces and Events commenced in 2019 but is postponed due to the continuing pandemic. Projects to Start Five strategic plan projects are due to start in 2021: City-Owned Property Brought to Market Innovation District (Bramm Yards) Master Plan Civic District Master Plan Set and Communicate Service Levels Customer Experience Program Status of the Business Plan Projects Completed Projects The following two business plan projects were completed in the first quarter of 2021: Transformation and Relaunch of Kitchener.ca On March 1, 2021, Kitchener launched its comprehensive new online experience for residents, including a completely transformed website and new customer service portal called MyKitchener. The integration between the new website, portal and services reimagines how municipalities offer services online. Staff redeveloped the online presence from the ground up, incorporating best-in-class web design practices to give Kitchener residents easy access to the information they are looking for. The new website is more accessible and easier to understand because it uses language at a Grade 7 reading level. Electronic Agenda Management -wide, fully automated application for submitting agenda items and managing meetings for Council, Standing Committees, and quasi-judicial committee meetings, such as the Committee of Adjustment. Through engagement in 2019, stakeholders identified opportunities to improve the report development and submission process. Agenda.NET creates a number of enhancements and efficiencies, including automatically assigning report numbers, document versioning, cross- departmental collaboration, and automated approval workflows. On Track Projects 7 business plan projects are on track for their scheduled end date in the 2021 Business Plan, including: Budd Park Strategy (2021) Cameron Heights Pool Feasibility Study (2021) Southwest District Pool Business Case (2021) Mobile Time Entry (2021) Rehabilitation of City Hall Outdoor Spaces Construction Phase 1 (2021) Facilities Infrastructure Program (2022) Implementation of Federal Disaster Mitigation & Adaptation Fund (2028) Delayed Projects 5 business plan projects are delayed with completion now planned for 2022 as follows: Ice Demand Study Development Charge (DC) and Community Benefits Charge (CBC) Studies Long Term Financial Plan Implementation Point of Sale and Expansion of Payment Options Implementation of Significant Parks Projects STRATEGIC PLAN ALIGNMENT: innovative, caring and vibrant Kitchener. FINANCIAL IMPLICATIONS: None COMMUNITY ENGAGEMENT: INFORM This report has council / committee meeting. CONSULT In 2018, Compass Kitchener consulted the public on developing community priorities for the 2019-2022 Strategic Plan, which informed preparation of the 2021 Business Plan project list. PREVIOUS REPORTS/AUTHORITIES: CAO-20-008 2020 Business Plan Year-End Progress Report and Recommended 2021 Business Plan Project List APPROVED BY: Dan Chapman, Chief Administrative Officer ATTACHMENTS: Appendix A: 2021 Business Plan Progress Report April 30, 2021 1 334778892 10101315182225252626272729 . .... ...... .............................. ................. ................ ................... .................. ..................... .................... ......................... ........................ ................................................................................ ............................ ............................. ................................................................ ................................ ................................................................ ................................ ................................................................ ................................ ................................ ................................ ................................ ................................ ................................ ................................ ................................ ................................................................................................ ................................ ................................ ................................................................ ................................ ................................................................ ................................ ................................................................ ................................ ................................ ................................ ................................ ................................ ................................ ................................ ................................ ................................................................................................ ................................ ................................ ................................................................ ................................ ................................................................ ................................ ................................................................ ................................ ................................ ................................ ................................ ................................ ................................ ................................ ................................ ................................................................................................ ................................ ................................ ................................................................ ................................ ................................................................ ................................ ................................................................ ................................ ................................ ................................ ................................ ................................ ................................ ................................ ................................ ................................................................................................ ................................ ................................ ................................................................ ................................ ................................................................ ................................ ................................ ................................ ................................ ................................ ................................ ................................ ................................ rategic Plan Actions................................................................ ................................ 19: One Year Later ................................ - Transportation ................................................................ Friendly - ................................ ................................ Impact of COVIDOverall Status of StStrategic Plan Completions and AchievementsPeopleEnvironmental LeadershipVibrant EconomyCaring CommunityGreat Customer ServiceBusiness Plan Project CompletionsCommunity ServicesCorporate ServicesFinancial ServicesInfrastructure Services 2022 Strategic Plan Evaluation Criteria2022 Strategic Plan Actions -- Contents IntroductionOverall Status of the 2021 Business Plan Projects2019Strategic Plan2019Business Plan ProjectsBusiness Plan Projects 3 d an To nly staff s made include how is described of This g training and t the year. , with 10 projects project This report contains as a top priority through Each efficiencies. staff and improve n the Strategic Plan. term benefits. - business plan projects. lan and other key priorities. These projects form outlined i p 14 Council and the community can be proud strategic and business plan projects trategic egion and around the world changed as the World Health s 19. R - placed the safety of citizens modernize service delivery and has to he City pandemic and provide long While this would be a commendable start to any year, the progres - . the economic sustainability of businesses and employers in the municipality. . 2022 Strategic Plan, as well as ing - Over the past year, t and April 30, 2021 mentary and innovative approaches le all 25 actions from the 2019 19 a global pandemic. - recovery efforts, while also support lan, which is developed alongside the budget to ensure resources are aligned to complete the work. including anticipated timing for completion. Regular progress is reported to Council and the public throughou City Council approves a list of projects that implement the current p: One Year Later 19 - allenging time, staff demonstrated resiliency and made progress on local businesses and establishing centralized service counters at city hall. While some of the service delivery changes are o usiness in 2020, and 3 more completed in the first quarter of 2021 b Business Plan includes 1 business plan, March 11, 2020, the lives of Kitchener residents and citizens throughout Waterloo Introduction Each year, Kitchener the annualin the The 202update on progress made between January 1 Impact of COVID OnOrganization declared COVIDits pandemic response andachieve these priorities, staff took compenabling staff to work from home, providing more services online, offering existing programs in new virtual formats, providinsupports to temporary to address the pandemic restrictions, many will remain postThrough this chcompletedin the first quarter of 2021 is especially noteworthy after a year of living with COVIDadapted to the challenges of the pandemic and continued to deliver on the community priorities 4 projects (10%) are delayed, and 5 . Not Started end dates (30%) (29%) 7 projects 12 projects are expected to be completed in 2022, 2 in 2023 and planned 3 1 Delayed or Delayed or Not Started . their this year . (62%) (58%) Projects 21 - On TrackOn Track 25 projects14 projects 10 to be completed %) are on track to meet 62 pages projects 4 ness Plan projects ( as of April 30, 2021 i 5 2 , with 2 Bus 1 (8%) (13%) projects . 3 projects3 projects 40 CompletedCompleted Business Plan 1 started yet have been completed. comprises of the 202of Projects Scheduled for Completion in 2021 as of April 30, 2021 projects and their status is included on have not projects 3 , Status of the 202 StatusStatus (20%) Business Plan : 1:2 1 scription of April 30 de projects Overall The 2021 in 2028. As of 7The FigureFigure 5 ment Transformation and Relaunch of Kitchener.caElectronic Agenda Manage business plan projects 2 1 Construction Phase (2021) : Disaster Mitigation & Adaptation Fund include projects Online Customer Service Portal Development completed Budd Park Strategy (2021)Cameron Heights Pool Feasibility Study (2021)Southwest District Pool Business CaseMobile Time Entry (2021)Rehabilitation of City Hall Outdoor Spaces (2021)Facilities Infrastructure Program (2022)Implementation of Federal (2028) rack 3 T strategic plan project 7 business plan projects 1 Complete The On 25 projects are on track for their scheduled end date in the 2021 Business Plan, including: 6 Implementation on of Payment Options Ice Demand StudyDevelopment Charge (DC) and Community Benefits Charge (CBC) StudiesLong Term Financial Plan Point of Sale and ExpansiImplementation of Significant Parks Projects business plan projects are delayed into 2022, including: 5 (2023) : , including: scheduled to 2022) re (postponed, Community Centre/School Business Case Communicate Service Levels Owned Property Brought to Market - plan projects will begin in 2021 CityInnovation District (Bramm Yards) Master PlanCivic District Master PlanSet and Customer Experience Program Waste Diversion Strategy: Increase Waste Diversion in Our Public Spaces and EventsNew Rosenberg strategic 2 Strategic Plan projects are delayed, including To Start 5 Delayed 7 Plan. , staff Citizen 0 he Strategic As of April 30, 2021, the fall of 202 In . provide a roadmap for the s adopted the 2030 Agenda e implementation of the SDGs will ject he public through an online inning in 2021. 004. - 20 - serve as a model regionally, nationally, and globally. will nequality, confront injustice and tackle climate change by 2030. and Appendix B of report CAO p the SDGs for the Kitchener context. This pro 2022 strategic plan connect to at least one of the SDGs - ing 2022 Strategic Plan: - and adapt ment Goals ing localiz within the strategic planning process c benchmarks and measure progress towards achieving the SDGs within current and future strategic plans. provides advice to Council on 2022 Strategic Plan can be found in - completed (28%). als , begin work on of the 25 action statements within the 2019 Each Green Beacon , Citizen Advisory Committee identifies community priorities for action, and monitors progress toward achieving the community vision and in implementing t er has 4 levels of evaluation criteria/measures for the 2019 2022 Strategic Plan Evaluation Criteria - Overall Implementation of the Strategic PlanOverall Implementation of the Sustainable Development Goals (SDGs) through the Strategic PlanImplementation of Strategic Plan GoImplementation of Strategic Plan Actions Compass Kitchener to fully integrate, implement, and operationalize SDGs 2019 The Compass KitchenerCompass KitchenOne evaluation metric has been proposed for each of the 25 Strategic Plan actions. These metrics will be tracked by staff beg7 out of the 25 strategic plan actions have been At the United Nations (UN) Sustainable Development Summit in September 2015, world leaders from Canada and other member stateThe City of Kitchener is committed to working with the Government of Canada in embracing the 2030 Agenda and to supporting thin Canada and internationally.worked with local consultantCity This localized project has enabled the City to set specifiOnce the localized SDG targets and indicators are finalized and benchmark data has been collected, they will be shared with tDashboard. 8 Strategic Plan Overall Status of Strategic Plan Actions 9 Citizen the new strategic plan project and school bus ity portal of its kind developing c itchener account users can customize their , with additional rollout to follow by summer. DI strategy by end of June 2021. customer service portal, called MyKitchener. services edge - begin in 2021. With a MyK The portal offers a personalized user experience through a . the five goals of the Strategic Plan. The following leading its ith work to each of On March 1, 2021, the City of Kitchener unveiled its new corporate website along with input was the driving force and guiding principle behind online experience. address and individual interests, My Kitchener is the first in North Americadashboard with content that is relevant to them; view information about multiple properties in one place; receive notifications when new information is available like new skating and swimming events, road closuresdelays; view and pay property tax and utility bills; view news and upcoming events; watch a council meeting and download meeting minutes and agendas, and so much more. being prepared for public input. is projects under committed : Language Interpretation Support with key frontline - : s progress in include construction of the Protected Cycling Network, w considerable progress in the first quarter of 2021 in implementation of Multi Completions and Achievements is making Online Customer Service Portal Development A tender posted for A complete draft of the Community Climate Action Plan Starting Data set on tree canopy completed 1. as Strategic Plan The City w Other strategic plan 10 . here ooters as part sc - Update bikes and e - Progress wide bikeshare feasibility study - . a wider range of transportation Completed in 2019.Read Complete Streets Kitchener A regionwas approved that recommends a collaborative approach to a bikeshare program throughout the region. A regionwide project team is investigating the use of eof the future program and note that traditional private bikeshare providers have changed their business model to reflect options 2022 - to 2019 Timeline Complete Completedin 2020 Cronkite Project Manager Barry Cronkite Transportation Services Barry Transportation Services ch bicycles Project ikeshare service in whi b Actions hare Program made available for shared use to the public Complete Streets‘ƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЊВ͵Bikes Implement aare a feasibility study to determine the most appropriate system. Transform how people move through the city by making the transportation network safe, convenient, comfortable and connected. y 2021. Statement 2022 Strategic Plan - GOAL: Friendly Transportation - Strategic Plan Action Develop a set of Complete Encourage and incentivize 1.1 Streets (safe and comfortable) guidelines and an associated evaluation scorecard by 2020 to apply to roadway construction projects.1.2 alternative modes of transportation by developing and subsidizing a bikeshare program b 2019 People 11 Valley Update Progress . A tender has posted for construction, which will begin in spring 2021.Completed in 2020.Read the Cycling and Trails Master Plan hereTrail improvements are being planned on several community trails and bridges including: Traynor to Wilson, Kingsway to Vanier, sections of the Laurentian Trail, bridges in Vanier, Rothsay, Lynn and Victoria Park. 3 2022022 -- to 2020 Timeline Complete 2020 Completedin 2020 Project Christensen Manager Darren Kropf Transportation Services Liz Christensen Transportation Services Liz Parks & Open Space Design & Development with , round - athways and the Round , in one - Connected to the cent neighbourhoods Trails and P 3 km of existing trails . se round access to a U - use trails and pathways - - Project connectivity and year wayfinding. road cycling facilities, as well as - town by 2022 Use Trails and Pathways Master Plan - the 2010 Cycling Master Plan e actions, Cycling and Trails Master Plan UpdateConnectivity and Year road trails infrastructure nclude on - i Protected Cycling NetworkDowntown Install a continuous and protected cycling network that connects adjato the down 1.4.1 Update2012 Multito offcomprehensive plan that also addresses education and 1.4.2 Maintenance of Multi Prioritizmaintenance to multithrough the Cycling and Trails Master Planan initial target of yearminimum of an additional by 2022. . . cent round access - Statement use trails and pathways town by 2022 - round maintenance to -minimum of an additional Strategic Plan Action Install a continuous and Improve connectivity and 1.3 protected cycling network that connects adjaneighbourhoods to the down 1.4 yearmultias prioritized through the Cycling and Trails Master Planwith an initial target of providing yearto a 3 km of existing trails by 2022 12 Update interventions. Progress cost street - pace in late spring 2021, subject to Gaukel Street was closed to traffic during the pandemic and will continue to remain closed as a passive pedestrian space. The block between King St and Charles St will be turned into passive sdevelopment construction completing, and additional formal seating will be added to the Joseph St/Charles St block in summer 2021.A project charter has been approved. Staff is investigating programming and low 20212022 -- to Timeline Complete 20202021 Project Manager Darren Kropf Transportation Services Darren Kropf Transportation Services . destrians over et Plan for Gaukel et Plan for Kitchener Gaukel Street. Project First StreFirst Stre -- PedestrianPedestrian 1.5.1 Street Develop plans to prioritize pedestrians over other travel modes on 1.5.2 Market Develop plans to prioritize peother travel modes between the Kitchener Market ION station and Kitchener Market first streets - Statement Strategic Plan Action Develop a plan to create 1.5 pedestrianbetween Victoria Park and City Hall and between the ION and Kitchener Market by 2022. 13 . here sources. 2021. - h projects are underway. capital energy reserve project Progress Update 19 safety concerns the project was - Project completed in 2019. Read the Corporate Climate Action Plan Originally the 2020 was to retrofit the remaining administrative office lighting at the Kitchener Operations Facility (KOF). Due to COVIDswitched to outfitting Civic District Garage and KOF Shops & Stores. BotThe KOF administrative lighting project is on hold and will be reassessed in 2021 if it or another project with similar payback will take its place.A draft of the Community Climate Action Plan is complete and is being prepared for final public input. The community climate action plan will be presented to Council by mid 20222021 -- 2019 Complete Timeline to Completed in 20202020 --- Project Manager Claire Bennett AdministrationDevelopment Services Claire Bennett AdministrationDevelopment Services Claire Bennett AdministrationDevelopment Services Reporting Project nually on greenhouse gas emission ommunity Climate Action Plan Corporate Climate Action Plan‘ƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЊВ͵anreduction will continue until 2026.Leverage the Energy Efficiency Reserve Fund Leverage the fund to undertake energy efficiency retrofit projects on City of Kitchener assets and capture and reinvest the operating savings to pay for capital costs.C Complete the 80x50 Community Climate Action Plan. . ciency Reserve i Statement ergy Eff arting in 2019, leverage Achieve a healthy and livable community by proactively mitigating and adapting to climate change and by conserving natural re . Launch and implement a StDevelop a Community Strategic Plan Action 2.1 Corporate Climate Action Plan by 2019 to achieve an absolute greenhouse gas emission reduction of at least 8% by 2026.2.2 the EnFund and other resources to reduce consumption and emission at our facilities and in our operations 2.3 Climate Action Plan with partner organizations by 2020 Environmental Leadership Goal: 14 learning or with visual Community and Council Progress Update emic, large public events were The final tree canopy dataset has been received from the consultant.engagement regarding Kitchener's tree canopy and the setting of a tree canopy target will occur in the spring/early summer of 2021, followed by Council consideration of a tree canopy target.Approximately 630 trees will be planted in 2021. All suitable tree replacement locations identified as of December 31, 2018 will have been planted by the end of 2021, eliminating the 2018 tree planting backlog.Due to the pandcancelled, and this project is postponed until events restart. Recycling and organics diversion has also increased across public facilities and spaces, including a pilot project to improve waste station wayfinding for people impairments as well as English as a second language (ESL) visitors. 22 2021202220 --- Complete Timeline to 202020202020 - Project Manager Dave Schmitt Forestry & Natural Areas Management Adam Buitendyk Forestry & Natural Areas Management Claire Bennett AdministrationDevelopment Services acklog B Project vailability, quality of lanting P run events with large - ion Tree Canopy TargetTree iminat 2.4.1 Review the current canopy cover and set an achievable target based on best practices as well as constraints such as land asoil, etc. in order to guide ongoing and future investment in tree planting, protection and maintenance.2.4.2 El Plant at least 750 trees in 2020, with the goal of reaching 2,500 trees and eliminating the current backlog by the end of 2022.Waste Diversion Strategy: Increase Waste Diversion in Our Public Spaces and Events Expand the Waste Diversion Station to all Cityvolunteer involvement, and evaluate expanded waste diversion stations at events, parks and public facilities. nd events by Statement . . Implement the Reduce waste diverted to Strategic Plan Action 2.4 Sustainable Urban Forest Strategy with a focus on establishing a tree canopy target by 2020 and eliminating the current (2018) tree planting backlog by 2022 2.5 landfills by implementing new diversion programs at our facilities a2021 15 here. and great places . here Progress Update 2019.2019. in in about this project Completed Read the Urban Design Manual Completed Learn 20192019 Complete Timeline to Completed in Completed in Project Manager Dayna Edwards Planning Cory Bluhm Economic Development Project Buildout of 44 Gaukel Urban Design Manual‘ƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЊВ͵3.2.1 ‘ƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЊВ͵ - wide - tech industries. - working spaces by completing Build a vibrant city by making strategic investments to support job creation, economic prosperity, thriving arts and culture, - h/med Complete a new Urban Design Foster the creation of a city Strategic Plan Action Statement 3.1 Manual by 2019 that expresses city building and design expectations to ensure vibrant new development throughout Kitchener.3.2 network of incubators, accelerators and cothe buildout of 44 Gaukel in 2019, advancing work on a Creative Hub and undertaking business cases in 20192021 for the food manufacturing and healt Vibrant Economy GOAL:to live. 16 . here is in late A Because of the to Council owned space and with - ke It Kitchener, components of Progress Update . Due to the pandemic, finalization of the omprehensive review and completion Staff is investigating opportunities for incubators within Citypotential partners. Business cases will be prepared and presented 2021. Completed in 2020.Read the Make It Kitchener 2.0 Strategy Initial focus has been on supportive housingsitesreview is delayed until 2021.pandemic and urgent need around affordable housing and Mathe review commenced in 2020.canticipated in 2021. 2021 - 1 2020 Complete Timeline to 2020 Completed in 202 msky & u Project Manager Cory Bluhm Economic Development Lauren Chlumsky Economic Development Lauren ChlRob Morgan Economic Development tech - eview to ensure the Accelerator and ives. Project comprehensive review ubators. owned properties by 2020 to - Owned Property R - Working Space Network - 3.2.2 Incubator, Co Lease all spaces in the Creative Hub, explore the potential to facilitate a Food Incubator with a business case pending, and explore partnerships for the development of manufacturing and health/medindustry inc Make It Kitchener 2.0 Strategy Develop the Make it Kitchener 2.0 Strategy by 2020 with a focus on transformative actionsattraction, success and retention of diverse businesses, talent, and arts/culture across the city.City Complete aof citydetermine how they could be effectively used to advance city strategic object owned properties by 2020 to - Develop the Make it Kitchener 2.0 Complete a comprehensive review Strategic Plan Action Statement 3.3 Strategy by 2020 with a focus on transformative actions to ensure the attraction, success and retention of diverse businesses, talent, and arts/culture across the city.3.4 of citydetermine how they could be effectively used to advance city strategic objectives. 17 working with University of Progress Update ght to market in late 2021 after This will occur once the City owned property review has been completed by September 2021. It is expected that the first property will be broucomprehensive community engagement.The current focus is Waterloo to build out the Health Innovation Arena on the Health Sciences Campus. Work on the Master Plan will commence in late 2021.Preliminary project planning has started. A visioning exercise will be completed before the Master Plan commences. 1 20232022022 --- 10 Complete Timeline to 2022022021 Bluhm Project Manager Brian Bennett Economic Development Cory Bluhm Economic Development Cory Economic Development th at least one new Project Owned Property Brought - Innovation District (Bramm Civic District Master Plan arket owned property brought to - 3.5.1 Cityto M Develop a vision for downtown Kitchener and continue to position downtown Kitchener as a leading destination for redevelopment opportunities, wicitymarket by 2020.3.5.2 Yards) Master Plan Finalize the Innovation District (Bramm Yards) Master Plan by 2022.3.5.3 Finalize the Civic District Master Plan by 2022. s) owned property brought to Develop a vision for downtown - Strategic Plan Action Statement 3.5 Kitchener and continue to position downtown Kitchener as a leading destination for redevelopment opportunities, with at least one new citymarket by 2020. Finalize the Innovation District (Bramm YardMaster Plan by 2021 and the Civic District Master Plan by 2022. 18 - - & here task force ty, Anti by the end income youth informed - - working groups will be to complete work the Progress Update entorship program for low ommunity grant for racialized groups Policy Training Demographic Data CollectionHiring & Recruitment Communications CM The Mayor's Task Force on Equity, Diversity & Inclusion is on track of June 2021. There are currently seven working groups developing equitystrategies and recommendations in the following areas: The deliverables of compiled into a comprehensive Equity & AntiRacism Strategy for the City of Kitchener, to be implemented by the newly formed EquiRacism & Indigenous Initiatives staff team.Completed in 2020. 2021 - to 2020 Timeline Complete 2020 Completed in - Project Manager ervices Elin Moorlag Silk AdministrationCommunity S Andrew Ramsaroop Planning f o . focused on better nity groups and the and Inclusion able Housing Project industry represented people, as - Strategy reate an Equity, Diversity and Equity, DiversityStrategy CInclusion engaging and serving marginalized and underwell as creating a more inclusive City workplace.Affordable Housing Strategy Create an AffordStrategy for Kitchener by 2020 in collaboration with the Region Waterloo, commudevelopment . . nclusion I industry f Waterloo, o Statement nity groups and the Diversity and , Strategic Plan Action Create a comprehensive Create an Affordable Caring Community 4.1 EquityStrategy by 2020 to combat systemic barriers to full economic and social participation in the city 4.2 Housing Strategy for Kitchener by 2020 in collaboration with the Region commudevelopment 4. GOAL:supporting our diverse populations & helping to make housing affordable. 19 to of 2021. 2 Q . in here Progress Update 2019. in nticipate starting A stigma training will now become a core - Completed in 2020.Antilearning program with ongoing evaluation and customization as required to meet the diversity of staff needs throughout the organization andensure the content is relevant to evolving community needs. Completed Learn about this project Staff resource supporting this project has been redeployed to run summer programs and services. 2021 - to 20202019 Timeline Complete Completed in Completed in 2020 Project Manager Paula Dunn Human Resources Mark Hildebrand Neighbourhood Programs & Services tigma through S aphics. Business Case Project ocial S needs assessment and Courtland Community raining Reduce Support for Safe Consumption Mill T taff 4.3.1 S Provide staff with the resources torespond effectively to changing community demogr 4.3.2 and Treatment Facilities‘ƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЊВ͵4.4.1 Centre Expansion Complete a business case to determine the requirements for an addition to the Mill Courtland Community Centre. resources across Statement . and support the and an Open Space ers, Strategic Plan Action Reduce social stigmas Better utilize existing 4.3 experienced by those living with mental illness and addiction in our community through staff training and supporting the creation of appropriate safe consumption and treatment facilities in Kitchener 4.4 facilities, provide relevant programming at community centequitable distribution of leisureprograms and neighbourhoods. Start work on the Mill Courtland Community Centre expansion by 2020 and the Rosenberg Community Centre by 2021. Complete the Huron Brigadoon Community CentreStrategy by 2021. 20 . roject has been sent Progress Update awaiting final costing and approvals - have been approved. P . Project pushed out to 2023 to 2026 by the school boardDetailed design has been completed. Building permits have been approved. Application to the Province for approval of design and budget submitted by Waterloo Region District School Boardto tender Project initiation is ongoing with project manager identified, scope and charter being developed. 2 2022022 -- to 23 Timeline Complete 2021 New date: 20 2020 2020 Lobley Project Manager Mark Hildebrand Neighbourhood Programs & Services Mark Hildebrand Neighbourhood Programs & Services Niall Parks & Cemeteries / assessment and Business Case Project New Rosenberg Community Huron Brigadoon Area School Open Space Strategy 4.4.2 Centre/School With the Catholic School board, complete a needs business case to determine the requirements for a joint community centre/school in the Rosenberg area.4.4.3 Community Centre Construction Construct a joint school/community centre in the Huron Brigadoon area, in partnership with the Waterloo Region District School Board.4.4.4 Develop an open space strategy to explore the value of open spaces, how they function, are planned, maintained, and managed, and including a review of permitted uses in parks. Statement Strategic Plan Action 21 terloo for ime to commence Progress Update on these initiatives in underway. pandemic, and therefore engagement has - The City developed a partnership with the Region of Waterloo and the City of Wastakeholder consultation, research and analysis. A Terms of Reference and plan for stakeholder consultation are under development. Consultation was anticipated for late 2020, however this has been postponed until later in 2021. The appropriate tcommunity engagement for the Culture Plan is postbeen postponed. Support for professional artists and cultural organizations will be considered as part of the COVID recovery plan. Specific engagement 2 202 - to Timeline Complete 2020 Project Manager Emily Robson Economic Development cultural - Project by engaging a broad section of the community - Arts and Culture Plan Develop a new and inclusive Arts and Culture Plan crossincluding the arts and creative industry sector and multicommunities. - - Statement Strategic Plan Action Engage a broad cross 4.5 section of the community including the arts and creative industry sector and multicultural communities to develop an inclusive arts and culture Plan by 2021. 22 open. - re based feedback collection - nal service channels will be mail Progress Update call surveys at our contact centres, as well - Contract for service has been finalized with the vendor. Work with community centres to determine top languages (by neighbourhood) to advertise the new service is complete. A more limited implementation of this service, with key frontline users including Bylaw, Revenue, Corporate Contact Centre and Community Centres, is scheduled to be complete by the end of the April with additional roll out to more staff to follow by summer.Postas online and ebegan in late 2020 for City Hall appointment and Book Your Bubble bookings, and overnight parking exemptions. The program has expanded to include the new MyKitchener portal and website beta launch feedback collection. Additioincorporated into the program as they 20212021 -- Complete Timeline to 20202020 Project Manager Jana Miller Corporate Customer Service Christine Baker Corporate Customer Service ience - wide - demand multi - person inquiries to Project - 7 on - 24 time feedback, monitoring - and engagement with the city by providing friendly, easy and convenient services. an organization Language Interpretation Support - stomer Satisfaction Program that ulti M Implement a language interpretation support for telephone and inenable staff in all facilities to ensure a more consistent and equitable experfor all customers.Customer Satisfaction Program Implement Cuenables realand reporting of satisfaction data to drive service improvements. wide - collection demand - Statement . Strategic Plan Action Provide onIntroduce a corporate 5.1 customer service support in many languages through the Corporate Contact Centre by 2020 5.2 Customer Satisfaction Program that will allow for the of real time feedback from customers accessing city facilities, programs, and services by 2020. Great Customer Service GOAL: 23 rtal: k and portal . Progress Update MyKitchener customer service Completed in 2021.The launched in beta (an almost finished version the public can provide feedback on) to the public on March 1, 2021. The public is testing the functionality of the portal during the beta test and staff are monitoring feedbacmaking improvements based on what we learn. Later in 2021, the project team will regroup to review the scope of Phase 2 of the portal's development, which will include additional new functionality for residents.See the new website and access the powww.kitchener.ca Project to start in late 2021 2022 - Complete Timeline to Completed in 2021 2021 Project Manager Jana Miller Corporate Customer Service Jana Miller Corporate Customer Service services - nd grass e Portal Project ugh a personalized, single a centralized online service portal on account. - aunch Online Customer ServicDevelopment Lwhere citizens can access their ein one place throsign Set and Communicate Service Levels Set clearly communicated and specific service levels for frequently asked about or accessed City services, including: tree maintenance, parking, property standards complaints, snow clearing acutting by 2022. ng and . by 2022 Statement and allowing financial , Strategic Plan Action Enhance customer Set clearly communicated 5.3 experience online by delivering customized information, providing easy access to servicestransactions by 2021.5.4 and specific service levels for frequently asked about or accessed City services, including: tree maintenance, parking, property standards complaints, snow clearigrass cutting 24 . Progress Update Project to start in 2021 2022 - Complete Timeline to 2021 ce Project Manager Jana Miller Corporate Customer Servi Project Customer Experience Program Implement a comprehensive CustomerExperience Review Program to help ensure services are easy and convenient by 2022. Statement Strategic Plan Action Implement a 5.5 comprehensive Customer Experience Review Program to help ensure services are easy and convenient to access from the 2022. 25 ner new website, Council, Standing the its comprehensive new ed wide, fully automated application MyKitchener portal will empower - edge online customer service portal - eedback made it clear that the City is judicial committee meetings, such as the - reimagines how municipalities offer services online. class web design practices to give Kitchener residents - the City of Kitchener launch in - departmental collaboration, and automated approval - serve on their schedule. - ss On March 1, 2021, online experience for Kitchener residents, including a completely transformed website and new, cuttingcalled MyKitchener. The seamless integration between portal and City servicesThe City has redeveloped its online presence from the ground up, incorporating bestexperience includes a new website with plain language content. By lowering the reading level of the website from college to grade seven, the City is making their website more accessible and easier to understand. The City hopes that the new website and residents to self for submitting agenda items and managing meetings for Committees, and quasiCommittee of Adjustment. Through engagement across the City in 2019, stakeholders identified opportunities to improve our report development and submission process. Valuable fready for an enhanced and efficient report writing and meeting management software solution. Agenda.NET creates enhancements and efficiencies, including automatically assigning report numbers, document versioning, croworkflows. For report writers and approvers, it is time to make creating and submitting items to Council and Committee meetings easy! s Transformation and Relaunch of Kitchener.caElectronic Agenda Management 1.2. Business Plan Project Business Plan Project Completions 26 term impacts of - g own. n p the terms of reference for o School Board contacted by the pandemic on ice users is unk Progress Update A condition report has been completed for the facilities on the site. The work to evaluate the benefits of the Budd Lands for employment and for recreation is underway.Waterloo Region District end of March 2021 to confirm support to release the Terms of reference for consultant services.Planning is underway to develthe pool business case.Work was paused to avoid putting additional pressures on the user groups during the pandemic. Speculation on future ice demands is challenging when the lonthe to 2021202120212021 ---- 0 22 TimelineComplete 202202020202020 New date: 20 Project Manager Kim Kugler Sport Kim Kugler Sport Kim Kugler Sport Jeremy Dueck Sport e ermine the elements Feasibility Study Waterloo Region District School Pool Business Cas timing of a new arena. Community ServicesBudd Park Strategy Identify potential sites and estimated costs to relocate the recreational assets at Budd Park and compare the costs to the economic benefits of using the Budd Park for employment lands.Cameron Heights Pool Collaborate with the Board to determine the renovations and estimated costs to isolate the pool operation from the school operation to preserve a recreational asset in the downtown.Southwest District Engage community residents/stakeholders in a needs assessment and business case to detto be included in the new pool.Ice Demand Study Evaluate ice user needs and trends for ice time to determine the 1234 BP0BP0BP0BP0 Business Plan Projects 27 taff , s for council and members of the launch rollout will continue within the - governance, training, documenting ated rules are being considered and built into the . Post launch administrative work will be ongoing - rel - Progress Update The website and portal launched March 1, 2021. Postincludingprocesses, early improvements, etc.Agenda.Net was launched February 5, 2021 for City and on February 19, 2021publicorganiza tion as more Committees are added to the platform. Progress Update Project team currently completing requirements workshops and beginning design phase of the solution. Close collaboration with divisions that will become early adopters has been effective in ensuring all business processes and unionfinal solution. 2021 - Timeline to Complete 2020 Timeline to Complete Completed in 2021Completed in 2021 Communications Services Project Manager Jason Winter Asset Management & Business Solutions Project Manager Nicole Amaral Corporate & Marketing Jeff Bunn Legislated first - based timesheets. - the have to Implement mobile time entry for operations, Corporate ServicesTransformation and Relaunch of Kitchener.ca Relaunch Kitchener.ca as a userdesigned site that is easy for residents to quickly find any information they are looking for, as well as delivered to them.Electronic Agenda Management Create, prepare, approve and publish meeting agenda packages and minutes in a more efficient, collaborative, streamlined manner.Financial ServicesMobile Time Entry eliminating the need for paper 5 06 BP0BP BP07 28 consider the expansion of payment determination on Community Benefits Charge to be Progress Update Provincial legislation proclaimed in Fall 2020. Consultant has been retained and work will be launching in Q1 2021. Planning to complete Development Charges study in 2021, with completed in 2022.Capital Variance report and some policy updates planned for 2021. Other policy updates will occur in a future year.Expansion of Payment Options for Utility and Property Tax customers went live on February 24, 2021. The next phase of the project will options for Business Licensing, Building Permit, Planning and Miscellaneous Receivable services.The Point of Sale part of the project will be delayed until 2022. 202120212021 --- 2 22222 Timeline to Complete 2020 New date: 20 2020 New date: 20 2020 New date: 20 Project Manager Ryan Hagey Financial Planning Ryan Hagey Financial Planning Saleh Saleh Revenue Term - . Implementation ge study life cycle, and expand payment options Financial ServicesDevelopment Charge (DC) & Community Benefits Charge (CBC) Studies investigate whether the City should prepare a community benefits char Long Term Financial Plan Implement/consider recommended actions identified as 2020 items in the LongFinancial Plan.Point of Sale and Expansion of Payment Options Replace the existing Point of Sale system, which is past its for various services. 080910 BPBPBP 29 and development of a , preparations will be taking background research on e, ongoing, and a series of stakeholder Progress Update Several project activities have been completed: a capital budget restructuring exercismunicipal and industry comparatorscapital planning framework and processes. Financial modelling and projection work areworkshops will be conducted starting in May 2021.Construction activities continued in Winter 2020/2021. It is expected that underground work will be completed in Carl Zehr Square in the Spring 2021 and final place for surface concrete placement. Mechanical installations for the ice rink and water feature are underway. The demolition of the upper terrace will also be a focus area of work. 2 lete 2022021 -- Timeline to Comp 20202020 Project Manager Beatrice Powell Facilities Management Lynda Stewart Facilities Management on Carl Zehr r Spaces ing ss the infrastructure focus , term maintenance and capital - comprehensive review of facility construction associated with the rehabilitation Infrastructure ServicesFacilities Infrastructure Program Conduct ainfrastructure needs that will incorporate building condition assessments, sustainability opportunities, and accessibility needs to identify current gaps and inform longimprovement strategies to addredeficit.Rehabilitation of City Hall OutdooConstruction Phase 1 Begin of City Hall Outdoor spacesSquare and College Street. BP11BP12 30 rand River rk to track Community Assessment report, First ently resumed with the donor and and REEP (DMAF funding recipients) Greenhouse Gas consultation, and a framewo - k for RBJ Schlegel Phase 2 is nearing completion WIP (Water Infrastructure Program) is completed to - wood Park will have design and engagement completed in Progress Update Design worwith construction tenders being issued and prepared through spring. Construction is scheduled for summer and fall 2021. Survivor Garden was deferred in 2020 due to the impacts of COVID; discussions have recit is anticipated that this will move forward in 2021, with a tentatively completion of end of 2021. Westwood Park is part of a bundle of parks projects that has been awarded for design, engagement and implementation; West2021, and it is anticipated a tender for work will be issued and awarded in 2021. Construction may need to be deferred to 2022. Currently finalizing reporting and financial claim templates for the program. Preceding conditions of the DMAF agreement are complete, including Nations preEmployment Benefits. Agreements with GConservation Authorityhave been executed. Approximately 9% of construction for the DMAFdate. lete 2028 2021 - - 2 2 Timeline to Comp 2020 New date: 20 2020 Project Manager Niall Lobley Parks & Cemeteries Nick Gollan Sanitary & Stormwater Utilities Park; ; and RBJ Schlegel urvivor Garden Adaptation Fund (DMAF) Infrastructure ServicesImplementation of Significant Parks Projects Complete Phase 2 design work for plan, design and construct the Scomplete the upgrade to Westwood Park.Implementation of the Federal Disaster Mitigation and Plan and execute stormwater management infrastructure projects across the city to leverage the DMAF grant funding and advance the implementation of the 2016 Integrated Stormwater Management Master Plan. 1314 BPBP