HomeMy WebLinkAboutFIN-2021-21 - Middle Strasburg Trunk Sanitary Sewer Budget Increase
REPORT TO: Council
DATE OF MEETING: June 28, 2021
SUBMITTED BY: Gross, Hans, Director of Engineering Services, 519-741-2200 ext.
7410
PREPARED BY: Spere, Chris, Manager, Construction Engineering, 519-741-2200 ext.
7412
Hagey, Ryan, Director, Financial Planning and Reporting, 519-741-
2200 ext. 7353
WARD(S) INVOLVED: Ward 5
DATE OF REPORT: June 10, 2021
REPORT NO.: FIN-2021-21
SUBJECT: Middle Strasburg Trunk Sanitary Sewer Budget Increase
RECOMMENDATION:
That the budget for the Middle Strasburg Trunk Sanitary Sewer (MSTSS) be increased
by $6,000,000, funded by development charges.
REPORT HIGHLIGHTS:
The purpose of this report is to increase the budget for a project that is more complex
than initially thought due to significant groundwater and soils challenges
The financial implications are limited to an additional transfer from the development
charges reserve, which is completely funded by growth.
This report supports the delivery of core services.
BACKGROUND:
The Middle Strasburg Trunk Sanitary Sewer (MSTSS) is located in the southwest part of the
city, in the vicinity of the Bleams Road and Fisher-Hallman Road. The project is required to
develop different parcels of developer-owned land and is also key in delivering some public
pieces of infrastructure including a branch library, community centre and school.
The MSTSS project was identified as a fully growth-related piece of infrastructure through
previous development charges studies. It was also subject to a credit/refund agreement
with developers that wanted to advance its construction ahead of its 2022 construction
timing. An agreement was originally approved by Council in 2018 and then
updated/amended in 2019.
Construction of the MSTSS was publicly tendered by the City and was awarded in the spring
of 2020 at a cost of $15.5M. This was somewhat above the estimated cost of $14.7M, but
still within the acceptable range of 120% (or $17.64M) contemplated in the credit/refund
agreement. Based on the terms of the agreement, the developers had an option not to
*** This information is available in accessible formats upon request. ***
Please call 519-741-2345 or TTY 1-866-969-9994 for assistance.
proceed if the cost of the project was beyond $17.6M, but since it was being awarded at
$15.5M, the tender was awarded. Work began in 2020 and is expected to be finished by
the summer of 2021.
REPORT:
During the construction of the project, significant groundwater and soils challenges were
encountered. These challenges were well beyond what was expected based on the
information gathered from the boreholes drilled to test the underground conditions during
the design phase of the project. The boreholes did not indicate the extent of groundwater
and the frequent changes in soil type that have been experienced during construction and
the issues encountered could not have been reasonably anticipated at the time of tendering
the project.
The additional construction complexities have led to claims for extra payment by the
contractor in the range of $6M. The claims relate to the following activities and works by the
contractors and consultant, some of which will take place during June and July 2021:
Removal and disposal of additional marl soil at the south-west corner of Fischer
Hallman Road and Bleams Road including dewatering, removal and stockpiling on
site to dry the soil, removal and disposal off site, and replacing the excavated marl
soil with dry, compactable soil from the site.
Additional, time, labour and equipment to dewater and manage the groundwater
inflow during the installation of the sewer using both open cut trenching and tunneling
methodologies.
Changing the installation methodology of a section of sewer adjacent to the Huron
Natural Area from open-cut trenching as per the design drawings to tunneling due to
the extremely high inflow of groundwater.
Stand-by costs for the contractors to allow for additional examination and assessment
of the soils and groundwater conditions for the sewer to be successfully installed.
Additional consultant engineering costs for the additional assessment of soils and
groundwater conditions.
Claims of this size are exceptional, and well beyond a normal contingency budget for a
project of this scope. The nature and value of the claims have been reviewed by City staff,
the project design consultant and the contract administration consultant. The cost increases
proposed to continue and successfully complete the project are reasonable based on the
conditions experienced. Based on the soil and groundwater conditions experienced during
the MSTSS project, the developers involved with the credit/refund agreement are
anticipating significant cost increases for their proposed developments as well.
ditional unanticipated costs for the MSTSS be funded
by development charges . While the project is subject to a credit/refund agreement
with the developers, had the full costs of the project been known at the time of tender (now
estimated to be $21.5M), the developers would have had the option to not proceed with the
project, since it exceeded the cut-off price in the agreement ($17.64M). Now that the total
project costs well exceed the upper limit in the agreement, staff believe the only viable option
is to transfer the additional funds from the DC reserve.
STRATEGIC PLAN ALIGNMENT:
This report supports the delivery of core services.
FINANCIAL IMPLICATIONS:
The recommendation would result in a $6M transfer from the Development Charges reserve
to the Middle Strasburg Trunk Sanitary Sewer (MSTSS) capital account. Before considering
this transfer, the DC reserve is projected to have a balance of $8.8M at the end of 2021. If
the recommendation is approved, the ending balance would instead be $2.8M at the end of
the year. Further, the City is undertaking an update of its DC bylaw, so any change in the
DC reserve balance would be accounted for in the rates of the new DC bylaw (ie DC rates
would increase to account for lower than projected DC reserve balances).
COMMUNITY ENGAGEMENT:
INFORM This report has been
of the council / committee meeting.
PREVIOUS REPORTS/AUTHORITIES:
INS-18-012, Middle Strasburg Trunk Sanitary Sewer-Credit/Refund Agreement
Request
DSD-19-063, Middle Strasburg Trunk Sanitary Sewer-Credit/Refund Agreement
Request
APPROVED BY: Justin Readman, General Manager, Development Services