HomeMy WebLinkAboutCAO-2021-004 - 2021 Business Plan - June Progress Report
REPORT TO: Council
DATE OF MEETING: June 28, 2021
SUBMITTED BY: Kathryn Dever, Director, Strategy and Corporate Performance
519-741-2200 ext. 78xx
PREPARED BY: Karen Cooper, Manager, Strategic and Business Planning,
519-741-2200 ext. 7817
WARD(S) INVOLVED: All Ward(s)
DATE OF REPORT: June 24, 2021
REPORT NO.: CAO-2021-004
SUBJECT: 2021 Business Plan - June Progress Report
RECOMMENDATION:
For information
REPORT HIGHLIGHTS:
This report presents the 2021 Business Plan June Progress Report (Appendix A).
This progress report lets Council and the community know that, due to the pandemic,
completing 22 of the 25 strategic actions are expected to be completed by 2022 and and 3
of the strategic actions are now to be completed in 2023.
Of the strategic and business projects expected to be completed this year, 3 strategic and 2
business projects have been completed as of the end of June. An additional 8 projects are
to be completed by year end. Updates on delayed projects and future year projects are
provided in this report.
caring and vibrant Kitchener.
BACKGROUND:
As previously reported, the COVID-19 global pandemic dramatically changed the lives of Kitchener
residents and citizens throughout Waterloo Region and around the world. Over the past year, the
City placed the safety of citizens and staff as a top priority throughout its pandemic response and
recovery efforts, while also supporting the economic sustainability of businesses and employers in
the municipality. Council approved the 2020 budget focusing on delivery of the Strategic Plan and
continued this focus within a constrained budget in 2021 to address financial impacts of the
pandemic. These were sound decisions that enabled city staff to focus on key priorities while
delivering core services.
Increasingly, the pandemic has had impacts on staff workloads, retention, retirements and
recruitment that are being felt in the organization affecting service delivery and operations.
*** This information is available in accessible formats upon request. ***
Please call 519-741-2345 or TTY 1-866-969-9994 for assistance.
The Corporate Leadership Team has been working to address these issues through supports to
employees, reviewing workloads to focusing on priorities, and reassessing what are reasonable
expectations during these times. This includes balancing core service workload with pandemic
response and addressing related staffing resource challenges.
The 2021 Strategic Plan and Business Plan commitments have also been reviewed. While a great
deal of progress has been made this year despite the pandemic and workload challenges, a
number or projects have been delayed, and several since the April update that Council received.
These delays are concentrated in a few key areas, as a result of both the pandemic and resourcing
challenges. With respect to the 25 Actions in our 2019-2022 Strategic Plan, staff remain committed
to action all of them within the term of Council, however 3 actions will now be completed in 2023.
REPORT:
Overall Status of Strategic Plan Actions
The following chart illustrates the status of the 25 Strategic Plan actions
Status of 2021 Scheduled End Date Projects
In total, nine strategic actions are completed of which three have been completed in 2021 as
scheduled. An additional four projects are on track for completion by the end of 2021. Four
projects are delayed.
2021 Completed Projects
Community Climate Action Plan
Customer Satisfaction Program
On-Line Customer Service Portal
Community Climate Action Plan
TransformWR is a region-wide response to the global
climate crisis. It is a long-term strategy to achieve an
80% local greenhouse gas emission (GHG) reduction
target (based on 2010 levels), and identifies local action
needed to reduce emissions by 30% by 2030. It was
prepared by ClimateActionWR collaborative, led by
Reep Green Solutions and Sustainable Waterloo
Region with participation from the Cities, Townships
and the Region. On June 14, 2021, the Planning and
Strategic Initiatives Committee recommended to
Council that TransformWR be adopted as the city
Community Climate Action with an implementation plan
specific to the City of Kitchener to be prepared.
Customer Satisfaction Program
The closure of City facilities and the cancellation of programming due to the province-wide
shutdown means there are limited service areas to expand feedback collection at this time. When
areas reopen, the City's service offerings will be reviewed to determine what to include in the
next quarter. Staff are looking into collecting feedback on Golf (book a tee time online and onsite
feedback) and are working with the ActiveNet team to implement post-registration and post-
programming feedback collection, that will launch when programming reopens.
On-Line Customer Service Portal
In the first 120 days since MyKitchener launched to the public, 7,487 accounts were registered
- an average of 62 new accounts each day. With over a million views, there has been a 98.5%
success rate in searches.
Top 5 widgets Top 5 pages
My property taxes Homepage
My utilities Job opportunities
Programs and activities Kitchener Golf
Road closures Contact us
Job opportunities COVID-19 updates
2021 On Track Projects
City-Owned Property Review
Equity, Diversity and Inclusion Strategy
Mill Courtland Community Centre Expansion Business Case
Multi-Language Interpretation Support
2021 Delayed Projects
Bringing a Property to Market
Pedestrian-First Street Final Plan for Gaukel Street
Open Space Strategy
Tree Canopy Target
Bringing a Project to Market
The comprehensive property review is anticipated to be presented to Council in September 2021.
Recommendation for a property to be put on the market requires additional community consultation and
the impact of the pandemic on market conditions needs to be considered. It is anticipated that a property
brought to market will occur in 2022.
Pedestrian-First Street Plan for Gaukel Street
Additional seating has been added to the Joseph Street/Charles Street block for summer 2021.
Permanent solution delayed to 2022 due to pandemic restrictions while the interim solution remains
in place.
Open Space Strategy
As part of the Strategic Plan action to equitably distribute leisure facilities an Open Space Strategy
was to be prepared to update and replace the 2010 Parks Strategic Plan. Budget to undertake the
work was provided in 2020, however, the pandemic impacts delayed starting the new plan with
budget deferral to 2021. Ongoing staff resource challenges (Manager vacancy and DEL impacts)
and legislative changes (Development Charges and Community Benefit Charges) have caused
additional delays. Places and Spaces is the working title for this new plan. This reflects that the
spaces that we have in parks and open space across the City are important parts of building places
for the City and at a neighbourhood level.
The Planning Act requires that the Parkland Dedication bylaw and the supporting Parks Plan be in
place no later than September 2022. Staff have prioritized the Spaces component of the strategy
to be developed in 2021. Engagement will occur through summer and fall 2021 and Spaces will
be presented to Council alongside a Parkland Dedications bylaw in the first half of 2022.
It is anticipated that engagement on the Places component will begin in late summer and fall 2021,
continuing through to summer 2022 with Places presented to Council in the first half of 2023.
A Council Strategic Session in August is planned to provide a more fulsome update on Places and
Spaces and to seek engagement with Council on emerging themes.
Tree Canopy Target
outlining a community informed vision for urban forestry across the City of Kitchener. Stemming
from that plan, two actions were embedded in the Strategic Plan:
Eliminate the 2018 tree planting backlog by 2022
Establishing a tree canopy target by 2020
The tree inventory and risk assessment has been delayed but is underway in 2021. Work started
on a tree pruning program in 2020 is now delayed due to staffing pressures but is being revisited
in 2021. COVID-19 also created a delay in receiving updated tree canopy data for the City. Work
to develop a tree canopy target includes understanding the priorities for tree canopy through
seeking feedback on what is important about how the City provides and maintains canopy cover.
Work is also needed to understand the desire and capacity for future investments in the tree
canopy from to ensure that a target is aligned with the financial capacity of the City to be able to
deliver on. Due to staffing vacancies this work cannot be completed as planned in 2021.
Status of 2022 Scheduled End Date Projects
On Track Projects
Bikeshare Program
Connectivity and Year-Round Maintenance of Multi-Use Trails and Pathways
Pedestrian-First Street Plan for Kitchener Market
Tree Planting to Eliminate Backlog
Arts and Culture Plan
Huron Brigadoon Area School/Community Centre Construction
Leverage the Energy Efficiency Reserve Fund
Set and Communicate Service Levels
Customer Experience Program
Delayed Project
Waste Diversion Strategy work commenced in 2019 but is postponed due to the lack of events
during the pandemic.
Projects now Scheduled for 2023
Protected Cycling Network Connection to the Downtown
New Rosenberg Community Centre/School Business Case
Open Space Strategy - Places Component
Innovation District (Bramm Yards) Master Plan
Civic District Master Plan
Overall Status of Business Plan Projects
On Track Projects
6 business plan projects are on track for their scheduled end date, including:
Budd Park Strategy (2021)
Cameron Heights Pool Feasibility Study (2021)
Southwest District Pool Business Case (2021)
Rehabilitation of City Hall Outdoor Spaces Construction Phase 1 (2021)
Facilities Infrastructure Program (2022)
Implementation of Federal Disaster Mitigation & Adaptation Fund (2028) with caution due
to staffing level
Delayed Projects
6 business plan projects are delayed with completion now planned for 2022, as follows:
Ice Demand Study - Likely to begin in 2022 but TBD on completion.
Mobile Time Entry - Delay due to workload pressures. Phased approach considered for roll-out
with implementation starting in Q1 of 2022
Development Charge (DC) and Community Benefits Charge (CBC) Studies - Work with consultant
underway - won't be completed in time to be reflected in the 2022 capital forecast. Approval by
Council to be sought in Q1 2022 with new rates effective July 1, 2022
Long Term Financial Plan Implementation - Investment policy approved in April 2021. Capital
variance report delayed to 2022 due to implementation of new roles/structure in Financial Services
Point of Sale and Expansion of Payment Options Point of Sale delayed to 2022, Work continues
on expanded online payment options.
Implementation of Significant Parks Projects - RBJ Schlegel remains on track for late 2021/early
2022 completion. Other significant park projects have been started with engagement initiated in
Spring 2021. Completion of upgrades in 2022 delayed as per previous April update due to staff
on DEL.
STRATEGIC PLAN ALIGNMENT:
This
vibrant Kitchener.
FINANCIAL IMPLICATIONS:
None
COMMUNITY ENGAGEMENT:
INFORM This report has been
council / committee meeting.
CONSULT In 2018, Compass Kitchener consulted the public on developing community priorities
for the 2019-2022 Strategic Plan, which informed preparation of the 2021 Business Plan project
list.
On May 6, 2021 Compass Kitchener hosted a virtual meeting of all of the Advisory Committee
Chairs and Vice Chairs. Twenty-three advisory committee members attended, including Compass
Kitchener members. One of the workshop sessions held addressed evaluating strategic plan
progress. Staff presented a summary of the status the strategic plan projects and the advisory
committee members discussed their views on highlights of progress made to date.
General Comments on Highlights of Strategic Plan Progress
All of it!
Appreciate approach to
Very innovative
Happy to see vibrancy is wrapped into planning metrics (not just economic) in urban design
Many completed items are strategies so implementation will show progress over time
Impressed by how much is being done.
Excited to see areas such as complete streets, bike programs, affordable housing.
Specific Highlights of Strategic Plan Progress
Great Customer Service initiatives regarding the portal and website update were
mentioned the most at 10 times.
Housing for All and Make it Kitchener 2.0 were mentioned 7 times each.
Caring Community initiatives including CTS, Sanguen training, mental health strategy and
anti-stigma training were mentioned 6 times.
People-friendly Transportation initiatives including cycling grid, cycling and trails master
plan, and pedestrian first streets were mentioned 4 times.
Progress during pandemic was mentioned 3 times
Planning for vibrancy and people-first city received 1 mention each
Compass Kitchener will be reporting more fully on the results when they present their 2021 Report
Card to Council in the fall.
PREVIOUS REPORTS/AUTHORITIES:
CAO-21-002 2021 Business Plan April Progress Report
CAO-20-008 2020 Business Plan Year-End Progress Report and Recommended 2021 Business
Plan Project List
APPROVED BY: Dan Chapman, Chief Administrative Officer
ATTACHMENTS:
Appendix A: 2021 Business Plan Progress Report June 30, 2021
1
33466778992
1214182224242525262628
...
........
....................
............
.............
..............
.............
................
...............
....................
...................
.................................................................
.......................
........................
...........................
............................
..........................................................
................................
................................
................................................................
................................
................................
................................
................................
................................
................................
................................
................................
................................................................................................
................................
................................
................................
................................
................................................................
................................
................................
................................................................
................................
................................
................................
................................
................................
................................
................................
................................
................................................................................................
................................
................................
................................
................................
................................................................
................................
................................
................................................................
................................
................................
................................
................................
................................
................................
................................
................................
................................................................................................
................................
................................
................................
................................
................................................................
................................
................................
................................................................
................................
................................
................................
................................
................................
................................
................................
................................
................................................................................................
................................
................................
................................
................................
................................................................
................................
................................
................................
................................
................................
................................
................................
................................
................................
................................................................
rategic Plan Actions
................................
ervice
................................
................................................................
lan Project Completions
19: One Year Later
-
Friendly Transportation
-
................................
................................
ronmental Leadership
Overall Status of StStrategic Plan Completions and AchievementsPeopleEnviVibrant EconomyCaring CommunityGreat Customer SBusiness PCommunity ServicesCorporate ServicesFinancial ServicesInfrastructure
Services
2022 Strategic Plan Evaluation Criteria2022 Strategic Plan Actions
--
Contents IntroductionImpact of COVIDOverall Status of the 2021 Business Plan Projects2019Strategic Plan2019Business Plan ProjectsBusiness Plan Projects
3
is
an
made
each of
as a top improve
project
in
staff adapted
Each
how
and staff
of
This report contains
term benefits.
-
ete the work.
projects completed
3
gic Plan.
, with
modernize service delivery and
to
lan and other key priorities. These projects
p
business plan projects.
placed the safety of citizens
14
has
egion and around the world changed as the World
trategic
pandemic and provide long
R
-
s
outlined in the Strate
strategic projects
the economic sustainability of businesses and employers in
he City
Council and the community can be proud
ing
19.
-
ic Plan, as well as
and provides an update on new completion dates for projects.
While this would be a commendable start to any year, the progress
.
entary and innovative approaches
m
2022 Strateg
-Over the past year, t
le
of living with COVID
and June 30, 2021
15 months
recovery efforts, while also support
Later 19 a global pandemic.
-
ocal businesses and establishing centralized service counters at city hall. While some of the service delivery
all 25 actions from the 2019
including anticipated timing for completion. Regular progress is reported to Council and the public throughout
lan, which is developed alongside the budget to ensure resources are aligned to compl
enabling staff to work from home, providing more services online, offering existing programs in new virtual formats,
p
d
Fifteen Months
3 more completed in the first quarter of 2021
:
0, the lives of Kitchener residents and citizens throughout Waterloo
usiness
19
To achieve these priorities, staff took comp
llenging time, staff demonstrated resiliency and made progress on
include
-
business plan,
b
its pandemic response and
and
This
2020, 2021 is especially noteworthy after
Business Plan includes
1
in
Introduction Each year, Kitchener City Council approves a list of projects that implement the current form the annualdescribed in the the year.The 202update on progress made between
April 30, 2021 Impact of COVID On March 11, 202Health Organization declared COVIDpriority throughthe municipality.efficiencies. providing training and supports to lchanges are only
temporary to address the pandemic restrictions, many will remain postThrough this cha2019 and to dateto the challenges of the pandemic and continued to deliver on the community priorities
1
4
were
projects
Construction Phase
are
17
,
Thirteen
.
this year
ment
upcoming completions
be completed in 2021
project
.
to be completed
are on track to
Budd Park Strategy Cameron Heights Pool Feasibility StudySouthwest District Pool Business CaseRehabilitation of City Hall Outdoor Spaces
usiness plan
Transformation and Relaunch of Kitchener.caElectronic Agenda Manage
usiness plan projects
B
projects
2
8
2021 B
.
Projects
21
-
10
that were initially planned
omplete in 2023 and 1 in 2028
, an additional
pages
are to c
projects
4
ness Plan
i
in 2021
projects
, with 2
Bus
5
, :
1
completion
have been completed
projects
include
completions
40
completions
projects
upcoming completions
in 2021
5
,
s
comprises
s
2021
rack for 2022
project
t
Community Centre Expansion Business Case
projects and their status is included on
projects on track for
Satisfaction Program
Status of the 202
Language Interpretation Support
Completion
Projects
-
Business Plan
Owned Property Review
-
completed to date
projects on
1
trategic plan
projects on track for 2023
8 additional2051 project on track for 2028
Community Climate Action PlanCustomer Online Customer Service Portal Development
CityEquity, Diversity and Inclusion StrategyMill Courtland Multi
description of
now expected to be completed in 2022
trategic plan project
at the end of June
S
rojects
3 2021 S
Overall The 202expected to be completed in 2022, 2 in 2023 and 1 in 2028. As are The Complete P Upcoming
5
report
.
Capital variance
-
options
Community Benefits Charge Studies
upcoming completions
&
Likely to begin in 2022 but TBD on completion.
-
Facilities Infrastructure Program Ice Demand Study Mobile Time Entry Development ChargeLong Term Financial Plan Implementation Point of Sale and Expansion of PaymentImplementation of
Significant Parks Projects Implementation of Federal Disaster Mitigation & Adaptation Fund
2022 Business plan project 2028 Business plan project upcoming completion
Public
at
Use Trails
-
upcoming completionsupcoming completions
Round Maintenance Multi
-
project project
Year
/
First Street Final Plan for Gaukel StreetFirst Street Plan for Kitchener Market
--
Bikeshare ProgramConnectivityand PathwaysPedestrianPedestrianTree Planting to Eliminate BacklogTree Canopy TargetArts and Culture PlanHuron Brigadoon Area School/Community Centre ConstructionLeverage
the Energy Efficiency Reserve Fund Bringing a Project to MarketWaste Diversion Strategy: Increase Waste Diversion Spaces and Events Set and Communicate Service LevelsCustomer Experience
Program Protected Cycling Network Connection to the DowntownNew Rosenberg Community Centre/School Business CaseOpen Space StrategyBramm Yard Master Plan Civic District Master Plan
2022 Strategic plan 2023 Strategic plan
6
.
As
will
future
and
s adopted
e implementation
inning in 2021.
l be shared with the
004.
-
20
-
the SDGs for the Kitchener context. This
ing
within the strategic planning process
and adapt
2022 strategic plan connect to at least one of the SDGs
Appendix B of report CAO
-
ing
p
localiz
2022 Strategic Plan:
-
, begin work on
2022 Strategic Plan can be found in
provides advice to Council on
-
Green Beacon
,
to fully integrate, implement, and operationalize SDGs
Each of the 25 action statements within the 2019
identifies community priorities for action, and monitors progress toward achieving the community vision and
5 strategic plan actions have been completed (28%).
Plan.
Citizen Advisory Committee
rategic
, staff worked with local consultant
Compass Kitchener
0
Canada and internationally.
, 2021, 7 out of the 2
d project has enabled the City to set specific benchmarks and measure progress towards achieving the SDGs within current and
provide a roadmap for the City
2022 Strategic Plan Evaluation Criteria
-
will
Compass Kitchener
Overall Implementation of the Strategic PlanOverall Implementation of the Sustainable Development Goals (SDGs) through the Strategic PlanImplementation of Strategic Plan GoalsImplementation
of Strategic Plan Actions
June 30
the fall of 202
2019 The participation. in implementing the StCompass Kitchener has 4 levels of evaluation criteria/measures for the 2019One evaluation metric has been proposed for each of the 25 Strategic
Plan actions. These metrics will be tracked by staff begof
Local At the United Nations (UN) Sustainable Development Summit in September 2015, world leaders from Canada and other member statethe 2030 Agenda for Sustainable Development and 17
Sustainable Development Gand tackle climate change by 2030. The City of Kitchener is committed to working with the Government of Canada in embracing the 2030 Agenda and to supporting
thof the SDGs inInproject serve as a model regionally, nationally, and globally.This localizestrategic plans. Once the localized SDG targets and indicators are finalized and benchmark
data has been collected, they wilpublic through an online Citizen Dashboard.
7
Strategic Plan Overall Status of Strategic Plan Actions
8
-
registration and post
-
post
term strategy to achieve an 80% local
-
have been completed to date in 2021.
s
an average of 62 new accounts each day. With over a million
-
mine what to include in the next quarter. Staff are looking into
wide shutdown means there are limited service areas to expand feedback
-
prepared by ClimateActionWR collaborative, led by Reep Green Solutions and
The following strategic plan project
wide response to the global climate crisis. It is a long
-
19 updates
-
7,487 accounts were registered
is a region
HomepageJob opportunitiesKitchener GolfContact usCOVID
pages
Top 5
TransformWRgreenhouse gas emission (GHG) reduction target (based on 2010 levels), and identifies local action needed to reduce emissions by 30% by 2030. It wasSustainable Waterloo Region
with participation from the Cities, Townships and the Region. On June 14, 2021, the Planning and Strategic Initiatives Committee recommended to Council Community Climate Action with
an implementation plan specific to the City of Kitchener to be prepared.
the five goals of the Strategic Plan.
will launch when programming reopens.
each of
98.5% success rate in searches.
progress under
Completions and Achievements
My property taxesMy utilitiesPrograms and activitiesRoad closuresJob opportunities
is making
Line Customer Service Portal
-
Top 5 widgets
Strategic Plan The City Community Climate Action Plan Customer Satisfaction Program The closure of City facilities and the cancellation of programming due to the provincecollection
at this time. When areas reopen, the City's service offerings will be reviewed to detercollecting feedback on Golf (book a tee time online and onsite feedback) and are working with
the ActiveNet team to implementprogramming feedback collection, that On In the first 120 days since MyKitchener launched to the public, views, there has been a
9
here.
scooters as part
-
bikes and e
-
Progress Update
comfortable and connected.
wide bikeshare feasibility study
-
Completed in 2019.Read Complete Streets Kitchener A regionwas approved that recommends a collaborative approach to a bikeshareprogram throughout the region. A regionwide project team
is investigating the use of eof the future program and note that
complet
2022
-
to
2019
Timeline
Complete
Completedin 2020
Project
Manager
Barry Cronkite Transportation Services Barry Cronkite Transportation Services
ch bicycles
is underway
Project
Indigenous Initiatives started at the city in June and will oversee
ikeshare service in whi
b
Actions
Racism and
-
hare Program
made available for shared use to the public
:
s
are
Complete StreetsƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЊВ͵Bikes Implement aare in an effort to a feasibility study to determine the most appropriate system.
the fall of 2021 and recruiting to complete her staff team.
include
progress
Transform how people move through the city by making the transportation network safe, convenient,
Statement
onstruction of the Protected Cycling Network 2022 Strategic Plan
-
CThe New Director of Equity, Antion a new EDI strategy by Supportive housing projects GOAL:
Friendly Transportation
-
Strategic Plan Action
Develop a set of Complete Encourage and incentivize
1.1 Streets (safe and comfortable) guidelines and an associated evaluation scorecard by 2020 to apply to roadway construction projects.1.2 alternative modes of transportation by developing
and subsidizing a bikeshare program by 2021.
Other strategic plan 2019 People
10
transportation
is underway.
Progress Update
.
a wider range of
.
onstruction
traditional private bikeshare providers have changed their business model to reflect optionsCCompleted in 2020.Read the Cycling and Trails Master Plan hereTrail improvements are being
planned on several community trails and bridges including: Traynor to Wilson, Kingsway to Vanier, sections of the Laurentian Trail, bridges in Vanier, Rothsay, Lynn Valley
20232022
--
to
2020
Timeline
Complete
2020 Completedin 2020
Project
Manager
ace Design &
Darren Kropf Transportation Services Liz Christensen Transportation Services Liz Christensen Parks & Open SpDevelopment
round
-
athways
and the
dresses
Round
, in one
-
Connected to the
cent neighbourhoods Trails and P
.
se
U
use trails and pathways
-
-
Project
connectivity and year
wayfinding.
road cycling facilities, as well as
connects adja
-
town by 2022
Use Trails and Pathways Master Plan
-
the 2010 Cycling Master Plan
Cycling and Trails Master Plan UpdateConnectivity and Year
road trails infrastructure
-
include on
Protected Cycling NetworkDowntown Install a continuous and protected cycling network that to the down 1.4.1 Update2012 Multito offcomprehensive plan that also adeducation and 1.4.2 Maintenance
of Multi Prioritize actions,maintenance to multi
.
.
cent
round access
-
Statement
use trails and pathways
town by 2022
-
round maintenance to
-minimum of an additional
Strategic Plan Action
Install a continuous and Improve connectivity and
1.3 protected cycling network that connects adjaneighbourhoods to the down 1.4 yearmultias prioritized through the Cycling and Trails Master Planwith an initial target of providing yearto
a 3 km of existing trails by 2022
11
remain
.
anticipated to
end 2021
ork is
W
Permanent solution
the
Progress Update
ct charter has been approved.
cost street interventions.
-
and Victoria Park.be completed by Gaukel Street was closed to traffic during the pandemic and will continue to remain closed as a passive pedestrian space. The block between King St
and Charles St will be turned into passive space in late spring 2021, subject to development construction completing, and additional formal seating will be added to the Joseph St/Charles
St block in summer 2021.delayed to 2022 due to pandemic restrictions (interim solution will in place)A projeStaff is investigating programming and low
2
2022022
--
to
Timeline
Complete
20202021
Project
Manager
Darren KropfTransportation Services Darren Kropf Transportation Services
with
,
.
Street.
et Plan for Kitchener
3 km of existing trails
round access to a
-
Project
First Plan for Gaukel StreetFirst Stre
--
PedestrianPedestrian
through the Cycling and Trails Master Planan initial target of yearminimum of an additional by 2022.1.5.1 Develop plans to prioritize pedestrians over other travel modes on Gaukel 1.5.2
Market Develop plans to prioritize pedestrians over other travel modes between the Kitchener Market ION station and Kitchener Market
first streets
-
Statement
Strategic Plan Action
Develop a plan to create
1.5 pedestrianbetween Victoria Park and City Hall and between the ION and Kitchener Market by 2022.
12
.
here
sources.
ikely to continue but
l
wide response to the global
term strategy to achieve an
-
-
Progress Update
19 safety concerns the project was
is a region
-
outfitting Civic District Garage and KOF
prepared by ClimateActionWR collaborative,
nce new staff is onboard
Project completed in 2019. Read the Corporate Climate Action Plan Originally the 2020 capital energy reserve project was to retrofit the remaining administrative office lighting at the
Kitchener Operations Facility (KOF). Due to COVIDswitched toShops & Stores. Both projects are underway.Omodified due to COVID
TransformWRclimate crisis. It is a long80% local greenhouse gas emission (GHG) reduction target (based on 2010 levels), and identifies local action needed to reduce emissions by 30%
by 2030. It was
2022
-
20192021
Complete
Timeline to Completed in 2020 Completed in
---
stration
Project
Manager
TBD AdministrationDevelopment Services TBD AdminiDevelopment Services Samantha Tavenor AdministrationDevelopment Services
Reporting
Project
l continue until 2026.
Climate Action Plan
nually on greenhouse gas emission
Corporate Climate Action PlanƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЊВ͵anreduction wil Leverage the Energy Efficiency Reserve Fund Leverage the fund to undertake energy efficiency retrofit projects on
City of Kitchener assets and capture and reinvest the operating savings to pay for capital costs.Community Complete the 80x50 Community Climate Action Plan.
.
facilities and
ciency Reserve
i
Statement
ergy Eff
arting in 2019, leverage
Achieve a healthy and livable community by proactively mitigating and adapting to climate change and by conserving natural re
.
Launch and implement a StDevelop a Community
Strategic Plan Action
2.1 Corporate Climate Action Plan by 2019 to achieve an absolute greenhouse gas emission reduction of at least 8% by 2026.2.2 the EnFund and other resources to reduce consumption and
emission at our in our operations 2.3 Climate Action Plan with partner organizations by 2020
Environmental Leadership Goal:
13
inated,
is delayed and
that TransformWR be
Progress Update
when staffing secured.
occur
The final tree canopy dataset has been received from the consultant. Community and Council engagement regarding Kitchener's tree canopy and the setting of a tree canopy target will Spring
tree planting was cancelled in 2020 due to the pandemic. A fall tree plant took place in 2020 and staff remain optimistic that by the conclusion of the spring 2022 tree planting season,
the 2018 backlog of street trees will have been elimdelivering on the Strategic Plan target.
led by Reep Green Solutions and Sustainable Waterloo Region with participation from the Cities, Townships and the Region. On June 14, 2021, the Planning and Strategic Initiatives Committee
recommended to Council an implementation plan specific to the City of Kitchener to be prepared.
20212022
--
Complete
Timeline to 20202020
Schmitt
Project
Manager
Dave Forestry & Natural Areas Management Adam Buitendyk Forestry & Natural Areas Management
acklog
B
Project
lanting
P
ion
Tree Canopy TargetTree
iminat
2.4.1 Review the current canopy cover and set an achievable target based on best practices as well as constraints such as land availability, quality of soil, etc. in order to guide ongoing
and future investment in tree planting, protection and maintenance.2.4.2 El Plant at least 750 trees in 2020, with the goal of reaching 2,500 trees and eliminating the current backlog
by the end of 2022.
and
Statement
.
Implement the
Strategic Plan Action
2.4 Sustainable Urban Forest Strategy with a focus on establishing a tree canopy target by 2020 eliminating the current (2018) tree planting backlog by 2022
14
ikely to
, l
learning .
and great places
or
here.
.
public events were
here
Progress Update
Progress Update
nce new staff is onboard
2019.2019.
O
in in
Completed Read the Urban Design Manual Completed Learn about this project
Due to the pandemic, largecancelled, and this project is postponed until events restart. Recycling and organics diversion has also increased across public facilities and spaces, including
a pilot project to improve waste station wayfinding for people with visualimpairments as well as English as a second language (ESL) visitors.continue but modified due to COVID
22
20
-
20192019
Complete
Timeline to Completed in Completed in
Complete
Timeline to 2020
-
Project
Project
Manager
Manager
Dayna Edwards Planning Cory Bluhm
TBD AdministrationDevelopment Services
Project
Project
Buildout of 44 Gaukel
run events with large
-
Urban Design ManualƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЊВ͵3.2.1
Waste Diversion Strategy: Increase Waste Diversion in Our Public Spaces and Events Expand the Waste Diversion Station to all Cityvolunteer involvement, and evaluate expanded waste diversion
stations at events, parks and public facilities.
wide
-
Statement
Build a vibrant city by making strategic investments to support job creation, economic prosperity, thriving arts and culture,
.
Reduce waste diverted to Complete a new Urban Design Foster the creation of a city
Strategic Plan Action
Strategic Plan Action Statement
2.5 landfills by implementing new diversion programs at our facilities and events by 2021 3.1 Manual by 2019 that expresses city building and design expectations to ensure vibrant new
development throughout Kitchener.3.2 network of incubators, accelerators
Vibrant Economy GOAL:to live.
15
.
here
in late 2021.
Progress Update
It Kitchener 2.0 Strategy
owned space and with potential
to Council
-
Staff is investigating opportunities for incubators within Citypartners. Business cases will be prepared and presented Completed in 2020.Read the Make
2021
-
2020
Complete
Timeline to 2020 Completed in
Project
Manager
Economic Development Cory Bluhm Economic Development Lauren Chlumsky Economic Development
Accelerator
Strategy by
tech industry
-
Project
Working Space
-
ubators.
ƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЊВ͵3.2.2 Incubator, and CoNetwork Lease all spaces in the Creative Hub, explore the potential to facilitate a Food Incubator with a business case pending, and explore
partnerships for the development of manufacturing and health/medinc Make It Kitchener 2.0 Strategy Develop the Make it Kitchener 2.0 2020 with a focus on transformative actions to
-
Make it Kitchener 2.0
tech industries.
-
working spaces by completing
-
h/med
Develop the
Strategic Plan Action Statement
and cothe buildout of 44 Gaukel in 2019, advancing work on a Creative Hub and undertaking business cases in 20192021 for the food manufacturing and healt 3.3 Strategy by 2020 with a
focus on transformative actions to ensure the attraction, success and retention of diverse businesses, talent, and arts/culture across the city.
16
is
.
will be
sites
after comprehensive
2
in late
Because of the pandemic and
2021.
Progress Update
late
round affordable housing and Make It
omprehensive review and completion
A c
2021. It is expected that the first property
Initial focus has been on supportive housingDue to the pandemic, finalization of the review is delayed until 2021.urgent need aKitchener, components of the review commenced in 2020.anticipated
in This will occur once the City owned property review has been completed brought to market in 202community engagement.
2023
-
11
Complete
Timeline to 202202
Project
Manager
Brian Bennett& Rob Morgan Economic Development Brian Bennett Economic Development
eview
to advance
owned
arket
-owned property
-
comprehensive
Project
Owned Property
-
Owned Property R
-
ensure the attraction, success and retention of diverse businesses, talent, and arts/culture across the city.City Complete areview of cityproperties by 2020 to determine how they could
be effectively usedcity strategic objectives.3.5.1 CityBrought to M Develop a vision for downtown Kitchener and continue to position downtown Kitchener as a leading destination for
redevelopment opportunities, with at least one new citybrought to market by 2020.
s)
owned properties by 2020 to
-
owned property brought to
Complete a comprehensive review Develop a vision for downtown
-
city
Strategic Plan Action Statement
3.4 of determine how they could be effectively used to advance city strategic objectives. 3.5 Kitchener and continue to position downtown Kitchener as a leading destination for redevelopment
opportunities, with at least one new citymarket by 2020. Finalize the Innovation District (Bramm YardMaster Plan by 2021 and the Civic District Master Plan by 2022.
17
in 2023
The project is
The project is delayed
Progress Update
The current focus is working with University of Waterloo to build out the Health Innovation Arena on the Health Sciences Campus. delayed and is expected to be completed in 2023Preliminary
project planning has started. A visioning exercise will be completed before the Master Plan commences.and is expected to be completed
1
2022022
- -
0
2323
Complete
Timeline to 202 New date: 20 2021 New date: 20
Project
Manager
Cory Bluhm Economic Development Cory Bluhm Economic Development
District
Project
Innovation District Civic District Master
3.5.2 (Bramm Yards) Master Plan Finalize the Innovation District (Bramm Yards) Master Plan by 2022.3.5.3 Plan Finalize the Civic Master Plan by 2022.
Strategic Plan Action Statement
18
-
-
&
here
task force
y,
by the end
income youth
informed
-
-
working groups will be
to complete work
the
Progress Update
tegy for the City of Kitchener, to be
ining
entorship program for low
ommunity grant for racialized groups
Policy TraDemographic Data CollectionHiring & Recruitment Communications CM
The Mayor's Task Force on Equity, Diversity & Inclusion is on track of June 2021. There are currently seven working groups developing equitystrategies and recommendations in the following
areas: The deliverables of compiled into a comprehensive Equity & AntiRacism Straimplemented by the newly formed Equity, AntiRacism & Indigenous Initiatives staff team.Completed in
2020.
2021
-
to
2020
Timeline
Complete
2020 Completed in
-
er
Project
Manag
Elin Moorlag Silk AdministrationCommunity Services Andrew Ramsaroop Planning
f
o
.
focused on better
nity groups and the
Project
ty, Diversity and
industry
represented people, as
-
Strategy
reate an Equi
Equity, Diversity and Inclusion Strategy CInclusion engaging and serving marginalized and underwell as creating a more inclusive City workplace.Affordable Housing Strategy Create an
Affordable Housing Strategy for Kitchener by 2020 in collaboration with the Region Waterloo, commudevelopment
.
.
nclusion
I
industry
f Waterloo,
o
Statement
nity groups and the
Diversity and
,
Strategic Plan Action
Create a comprehensive Create an Affordable
Caring Community
4.1 EquityStrategy by 2020 to combat systemic barriers to full economic and social participation in the city 4.2 Housing Strategy for Kitchener by 2020 in collaboration with the Region
commudevelopment
4. GOAL:supporting our diverse populations & helping to make housing affordable.
19
.
.
here
relevant to evolving
Progress Update
2019.
in
stigma training will now become a core
-
Completed in 2020.Antilearning program with ongoing evaluation and customization as required to meet the diversity of staff needs throughout the organization and to ensure the content
is community needs. Completed Learn about this project Staff have been able to start the business case in Q2. They are currently completing a terms of reference to hire a consultant
2021
-
to
20202019
Timeline
Complete
Completed in Completed in 2020
er
Project
Manag
Paula Dunn Human Resources Mark Hildebrand Neighbourhood Programs & Services
tigma through
S
Business Case
Project
ocial
S
needs assessment and
raining
Reduce Support for Safe Consumption Mill Courtland Community
T
taff
4.3.1 S Provide staff with the resources torespond effectively to changing community demographics. 4.3.2 and Treatment FacilitiesƚƩƉ ĭƚƒƦƌĻƷĻķ źƓ ЋЉЊВ͵4.4.1 Centre Expansion Complete
a business case to determine the requirements for an addition to the Mill Courtland Community Centre.
creation of
resources across
Statement
d an Open Space
.
and support the
an
ers,
Strategic Plan Action
Reduce social stigmas Better utilize existing
4.3 experienced by those living with mental illness and addiction in our community through staff training and supporting the appropriate safe consumption and treatment facilities in
Kitchener 4.4 facilities, provide relevant programming at community centequitable distribution of leisure programs and neighbourhoods. Start work on the Mill Courtland Community Centre
expansion by 2020 and the Rosenberg Community Centre by 2021. Complete the Huron Brigadoon Community CentreStrategy by 2021.
20
rating agreement
and the ongoing
19, this project is now delayed.
-
Progress Update
out to 2023 to 2026 by the school
and 2022. The Places component now
moved
.
Project boardWeekly construction meetings have started. FM project Manager at regular meetings and reporting back. Construction agreement between City and School board completed and
signed. Negotiations for Opebetween the City and Board pending.Due to staffing contraintsimpacts of COVID'Spaces' is being advanced to be completed by the provincial timelines of September
2022 and will be discussed with Council in 2021.Engagement on both Spaces and Places will occur in 2021 has an anticipated completion in 2023.
2
2022022
--
to
2323
Timeline
Complete
2021 New date: 20 2020 2020 New date: 20
er
Hildebrand
Project
Manag
Mark Hildebrand Neighbourhood Programs & Services Mark Neighbourhood Programs & Services Niall Lobley Parks & Cemeteries
/
Business Case
Project
Catholic School board,
New Rosenberg Community Huron Brigadoon Area School Open Space Strategy
parks.
4.4.2 Centre/School With the complete a needs assessment and business case to determine the requirements for a joint community centre/school in the Rosenberg area.4.4.3 Community Centre
Construction Construct a joint school/community centre in the Huron Brigadoon area, in partnership with the Waterloo Region District School Board.4.4.4 Develop an open space strategy
to explore the value of open spaces, how they function, are planned, maintained, and managed, and including a review of permitted uses in
Statement
Strategic Plan Action
21
loo for
to commence
these initiatives in underway.
Progress Update
pandemic, and therefore engagement has
-
The City developed a partnership with the Region of Waterloo and the City of Waterstakeholder consultation, research and analysis. A Terms of Reference and plan for stakeholder consultation
are under development. Consultation was anticipated for late 2020, however this has been postponed until later in 2021. The appropriate timecommunity engagement for the Culture Plan
is postbeen postponed. Support for professional artists and cultural organizations will be considered as part of the COVID recovery plan. Specific engagement on
2
202
-
to
Timeline
Complete
2020
er
Project
Manag
Emily Robson Economic Development
cultural
-
engaging a broad
Project
section of the community
-
Arts and Culture Plan Develop a new and inclusive Arts and Culture Plan by crossincluding the arts and creative industry sector and multicommunities.
-
-
Statement
Strategic Plan Action
Engage a broad cross
4.5 section of the community including the arts and creative industry sector and multicultural communities to develop an inclusive arts and culture Plan by 2021.
22
nology
he services it
The MyKitchener customer
support being trained to
Progress Update
launched in beta (an almost
person support (eg. community
-
during Covid. There are more services
portal
Plan to implement will be phased with staff providing telphoneuse the service this summer (eg. CCC, Revenue, Service Counters etc.) Staff who require providing incentres) will be trained
in fall when techis in place.Completed in 2021.This is as complete in terms of tavailableto expand to and additional technology (kiosks) to explore however this will rely on moving
past the pandemic to regular service offerings.Completed in 2021.servicefinished version the public can provide feedback on) to the public on March 1, 2021. The public is testing the
functionality of the portal during the beta test and staff are monitoring feedback and making
20212021
--
Complete
Timeline to 20202020 Completed in 2021Completedin 2021
Project
Manager
Jana Miller Corporate Customer Service Christine Baker Corporate Customer Service Jana Miller Corporate Customer Service
-
services
-
wide
o ensure a
-
demand multi
-
person inquiries to
Project
-
ugh a personalized, single
7 on
-
24
time feedback, monitoring
-
an organization
r Satisfaction Program that
a centralized online service portal
Language Interpretation Support
-
on account.
-
ulti
aunch
M Implement a language interpretation support for telephone and inenable staff in all facilities tmore consistent and equitable experience for all customers.Customer Satisfaction Program
Implement Customeenables realand reporting of satisfaction data to drive service improvements.Online Customer Service PortalDevelopment Lwhere citizens can access their ein one place
throsign
wide
-
collection
delivering
demand
-
service support in
Statement
and allowing financial
,
.
Strategic Plan Action
Provide onIntroduce a corporateEnhance customer
5.1 customer many languages through the Corporate Contact Centre by 2020 5.2 Customer Satisfaction Program that will allow for the of real time feedback from customers accessing city
facilities, programs, and services by 2020.5.3 experience online by customized information, providing easy access to servicestransactions by 2021.
Great Customer Service GOAL:
23
.
.
year
tion
at this time.
priate data to set
o
what we learn. Later
approximately a
work on this
Project to start in late 2021
Progress Update
to start and end in 2022. This
to start in 2022.
ore work is needed to ensure proper data
Project now
improvements based on in 2021, the project team will regroup to review the scope of Phase 2 of the portal's development, which will include additional new functionality for residents.See
the new website and access the portal:www.kitchener.ca Project Service areas where this will be required are without capacity to Mcollection to have the apprservice levels with. hinges
on data from Customer SatisfacProgram and it will take to have enough data to show a full review
20222022
--
Complete
Timeline to 20212021
Project
Manager
Jana Miller Corporate Customer Service Jana Miller Corporate Customer Service
Program
Project
2022.
Set and Communicate Service Levels Set clearly communicated and specific service levels for frequently asked about or accessed City services, including: tree maintenance, parking, property
standards complaints, snow clearing and grass cutting by Customer Experience Implement a comprehensive CustomerExperience Review Program to help ensure services are easy and convenient
by 2022.
.
by 2022
Statement
Strategic Plan Action
Set clearly communicated Implement a
5.4 and specific service levels for frequently asked about or accessed City services, including: tree maintenance, parking, property standards complaints, snow clearing and grass cutting
5.5 comprehensive Customer Experience Review Program to help ensure services are easy and convenient to access from 2022.
24
MyKitchener
ncil, Standing
new website,
the
its comprehensive new
ed
wide, fully automated application
-
back made it clear that the City is
edge online customer service portal
-
ite and MyKitchener portal will empower
judicial committee meetings, such as the
-
class web design practices to give Kitchener residents
-
the City of Kitchener launch
in
-
departmental collaboration, and automated approval
-
serve on their schedule.
-
services reimagines how municipalities offer services online.
On March 1, 2021, online experience for Kitchener residents, including a completely transformed website and new, cuttingcalled MyKitchener. The seamless integration between portal and
City The City has redeveloped its online presence from the ground up, incorporating bestexperience includes a new website with plain language content. By lowering the reading level
of the website from college to grade seven, the City is making their website more accessible and easier to understand. The City hopes that the new websresidents to self
for submitting agenda items and managing meetings for CouCommittees, and quasiCommittee of Adjustment. Through engagement across the City in 2019, stakeholders identified opportunities
to improve our report development and submission process. Valuable feedready for an enhanced and efficient report writing and meeting management software solution. Agenda.NET creates
enhancements and efficiencies, including automatically assigning report numbers, document versioning, crossworkflows. For report writers and approvers, it is time to make creating and
submitting items to Council and Committee meetings easy!
s
Transformation and Relaunch of Kitchener.caElectronic Agenda Management
1.2.
Business Plan Project Business Plan Project Completions
25
p the terms of reference for
o
s signature on the MOU for the roles and
due to COVID and impacts on user groups. Likely to
Progress Update A condition report has been completed for the facilities on the site. The work to evaluate the benefits of the Budd Lands for employment and for recreation is underway.responsibilitie
s of the City and WRDSB related to the feasibility study. Once the MOU is signed the TOR will be circulated.Planning is underway to develthe pool business case.Delayed begin sometime
in 2022 but unclear at this time when it could be completed.
2021202120212021
----
0
22
Timeline to Complete 202202020202020 New date: 20
Kugler
Project Manager Kim Sport Kim Kugler Sport Kim Kugler Sport Jeremy Dueck Sport
e
Feasibility Study
residents/stakeholders in a needs
Pool Business Cas
Study
Community ServicesBudd Park Strategy Identify potential sites and estimated costs to relocate the recreational assets at Budd Park and compare the costs to the economic benefits of using
the Budd Park for employment lands.Cameron Heights Pool Collaborate with the Waterloo Region District School Board to determine the renovations and estimated costs to isolate the pool
operation from the school operation to preserve a recreational asset in the downtown.Southwest District Engage community assessment and business case to determine the elements to be
included in the new pool.Ice Demand Evaluate ice user needs and trends for ice time to determine the timing of a new arena.
1234
BP0BP0BP0BP0
Business Plan Projects
26
taff
,
s
out with
-
.
for council and members of the
DC work with the consultant underway
.
launch rollout will continue within the
-
governance, training, documenting
. Post
launch administrative work will be ongoing
-
Progress Update The website and portal launched March 1, 2021. Postincludingprocesses, early improvements, etc.Agenda.Net was launched February 5, 2021 for City and on February 19, 2021publicorganiza
tion as more Committees are added to the platform.
elay due to workload pressures in other areas (operations,
Progress Update DHR) Phased approach being considered for rollimplementation not starting until Q1 of 2022Provincial legislation proclaimed in Fall 2020. Consultant has been retainedbut
won't be completed in time to be reflected in the 2022
20212021
--
Timeline to Complete 20202020
Timeline to Complete Completed in 2021Completed in 2021
Services
Project Manager Jason Winter Asset Management & Business Solutions Ryan Hagey Financial Planning
ing
Project Manager Nicole Amaral Corporate Communications & Market Jeff Bunn Legislated
first
-
based timesheets.
-
the
have
to
Implement mobile time entry for operations,
Corporate ServicesTransformation and Relaunch of Kitchener.ca Relaunch Kitchener.ca as a userdesigned site that is easy for residents to quickly find any information they are looking
for, as well as delivered to them.Electronic Agenda Management Create, prepare, approve and publish meeting agenda packages and minutes in a more efficient, collaborative, streamlined
manner.Financial ServicesMobile Time Entry eliminating the need for paper Development Charge (DC) & Community Benefits Charge (CBC) Studies
5
0608
BP0BP BP07BP
27
next phase
delayed until 2022.
is
.
capital variance report until 2022 due to
in
elay
Progress Update capital forecast. Recommend approval by Council in Q1 2022 with new rates effective July 1, 2022Investment policy completed and approved in April 2021. Dimplementation
of new roles/structure in financial planning & reportingExpansion of Payment Options for Utility and Property Tax customers went live on February 24, 2021. The of the project will
consider the expansion of payment options for Business Licensing, Building Permit, Planning and Miscellaneous Receivable services.The Point of Sale part of the project
20212021
--
2
22222
Timeline to Complete New date: 20 2020 New date: 20 2020 New date: 20
Project Manager Ryan Hagey Financial Planning Saleh Saleh Revenue
Term
-
.
Implementation
oint of Sale system, which is
development charges study and
Financial Services investigate whether the City should prepare a community benefits charge study Long Term Financial Plan Implement/consider recommended actions identified as 2020 items
in the LongFinancial Plan.Point of Sale and Expansion of Payment Options Replace the existing Ppast its life cycle, and expand payment options for various services.
0910
BPBP
28
and development of a
,
background research on
ce will also be a focus area of
e,
derground work will be completed in Carl Zehr
Progress Update Several project activities have been completed: a capital budget restructuring exercismunicipal and industry comparatorscapital planning framework and processes. Financial
modelling and projection work are ongoing, and a series of stakeholder workshops will be conducted starting in May 2021.Construction activities continued in Winter 2020/2021. It is
expected that unSquare in the Spring 2021 and final preparations will be taking place for surface concrete placement. Mechanical installations for the ice rink and water feature are
underway. The demolition of the upper terrawork.
2
2022021
--
Timeline to Complete 20202020
t
ProjecManager Beatrice Powell Facilities Management Lynda Stewart Facilities Management
on Carl Zehr
r Spaces
ing
ss the infrastructure
focus
,
to addre
term maintenance and capital
-
comprehensive review of facility
construction associated with the rehabilitation
Infrastructure ServicesFacilities Infrastructure Program Conduct ainfrastructure needs that will incorporate building condition assessments, sustainability opportunities, and accessibility
needs to identify current gaps and inform longimprovement strategies deficit.Rehabilitation of City Hall OutdooConstruction Phase 1 Begin of City Hall Outdoor spacesSquare and College
Street.
BP11BP12
29
to the impacts of
rand River
Assessment report, First
and REEP (DMAF funding recipients)
Greenhouse Gas
or design, engagement and implementation;
Benefits. Agreements with G
consultation, and a framework to track Community
-
WIP (Water Infrastructure Program) is completed to
-
Progress Update Design work for RBJ Schlegel Phase 2 is nearing completion with construction tenders being issued and prepared through spring. Construction is scheduled for summer and
fall 2021. Survivor Garden was deferred in 2020 dueCOVID; discussions have recently resumed with the donor and it is anticipated that this will move forward in 2021, with a tentatively
completion of end of 2021. Westwood Park is part of a bundle of parks projects that has been awarded fWestwood Park will have design and engagement completed in 2021, and it is anticipated
a tender for work will be issued and awarded in 2021. Construction may need to be deferred to 2022. Currently finalizing reporting and financial claim templates for the program. Preceding
conditions of the DMAF agreement are complete, including Nations preEmploymentConservation Authorityhave been executed. Approximately 9% of construction for the DMAFdate.
2028
2021
-
-
2
2
Timeline to Complete 2020 New date: 20 2020
t
ProjecManager Niall Lobley Parks & Cemeteries Nick Gollan Sanitary & Stormwater Utilities
Park;
; and
Management
RBJ Schlegel
urvivor Garden
Infrastructure ServicesImplementation of Significant Parks Projects Complete Phase 2 design work for plan, design and construct the Scomplete the upgrade to Westwood Park.Implementation
of the Federal Disaster Mitigation and Adaptation Fund (DMAF)Plan and execute stormwater management infrastructure projects across the city to leverage the DMAF grant funding and advance
the implementation of the 2016 Integrated Stormwater Master Plan.
1314
BPBP