HomeMy WebLinkAboutCAO-2022-163 - 2022 Business Plan April Progress Report REPORT TO: Finance and Corporate Services Committee DATE OF MEETING: April 25, 2022 SUBMITTED BY: Kathryn Dever, Director, Strategy and Corporate Performance 519-741-2200 ext. 7370 PREPARED BY: Karen Cooper, Manager, Strategic and Business Planning, 519-741-2200 ext. 7817 WARD(S) INVOLVED: All DATE OF REPORT: April 7, 2022 REPORT NO.: CAO-2022-163 SUBJECT: 2022 Business Plan - April Progress Report RECOMMENDATION: For Information REPORT HIGHLIGHTS: The purpose of this report is to present the 2022 Business Plan - April Progress Report (Appendix A). Three projects have been completed in the first quarter of 2022, including; the Energy Efficiency Reserve Fund, Sustainable Urban Forest Strategy, and Reduce Waste Diverted to Landfills. All other strategic actions and business plan projects are on track to meet scheduled end dates at this time. There are no financial implications arising from this report. Community engagement included posting this report in advance of the committee meeting. This report supports BACKGROUND: The 2019-2022 Strategic Plan includes measurable, specific actions with a timeline for completion, and a commitment to measure and report on progress to Council and the public throughout the life of the plan. The annual business plan includes strategic plan actions and other high priority projects identified by Council and staff and progress is reported three times per year. *** This information is available in accessible formats upon request. *** Please call 519-741-2345 or TTY 1-866-969-9994 for assistance. REPORT: 2022 Business Plan - Overall Status The 2022 Business Plan comprises 12 strategic actions and 24 business plan projects. Of these 36 projects, 21 are to be completed in 2022, and 4 of these projects are already completed. Figure 1: Strategic Actions and Business Plan Projects scheduled for completion in 2022 Completed On Track Delayed / Not Started Ѝ ƦƩƚƆĻĭƷƭ ЊА ƦƩƚƆĻĭƷƭЉ ƦƩƚƆĻĭƷƭ ΛЊВ іΜ ΛБЊіΜ ΛЉіΜ Overall Status of Strategic Plan Actions As illustrated in the following chart,16 of the 25 actions in the 2019-2022 Strategic Plan are now complete as of April 30, 2022. Three actions have already been completed in 2022, with three other actions planned to be completed by the end of 2022. Six actions are to be completed in 2023, with work underway this year. 2022 Completed Strategic Actions Under the Environmental Leadership Goal, three strategic actions have been completed in 2022. All five of the strategic actions under this goal are now complete. has been recognized-list in a global ranking conducted by the Carbon Disclosure actions have led to this recognition as one of seven Canadian cities among 95 global cities including Copenhagen and Tokyo, who are taking the lead on climate change. Energy Efficiency Reserve Fund The strategic action to leverage the Energy Efficiency Reserve Fund and other resources to reduce consumption and emissions at city facilities and in city operations has been completed. Starting in 2019 and continuing through to 2022, savings from corporate projects have been captured and reinvested into the revolving fund to support new capital investments to achieve a Sustainable Urban Forest Strategy The strategic action to implement the Sustainable Urban Forest Strategy focused on eliminating the 2018 tree planting backlog by 2022 and establishing a tree canopy target by 2020. By 2021 staff had planted sufficient additional trees to eliminate the 2018 backlog. In 2015 Kitchener had an urban forest canopy of around 26% or 3,474 hectares of canopy cover. In 2019 tree canopy coverage increased to 27% or around 3,615 hectares. While these are excellent results and rank Kitchener among the cities with the highest urban canopy covers in Ontario, to maintain or improve this will take work. In January 2022, Council approved an Urban Forest Canopy target of 30% per ward by 2050 and city-wide target of 33% by 2070. Reduce waste diverted to landfills In 2019 City of Kitchener events featured volunteer-run waste diversion stations, encouraging attendees to divert waste into the proper stream (organics, recycling, or landfill). The diversion station concept was a success and was planned to continue in 2020. However, the onset of the pandemic saw cancellation of most events and eliminated opportunities to advance public awareness for waste diversion. A pilot project at the Kitchener Market was completed in 2022 on making waste receptacles more accessible. Relevant findings of these projects will be considered in future waste strategy initiatives. Overall Status of Business Plan Projects Sixteen business plan projects are to be completed in 2022, with 6 to be completed in 2023 and 2to be completed in 2026. All projects are on track at this time to meet scheduled completion. STRATEGIC PLAN ALIGNMENT: This report supports FINANCIAL IMPLICATIONS: Capital Budget The recommendation has no impact on the Capital Budget. Operating Budget The recommendation has no impact on the Operating Budget. COMMUNITY ENGAGEMENT: INFORM council / committee meeting. PREVIOUS REPORTS/AUTHORITIES: CAO-20-008 2021 Business Plan Year-End Progress Report and Recommended 2022 Business Plan Project List APPROVED BY: Michael May, Deputy CAO and GM, Community Services Department ATTACHMENTS: Appendix A: 2022 Business Plan Progress Report as of April 30, 2022 2022 Business Plan April Progress Report PART 1. Strategic Plan Actions To Be Completed (2022 and 2023 completion dates) 1.People-Friendly Transportation GOAL: Transform how people move through the city by making the transportation network safe, convenient, comfortable and connected. Strategic Plan Action Project Project Completion Statement Manager 1.2 Encourage and incentivize Bikeshare Program Ivan Balaban 2022 The Region-led project team prepared alternative modes of Implement a bikeshare service Transportation three reports for Regional Council in transportation by developing in which bicycles are made Services April to: and subsidizing a bikeshare available for shared use to the bylaw to permit e-scooter use on program by 2021. public in an effort to address Regional trails and some Regional roads; inform Regional Council of feasibility study to determine implementation planning for the most appropriate system. establishing commercial bike share and e-scooter share operations; and a risk assessment. Local municipal staff will bring forward companion reports to local City Councils. Request For Proposals planned for May, with launch anticipated for summer 2022. 1.3 Install a continuous and Protected Cycling Network Darren Kropf 2023 Phase one construction of separated protected cycling network that Connected to the Downtown Transportation bike lanes on Joseph and Water streets connects adjacent Install a continuous and Services was completed in 2021. neighbourhoods to the protected cycling network Phase two construction tender has downtown by 2022. that connects adjacent been awarded for separated bike lanes neighbourhoods to the on Queen, Cedar and Ontario Streets, downtown by 2022. and traffic diversion for neighbourhood bikeways on Lancaster and Chapel Streets. On-road wayfinding signs were installed along one route in fall of 2021, with the remaining installation to take place in 2022. The final phase of construction is on track for 2023. Planning is underway for a promotional campaign to encourage use of the new cycling infrastructure. 1.5 Develop a plan to create 1.5.1 Pedestrian-First Plan for Darren Kropf 2022 Gaukel Street between Charles and pedestrian-first streets Gaukel Street Transportation Joseph Streets has hosted numerous between Victoria Park and City Develop plans to prioritize Services informal gatherings, art animations Hall and pedestrians over other travel and events, including Christkindl which modes on Gaukel Street. brought pop-up retail to the space. Grant applications have been completed to secure funding to further transform Gaukel into a hub of activity and commerce. Charlie West condominium construction is nearing 1 Strategic Plan Action Project Project Completion Statement Manager completion, with the developer to restore the roadway into a pedestrian- oriented space. between the ION and Kitchener 1.5.2 Pedestrian-First Street Darren Kropf 2023 Following engagement of over 800 Market by 2022. Plan for Kitchener Market Transportation residents and businesses, an action Develop plans to prioritize Services plan with 15 actions in three themes pedestrians over other travel has been created. The themes are: modes between the Kitchener Create a definable "feel" to the Market Market ION station and District; Improve safety and comfort Kitchener Market. for getting around as a pedestrian, and; Make it easy to host events on Eby Street. Outdoor seating and planters have been purchased through grant funding for use on Saturdays when the Market moves outdoors. A year-long programming plan utilizing Eby Street as a pedestrian space is ready for launch in the spring. 2. Environmental Leadership Goal:Achieve a healthy and livable community by proactively mitigating and adapting to climate change and by conserving natural resources. Strategic Plan Action Project Project Completion Progress Update Statement Manager 2.2 Starting in 2019, leverage Leverage the Energy Efficiency Anna Marie 2022 Completed the Energy Efficiency Reserve Reserve Fund Cipriani Savings from corporate projects Fund and other resources to Leverage the fund to undertake Admin- continue to be captured and reduce consumption and energy efficiency retrofit Development reinvested into the fund to support emission at our facilities and in projects on City of Kitchener Services new capital investments that will our operations. assets and capture and reinvest achieve even greater energy operating savings to pay capital efficiencies. costs. 2.4 Implement the Sustainable 2.4.1 Tree Canopy Target Josh Shea 2022 Completed Urban Forest Strategy with a Review the current canopy Parks & Staff eliminated the 2018 tree planting focus on establishing a tree cover and set an achievable Cemeteries backlog in 2021 and an Urban Forest canopy target by 2020 and target based on best practices Canopy target of 30% per ward by eliminating the current (2018) as well as constraints such as 2050 was adopted by Council in tree planting backlog by 2022. land availability, quality of soil, January 2022. etc. in order to guide ongoing and future investment in tree planting, protection and maintenance. 2.5 Reduce waste diverted to Waste Diversion Strategy: Anna Marie 2022 Completed landfills by implementing new Increase Waste Diversion in Cipriani A pilot project at Kitchener Market was Our Public Spaces and Events completed on making waste 2 Strategic Plan Action Project Project Completion Progress Update Statement Manager diversion programs at our Expand the Waste Diversion Admin receptacles more accessible for all. facilities and events by 2021. Station to all City-run events Development Relevant findings will be considered in with large volunteer Services future waste strategy initiatives. involvement, and evaluate expanded waste diversion stations at events, parks and public facilities. 3. Vibrant Economy GOAL: Build a vibrant city by making strategic investments to support job creation, economic prosperity, thriving arts and culture, and great places to live. Strategic Plan Action Project Project Completion Progress Update Statement Manager 3.2 Foster the creation of a 3.2.2 Incubator, Accelerator Cory Bluhm 2023 A partnership with the University of city-wide network of and Co-Working Space Economic Waterloo (UW) for the Innovation Arena incubators, accelerators and Network Development was announced in 2020; staff are co-working spaces by Lease all spaces in the working with UW on design, permits completing the buildout of 44 Creative Hub, explore the and approvals; site plan approval is Gaukel in 2019, advancing potential to facilitate a Food anticipated in spring 2022, with an work on a Creative Hub and Incubator with a business case expected 2023 opening date. Staff are undertaking business cases in pending, and explore also supporting UW in securing 2019-2021 for the food partnerships for the additional funding. manufacturing and development of City Council approved the business case health/med-tech industries. manufacturing and to establish a new incubation space at 2 health/med-tech industry King Street west to support businesses incubators. advancing the UN Sustainable Development Goals (SDGs). Staff continue to explore funding opportunities to support a Food Incubator; business cases will be prepared for Council approval in 2022. 3.4 Complete a comprehensive City-Owned Property Review Brian 2022 Initial focus has been on identifying review of city-owned Complete a comprehensive Bennett supportive housing sites. Land properties by 2020 to review of city-owned Economic assessment criteria have been determine how they could be properties by 2020 to Development established by staff, and a effectively used to advance city determine how they could be comprehensive review of all City-owned strategic objectives. effectively used to advance properties is in process. city strategic objectives. 3 Strategic Plan Action Project Project Completion Progress Update Statement Manager 3.5 Develop a vision for 3.5.1 Downtown Vision and Brian 2023 Council endorsed the process to downtown Kitchener and City-Owned Property Brought Bennett develop a new downtown vision. A call continue to position downtown to Market Economic for community members to be part of a Kitchener as a leading Develop a vision for Development Downtown Community Working Group destination for redevelopment downtown Kitchener and was launched in late March. opportunities, with at least one continue to position A Request for Proposal is in progress to new city-owned property downtown Kitchener as a hire a consultant to guide the brought to market by 2020. leading destination for Community Working Group and staff in Finalize the Innovation District redevelopment opportunities, engaging the broader community in the (Bramm Yards) Master Plan by with one new city-owned development of the vision. It is 2021 and the Civic District property brought to market anticipated one city property will be Master Plan by 2022. by 2022. brought to market in 2022. 3.5.2 Innovation District Cory Bluhm 2023 In addition to UW Innovation Arena (Bramm Yards) Master Plan Economic noted in 3.2 above, a broad Master Plan Finalize the Innovation District Development will be developed in concert with (Bramm Yards) Master Plan by community engagement for developing 2022. the downtown vision. 3.5.3 Civic District Master Cory Bluhm 2023 The visioning exercise will be completed Plan Economic in concert with community engagement Finalize the Civic District Development in developing the downtown vision. Master Plan by 2022. 4. Caring Community GOAL: connection by providing welcoming community spaces & programs; better engaging, serving & supporting our diverse populations & helping to make housing affordable. Strategic Plan Action Project Project Completion Progress Update Statement Manager 4.4 Better utilize existing 4.4.1 Mill Courtland Mark 2022 A consultant is completing a needs facilities, provide relevant Community Centre Expansion Hildebrand assessment and business case to programming at community Business Case Neighbourhood outline requirements for an addition centers, and support equitable Complete a needs assessment Programs & to Mill Courtland Community Centre. distribution of leisure programs and business case to Services The business case is to be completed and resources across determine the requirements in the third quarter of 2022. neighbourhoods. Start work on for an addition to the Mill the Mill Courtland Community Courtland Community Centre. Centre expansion by 2020 and the Rosenberg Community 4.4.2 New Rosenberg Mark 2026 The Minister of Education announced Centre by 2021. Community Centre/School Hildebrand that funding for the construction of a Business Case Neighbourhood school in the South Estates/ With the Catholic School Programs & Rosenberg subdivision has been board, complete a needs Services approved. The anticipated assessment and business case construction period is 2023 to 2026. to determine the requirements for a joint community centre/school in the Rosenberg area. 4 Strategic Plan Action Project Project Completion Progress Update Statement Manager Complete the Huron Brigadoon 4.4.3 Huron Brigadoon Area Mark 2022 The Huron Brigadoon school / Community Centre by 2021 School / Community Centre Hildebrand community centre project is on track Construction Neighbourhood and construction is ongoing. Construct a joint Programs & Negotiations for an operating school/community centre in Services agreement between the City and the Huron Brigadoon area, in School Board are pending. The facility partnership with the Waterloo is expected to open early in the fourth Region District School Board. quarter of 2022. Complete an Open Space 4.4.4 Open Space Strategy Mark Parris 2023 Engagement with stakeholders, Strategy by 2021. Develop an open space Parks & residents and community members is strategy to explore the value Cemeteries progressing, having heard from over of open spaces, how they 2000 people to date. The engagement function, are planned, focused on the vision for where and maintained, and managed, how much parkland the City should and including a review of have, using a deliberate, relationship- permitted uses in parks. building approach, and an equity, diversity and inclusive approach. The Spaces component of the Open Space Strategy addresses the quantity of park and open spaces and will be presented to Council in June 2022. The Places component shifts focus to the quality of park and open spaces and work will continue through to mid-2023. 4.5 Engage a broad cross-Arts and Culture Plan Emily Robson 2023 A Terms of Reference and stakeholder section of the community Develop a new and inclusive Economic consultation is under development in including the arts and creative Arts and Culture Plan by Development partnership with the other area industry sector and multi-engaging a broad cross-municipalities. cultural communities to section of the community develop an inclusive arts and including the arts and creative In March 2022 the City launched a culture Plan by 2021. industry sector and multi-year-long partnership with the cultural communities. Bloomberg Centre for Cities at Harvard University as part of the Bloomberg Harvard City Leadership Initiative to support the development of new Arts and Culture Plan. An initial kick-off event with 40 local arts and culture leaders, stakeholders and staff was carried out, and a smaller team has been established to refine the framework and develop potential initiatives. 5 5. Great Customer Service GOAL: Strategic Plan Action Project Project Completion Progress Update Statement Manager 5.4 Set clearly communicated Set and Communicate Service Jana Miller 2022 Levels for the first areas identified in and specific service levels for Levels Corporate the strategic plan are on track to be frequently asked about or Set clearly communicated and Customer complete by the end of 2022. accessed City services, specific service levels for Service including: tree maintenance, frequently asked about or Work is underway to determine how parking, property standards accessed City services, service levels will be shared via a new complaints, snow clearing and including: tree maintenance, Report A Problem widget on the grass cutting by 2022. parking, property standards MyKitchener portal. Next steps complaints, snow clearing and include a workshop with Corporate grass cutting by 2022. Leadership Team to prioritize setting service levels for all City services 6 PART 2: Status of Business Plan Projects by Department Community Services Project Manager Completion Progress Update A consultant has been hired to conduct a station BP01 Fire Station 8 Location Study Helena Foulds 2022 location study for Fire Station 8, as well as review all Identify potential sites for Fire Administration - fire response zones. Staff plan to bring a report to Station 8, including an analysis of Community Council with recommendations in Q3 2022. response times based on an eight-Services station model. Corporate Leadership Team and Council endorsed the BP02 City Hall Customer Service Counter Jana Miller 2022 vision for a centralized City Hall service centre and Centralize all in-person services at Corporate started communicating the customer service vision City Hall to one service counter Customer Service with staff. Work is underway to gather technical and located on the main floor, including design requirements and an internal change the addition of a back-end work management plan is being developed. Request for area to provide customer service Proposal for an architect is in progress. Staff are support. expected to move to a temporary service centre in the Conestoga Room on the main floor of City Hall by June 2022. The planned staff update to Corporate Leadership BP03 Budd Park Strategy Kim Kugler 2022 Team did not occur in January due to competing Identify potential sites and Sport priorities, and is now planned for April 2022. Next estimated costs to relocate the steps include bringing a report to Council for further recreational assets at Budd Park direction. and compare the costs to the economic benefits of using the Budd Park for employment lands. BP04 Cameron Heights Pool Feasibility Kim Kugler 2022 Initial investigation of the existing facility and amenities has been completed by the consultant. Study Sport Conceptual block drawings are being reviewed by City Collaborate with the Waterloo and School Board staff for feasibility. Region District School Board to determine the renovations and estimated costs to isolate the pool operation from the school operation to preserve a recreational asset in the downtown core. BP05 Indoor Recreation Complex at RBJ Chris Oke/Kim 2022 The consultant leading the business case has engaged Schlegel Park Business Case & Kugler internal stakeholders, and staff and the consultant completed site tours of comparator facilities, with an Conceptual Design FM/Sport update provided to Corporate Leadership Team. The Engage community business case will be completed in May 2022, and a residents/stakeholders in a needs Request for Proposal for the detailed design and assessment and business case to construction consultant will be issued June 2022. determine the elements to be included in the new pool. BP06 Ice Demand Study Jeremy Dueck 2023 The work will resume in 2023 after sport groups are able to operate a full season without restrictions. The Evaluate ice user needs and trends Sport COVID-19 pandemic has had a direct impact on user for ice time to determine the timing groups and demand for ice. of a new arena. 7 Corporate ServicesProject ManagerCompletionProgress Update Demographic Data Collection Phase 1 of the Demographic Data Collection BP07 Elin Moorlag Silk 2022 Strategy Strategy is well underway in the first half of 2022. EARII Standardized demographic data is now being Develop a strategy for the collected in the following areas: collection of community 1. Engage Kitchener online surveys demographic data to guide the 2. Volunteer applications identification and removal of 3. Applications for Advisory Committees and Boards systemic barriers in City programs 4. Customer Service satisfaction surveys and services. 5. Community Centre facility rentals 6. Community Grant applications Staff are currently working to implement data collection for delegates to Council, applications for all City of Kitchener grants, and applications for all job opportunities at the City; these initiatives are expected to be implemented by the second half of 2022. Launch of the Grant Program for The RISE Fund was successfully launched in February BP08 Elin Moorlag Silk 2022 Black, Indigenous & Racialized and the first application review period from EARII groups (RISE Fund) February 14 to March 17 saw 17 applications Implementation of a new totaling over $150,000 in requested funds. The community grant program for Equity and Anti-Racism Advisory Committee, which Black, Indigenous and Racialized serves as the selection committee for the RISE Fund, groups, as a tangible deliverable of is currently reviewing applications and will make the Corporate Equity & Anti-Racism recommendations to allocate the available funds. Strategy. Development Services Project Manager Completion Progress Update BP09 New Greenhouse Gas Emissions Anna Marie 2022 Throughout 2022, staff are pursuing projects that Reduction Target(s) Cipriani reduce corporate GHGs; developing target(s) for the next Corporate Climate Action Plan; and, identifying Administration- The City of Kitchener met the potential pathways to achieve the target(s). Development previous Corporate Climate Action Services Plan (CorCAP) target of 8% absolute GHG reduction. Through this new project, a new/next generation CorCAP will be developed. Financial Services Project Manager Completion Progress Update BP10 Budget System Implementation Ryan Hagey 2023 Specifications and tender document prepared, and the Replace the existing Budget System, project is planned to start in Q2/Q3 of 2022. Financial Planning which was developed in-house more than 20 years ago, with an & Reporting external software solution. 8 Financial ServicesProject ManagerCompletionProgress Update BP11 Climate Event Sensor Jason Winter 2023 Staff are awaiting a final decision regarding a grant Implementation application which would fund this opportunity. If Asset Management Investigating and initial successful, implementation will include installation of & Business implementation of climate sensors a number of weather stations installed throughout the Solutions throughout the City to gain climate summer and data collected for modeling and trending related data for modelling, real- by Q3 of this year. time analysis, and emergency response. BP12 Asset Management Planning Jason Winter 2023 Final reviews are underway for the Water asset Develop and publish two key asset management plan, expecting to have it finalized by the Asset Management management plans for Facilities end of April. Asset management plans are also being & Business and Water categories to support completed for both roads and sidewalk infrastructure, Solutions adherence to O. Reg 588/17 with expected completion by June 2022.The team is currently working with FM to scope their asset management plan. The end date for the entire project has been extended to 2023 from 2022. BP13 Concur Invoice Automation Lisa Dueck 2023 Currently gathering project requirements including Invoice management solution to pricing and resourcing, with a tentative project start Financial fully digitize AP processes. Includes date in fall 2022. Operations invoice capture, tracking, approvals and enhanced reporting for spend analysis. BP14 E-invoices for Miscellaneous Lindsey Taylor 2022 The e-invoicing project is progressing with work Receivables underway. Collaboration with staff to refine the Revenue Customers are frequently solution will continue in the coming months with the requesting e-invoices for goal to implement the e-invoicing solution in Q4 2022. Miscellaneous Receivables which represent services that are financial system (SAP). Examples of services billed through miscellaneous receivables include Direct Detect for alarm monitoring, Parking and Cemetery sales. Property tax and utility accounts are not included in miscellaneous receivables. Completion of this project will allow customers to receive invoices by e-mail. BP15 Mobile Time Entry Jason Winter 2022 Great progress has been made during Q1 of 2022 with the overall solution set. Collaboration underway to Implement mobile time entry for Asset Management understand and implement solution for the operations, eliminating the need & Business complexities of many business processes. On track for for paper-based timesheets. Solutions first phase of implementation in fall of 2022. Development Charge (DC) & DC Study and Bylaw posted online in March and BP16 Ryan Hagey 2022 Community Benefits Charge (CBC) presented to Council in April. Report will be Financial Planning Studies considered by Council in May, and pending approval, & Reporting new rates will be effective July 1, 2022. charges study and investigate whether the City should prepare a community benefits charge study. 9 Financial ServicesProject ManagerCompletionProgress Update BP17 Long Term Financial Plan Ryan Hagey 2022 Investment policy completed and approved in April Implementation 2021. Work underway to consider which additional Financial Planning policies to move forward in 2022 (e.g., debt policy). Implement/consider recommended & Reporting actions identified as 2020 items in the Long-Term Financial Plan. BP18 Point of Sale and Expansion of Saleh Saleh 2023 Expansion of Payment Options for Utility and Property Tax customers went live February 2021. The next Payment Options Revenue phase of the project will see expansion of payment Replace the existing Point of Sale options for Business Licensing, Building Permit, system, which is past its life cycle, Planning and Miscellaneous Receivable services with a and expand payment options for planned go-live for fall of 2022. The Point-of-Sale part various services. of the project is planned for 2023 to potentially align with the proposed centralized City Hall customer service counter. Infrastructure Services Project Manager Completion Progress Update Project charter and project plan have been developed BP19 Water Infrastructure Program (WIP) Bu Lam 2023 and will be reviewed and approved by the Steering Undertake an assessment of the Sanitary & Committee in April 2022. Project Advisory Team will Water Infrastructure program Stormwater be compiling data and performing analyses originally completed in 2017 and Utilities throughout 2022 to support the WIP review. review for the next 5 years. This will inform the long-term maintenance and renewal strategy for water infrastructure (water, sanitary and stormwater) l to ensure continued safe, reliable and efficient service delivery. BP20 Sustainable Urban Forest Strategy Josh Shea 2023 Council endorsed 10-year capital funding to extend work with REEP Green Solutions. Funding has been (SUFS) Implementation Parks & doubled and work is targeted to support the Cemeteries Continue to implement the SUFS by objectives of the Tree Canopy Target. providing grant funding to REEP Green Solutions to partner on Planning has been initiated for the planting of trees in private tree planting and parks as part of the 2022 and 2023 work program. stewardship and planting 400 trees in parks before the end of 2023 to replace trees lost through EAB, storms and other events. The first quarter of 2022 focused on key initiatives to BP21 Facilities Infrastructure Program Beatrice Powell 2022 further support and drive evidence-based facilities Conduct a comprehensive review of Facilities capital planning. Facilities capital budget re- facility infrastructure needs to Management structuring, which supports a needs based / state of incorporate building condition good repair approach to capital project planning is assessments, sustainability complete. An FCM grant will support development of opportunities, and accessibility an asset management framework specific to facilities. needs to identify current gaps and In combination with facilities asset data, the inform long-term maintenance and framework will support Provincial requirements for capital improvement strategies to Asset management planning for municipal address the infrastructure deficit. infrastructure. 10 Infrastructure ServicesProject ManagerCompletionProgress Update Rehabilitation of City Hall Outdoor Construction continued throughout 2021 and Phase 1 BP22 Lynda Stewart 2022 Spaces Construction Phase 1 and of Carl Zehr Square construction will be completed in Facilities June 2022. Phase 2 work on Duke and Young Streets Phase 2 Management will begin in spring 2022 and conclude by late fall Complete construction associated 2022. with the rehabilitation of City Hall Outdoor spaces. BP23 Implementation of Significant Parks Niall Lobley 2022 RBJ Schlegel Phase 2 continues with the washrooms Projects nearing completion and groundwork beginning on Parks & Phase 2 parkland infrastructure. Complete construction of RBJ Cemeteries Schlegel Park phase 2, Westwood Westwood Park and Brubacher Parks are at tender. Park and Brubacher Parks. Parkland improvements at Wilson are being implemented through the Montgomery Creek works, Tender and award work at Alpine, and designs are completed at Alpine, Vanier and Vanier/Traynor/Wilson and Shoemaker parks for construction in 2022. Shoemaker Parks. Public Engagement has begun for Initiate engagement at Oaten/Fergus/Idlewood and Kinzie Parks. Oaten/Fergus/Idlewood and Kinzie Parks. Implementation of the Federal Nick Gollan Work is progressing as planned on WIP utility BP24 2026 Disaster Mitigation and Adaptation replacement projects (full reconstructions) and Sanitary & Fund (DMAF) engagement continues on multiple parks and Stormwater Plan and execute stormwater stormwater facility projects. Rehabilitation of Utilities management infrastructure projects Montgomery Creek near Wilson Park will commence in across the city to leverage the DMAF 2022, and current work in Shoemaker Creek will be grant funding and advance the completed later this year. Additionally, design work is implementation of the 2016 planned to commence for 10+ creek and pond projects Integrated Stormwater Management in 2022. Master Plan. 11