HomeMy WebLinkAboutDSD-2023-096 - Biehn Drive and Sanitary Trunk Sewer Environmental Assessment
Development Services Department www.kitchener.ca
REPORT TO: Committee of the Whole
DATE OF MEETING: March 20, 2023
SUBMITTED BY: Carlos Reyes, Interim Director Engineering, 519-741-2200 ext. 7974
PREPARED BY: Eric Riek, Project Manager, 519-741-2200 ext. 7330
WARD(S) INVOLVED: Ward 4
DATE OF REPORT: March 14, 2023
REPORT NO.: DSD-2023-096
SUBJECT: Biehn Drive and Sanitary Trunk Sewer Environmental Assessment
RECOMMENDATION:
That Council directs staff to complete further studies to update the Biehn Drive and
Trunk Sanitary Sewer Extension Class Environmental Assessment - Environmental
Study Report , prepared by BT Engineering, dated January 18, 2023; and,
That Council directs staff to complete one additional consultation to be scheduled
once the additional studies have been completed; and,
That Council directs staff to use the remaining balance of the budget approved in
2020 for this EA to complete the additional work; and further,
That staff reports back to Council with an updated Biehn Drive and Trunk Sanitary
Sewer Extension Class Environmental Assessment (EA) Environmental Study Report
in late 2023 or early 2024.
REPORT HIGHLIGHTS:
The purpose of this report is to answer questions raised at the February 13, 2023
Community and Infrastructure Services committee and to provide recommendations for
additional investigation and consultation (Geotechnical, Hydrogeological and
Transportation).
The key finding of this report is the recommendation of additional investigation and
consultation to be completed and to update the Biehn Drive and Trunk Sanitary Sewer
Extension Class Environmental Assessment (EA) Environmental Study Report and
Preliminary Design Report with the findings of those studies, which would typically take
place after filing the EA.
The financial implications are Biehn Drive and Sanitary Trunk Sewer Extension was
included in the Development Charge Background Study, 2019. This project has full-
funding available as of 2022 in the capital forecast and is fully funded by Development
*** This information is available in accessible formats upon request. ***
Please call 519-741-2345 or TTY 1-866-969-9994 for assistance.
Charges. Remaining balance of the budget approved by Council in 2020 is required to
complete additional investigation.
Community engagement included two virtual public information centres with the first
th
meeting taking place April 20, 2021. The second virtual public information centre took
th
place on November 17, 2021. In addition, the project was presented to the Kitchener
th
Environmental Committee on June 17, 2021 and October 21, 2021. The project was
presented to the Regional Environmental Committee on November 29, 2021. Lastly, the
project was presented to Community and Infrastructure Services Committee on
February 13, 2023. One additional Public Information Centre is proposed once
additional investigation is completed (late 2023/ early 2024).
This report supports the delivery of core services.
EXECUTIVE SUMMARY:
The City of Kitchener (City) has undertaken a Schedule C Municipal Class Environmental
Assessment (EA) Study to develop a transportation plan for the extension of Biehn Drive
westerly to the Robert Ferrie Drive extension in the City of Kitchener. The Biehn Drive
extension will include municipal services including a trunk sanitary sewer, storm
sewer/ditches and watermain.
The following problem/opportunity was identified as part of the EA:
Future development within the Doon South and Brigadoon communities requires a defined
alignment for the extension of Biehn Drive to Robert Ferrie Drive as part of the area road
network and to accommodate municipal services. The sanitary sewer network must connect
to Biehn Drive.
To address this problem, the Study has developed and evaluated alternatives for the
alignment of the Biehn Drive extension, intersection locations/type and municipal services
while minimizing environmental, social, and cultural impacts of the project. Biehn Drive is a
Major Collector Road in the City of Kitchener Official Plan. The previous sanitary sewer
network has been constructed to accommodate the future service areas to connect directly
to Biehn Drive. No other alternative exists for the sanitary sewer network other than to
connect to Biehn Drive.
As a result of questions and concerns raised at the Community and Infrastructure Services
th
Committee meeting on February 13, 2023, staff are recommending the following studies
be completed to support the decisions made and refine the preferred solution of Council
consideration of the Biehn Drive and Sanitary Trunk Sewer Environmental Assessment (EA)
Environmental Study Report:
Scoped Environmental Impact Study to support geotechnical work (typically
completed at detailed design);
Detailed geotechnical and hydrogeological study to determine sewer installation
method and impacts to groundwater (typically completed at detailed design);
Complete an update to the Doon South Community and Broader Traffic Study (last
completed in 2016) to confirm what future traffic projections would look like with or
without Biehn Drive extension.
In addition to the studies mentioned above, staff proposes one additional Public Information
Centre to take place prior to reporting back to Council in Winter 2023/2024. After this
additional consultation is completed, the preferred solution will be confirmed taking into
consideration the results from the addition investigation, input and comments received from
the review agencies, Indigenous communities, and the Public, and after the evaluation of
the net environmental effects.
BACKGROUND:
Since the mid-
Brigadoon areas in the City of Kitchener have planned for area development and evolving
transportation needs. Several planning documents including the Official Plan and
Transportation Master Plan (TMP) have identified the need to extend Biehn Drive westerly
to the Robert Ferrie Drive extension and ultimately to Strasburg Road.
The Biehn Drive Extension would be a major collector road, as identified in Schedule B of
the Ci
and from the Brigadoon community and would help mitigate cut-through traffic on local
streets within the community. A collector road collects traffic from local roads within the
community and provides connectivity to high tier arterial roads including Strasburg Road.
Future development within the Doon South and Brigadoon communities requires a defined
alignment for the extension of Biehn Drive to Robert Ferrie Drive as part of the area road
network and to accommodate municipal services. The sanitary sewer network must connect
to Biehn Drive.
To determine the road alignment, this Study has considered the natural, social environments
and the future land use in the Study Area. The extension of Biehn Drive and the associated
municipal servicing has been a longstanding part of the integrated plan for the Brigadoon
neighbourhood.
The planned extension will improve local access to Strasburg Road to safely and reliably
accommodate all modes of transportation including vehicular, pedestrians, and cyclists, and
provide access to potential future transit. Defining the future road and municipal servicing
plans concurrently allows subsequent land use plans to be completed by developers by
providing certainty in the horizontal and vertical alignment of the municipal street Right-of-
Way (ROW).
The EA Study provides the opportunity to: improve accessibility to the local community by
providing additional network links; define a multi-modal transportation plan to support travel
within the local neighbourhoods; accommodate the required and previously planned sanitary
sewer extension; and allow development to proceed on lands that currently require the
roadway ROW plan to be defined prior to developing the land use plan.
REPORT:
Municipal Class EA Process
Class EA 2015. This document specifies the procedures required to plan specific road
projectsaccording to an approved provincial planning process.
The Class EA process was undertaken in a series of phases commencing with problem
identification and culminating in the filing of this Environmental Study report (ESR).
The Class EA process includes an evaluation of all reasonable alternatives and the selection
of a preferred alternative(s) with acceptable effects (including avoidance and mitigation of
any residual adverse effects) on the natural and social/cultural environments.
The Municipal Class EA process involves five phases:
Phase 1: Identify the Problem
Phase 2: Alternative Solutions
Phase 3: Alternative Design Concepts for the Preferred Solution
Phase 4: Environmental Study Report
Phase 5: Implementation
Current Environmental Assessment Status
Due to concerns received from the Public, staff is proposing to advance additional
investigation and consultation earlier in the process to update and file the Environmental
Study Report with the Ministry of Environment, Conservation and Parks for the mandatory
30-day review period which corresponds to Phase 4 in the Municipal Class EA process (See
Figure 1).
Figure 1 Municipal Class EA Process Map
Council Discussion and Questions
th
The following questions were raised at the February 13, 2023 Community and
Infrastructure Services Committee Meeting:
1. Question/Concern: Alternative 4 scoring review was completed as requested,
however, no changes were made to the Environmental Study Report. Response:
While alternative 4 scored the highest for Natural Environment, that is only one factor
out of six (6) that is considered. The evaluation considered all natural, social, cultural
environmental performances as well as cost and transportation. It is typical that a
preferred alternative in an Environmental Assessment would be a best-balanced
solution providing reasonable transportation and municipal services while minimizing
environmental effects and costs.
In this technical evaluation Alternative 1 was considered a better-balanced solution
considering all trade-offs. The overall scores of the competing alternatives is shown
below (Figure 14-from Environmental Study Report) and the colour of each factor
group illustrates where each option scored points in each criteria. Alternative 4 has
the largest green (natural environment) performance as shown in the figure but
poorer performance in other factor groups.
Figure 2 MATS Evaluation Ranking results Included in the ESR
Sensitivity testing was also completed to validate or test the weighting exercise which
is explained in detail below.
To evaluate the alternatives using the short-listed criteria, the Evaluation Team
members rated each global factor and sub-factor based on their knowledge and
experience. It is noted that every person assigning weights may have different
expertise (i.e. the Evaluation Team consists of a diversified team of professionals
with varied backgrounds) and may allocate slightly different scores between each
member. The Evaluation Team assigned percentage weights to each global factor
and sub-factor were assigned by each project team member based on the findings
of sub-studies, public comments, and whether the performance or impacts would be
short term or long term.
Their individual weights are then averaged to determine the Evaluation Team weight
for each global factor and sub-factor shown above. The sensitivity testing program
was a method to assess the range of perspectives in the group and to test if
judgements of individuals had a large variance or not. The testing considered the
outcome of each factor group using the highest or lowest perspective of importance
of anyone in the group. In this study the Alternative 1 was a robust solution ranking
first in every test.
Table 5 on Page 42 of the Environmental Study Report is shown below for reference.
Table 1 Sensitivity Testing Included in the ESR
What this demonstrates is that no one on that evaluation group considered
Alternative 4 as the preferred alignment alternative.
2. Question/Concern: Method of construction for extending sanitary trunk sewer and
watermain (open-cut, directional drilling, micro-tunneling, etc.). Response: Staff are
recommending proceeding with a detailed geotechnical study which is required
typically reaquired at and budgeted for in the detailed design stage. By completing
this study in advance, the following questions will be answered:
Method of sewer construction
Impacts to groundwater/ flooding concerns
To complete this geotechnical investigation, a scoped Environmental Impact Study
must be completed in advance (Spring/Summer 2023). Limited tree removal will be
required to access the lands with the B57 drill rig, see photo below for reference. Tree
stst
removal cannot take place during the bird nesting window (April 1 to August 31);
therefore, the geotechnical investigation will begin in September 2023.
B57 Drill Rig
3. Question/Concern: Does Biehn Drive need to be extended? Response: There have
been numerous studies completed to support the need for extending Biehn Drive
from the current terminus to Robert Ferrie Drive which are outlined in the
Environmental Study Report. Despite all the previous studies recommendations to
extend Biehn Drive, there are still questions about the need for the road extension.
In response to these questions and concerns, staff proposes to complete an update
to the Doon South Community and Broader Traffic Study (last completed in 2016)
to confirm what future traffic projections would look like with or without Biehn Drive
extension.
4. Question/Concern: Alternate routes for trunk sewer or alternative servicing options.
Response: The Biehn Drive trunk sewer will service a large area of the City (128.9
hectares including rural, residential, and agricultural lands) by gravity, see Figure 2
below for reference. This equates to approximately 2000 dwellings. Servicing by
gravity is the most efficient and cost-effective means of providing a sanitary outlet for
new construction.
The only alternative to gravity drainage is to provide a pumping station that would
pump sewage (via a forcemain) from a low point on the west side of the Provincially
Significant Wetland (PSW) to the existing trunk sewer on Biehn Drive. This forcemain
would either be installed under the wetland or follow local streets (Robert Ferrie Drive
to Caryndale Drive to Biehn Drive).Pumping stations are very expensive and carry a
perpetually high operating and maintenance cost for the City. Further, with the
changes from Bill 23,
Development Charge funds to ensure the money invested in new infrastructure is
done so responsibly and as efficiently as possible.
Figure 2- Biehn Drive Sanitary Sewer Catchment Map
Recommended Strategy and Next Steps
1. Scoped Environmental Impact Study which will include field investigations to be
completed in the spring and summer of 2023 to review existing mapped natural
features and identify additional features and constraints that should be considered
during the evaluation of alternative designs. This site investigation will document
the following beyond general natural heritage constraints: spring plants, tree
assessment, spring birds and frog call surveys, bat roosting screening, incidental
wildlife observation, and Species at Risk (SAR) potential habitat assessment. An
additional field visit will be completed in the summer of 2023 to ensure that existing
conditions are captured across multiple seasons.
A Scoped Environmental Impact Study (EIS) will be prepared which will summarize
existing conditions including constraints and opportunities in the Study Area, an
assessment of potential impacts, mitigation measures, construction timing windows
and a list of future studies, as well as permits and approvals that may need to be
obtained prior to additional geotechnical investigations. The report will inform the
design team of natural heritage considerations in their selection of the preferred
solution and design. The report will be distributed to MECP and GRCA as required
in support of permits and approvals
2. Complete Geotechnical/Hydrogeological investigation which will advance six (6)
boreholes to a depth of 8 metres within the wetland limits. Three (3) boreholes will
be converted to monitoring wells to measure groundwater fluctuations. The
boreholes will be advanced using a track-mounted drill-rig equipped with continuous
flight solid/hollow stem augers and split spoon (SPT) sampling equipment.
3. Complete an update to the Doon South Community and Broader Traffic Study (last
completed in 2016) to confirm what future traffic projections would look like with or
without Biehn Drive extension.
4. Additional Consultation in Winter of 2023/2024
5. Update the Environmental Study Report taking into consideration the results from
the additional investigation and consultation.
6. Final presentation of Environmental Study Report to Council in late 2023 or early
2024
STRATEGIC PLAN ALIGNMENT:
This report supports the delivery of core services.
FINANCIAL IMPLICATIONS:
Capital Budget The recommendation has no impact on the Capital Budget. Funds are
currently available from Development Charges.
Operating Budget The recommendation has no impact on the Operating Budget.
In 2020, Council approved $565,000 for the Biehn Drive and Sanitary Sewer Extension -
Municipal Class EA and Preliminary Design. On December 23, 2020, Council approved P20-
043 (Professional Services Class EA & Preliminary Design for Biehn Drive Extension and
Sanitary Trunk Extension (Current Terminus to Robert Ferrie Drive) with a total budget of
$369,817.36. Staff recommends the use of the remaining balance ($187,486.83) to
complete the additional work.
COMMUNITY ENGAGEMENT:
INFORM
the council / committee meeting.
CONSULT Community engagement included two virtual public information centres with
the first meeting taking place April 20th, 2021. The second virtual public information centre
took place on November 17th, 2021. In addition, the project was presented to the Kitchener
Environmental Committee on June 17th, 2021 and October 21, 2021. The project was
presented to the Regional Environmental Committee on November 29, 2021. Lastly, the
project was presented to Community and Infrastructure Services Committee on February
th
13, 2023.
One additional Public Information Centre is proposed to take place in Winter of 2023/2024
after the additional studies are completed.
PREVIOUS REPORTS/AUTHORITIES:
September 1989, City Council approved the Brigadoon Community Plan. The Community
Plan was processed concurrently with amendments to the Official Plan which established
a collector and arterial road network for the Community. The importance of connecting
the Brigadoon Community to Strasburg Road was recognized and three collector road
connections were proposed at that time including the extension of Biehn Drive. Approved
transit routes included Biehn Drive, Strasburg Road and Huron Road. The Biehn Drive
extension has been carried forward in all subsequent versions of the City of Kitchener
Official Plan.
February 1994, McCormick Rankin on behalf of the City of Kitchener completed the report
-
recognized the need to comprehensively plan a road network to accommodate growth
associated with a large geographic area. The process was undertaken in the form of the
Environmental Assessment Act. The report recommended several interrelated
transportation corridor network improvements and reaffirmed the need for the Biehn Drive
extension. Kitchener Planning and Economic Development Committee approved the
report and further recommendations dated June 20, 1994 which among other matters,
directs an amendment to the Kitchener Official Plan to incorporate the collector road
network which includes Biehn Drive.
The Brigadoon Community Plan was updated and approved by Kitchener City Council
on June 29, 2004. The updated Community Plan provides for the extension of Biehn
Drive to Strasburg Road and recognizes Strasburg Road as a 26 metre wide secondary
arterial road.
Drive extension is identified as a major community collector street. Biehn Drive is shown
as extending in a southwesterly direction and connecting to Strasburg Road.
City Planning Staff Report (CSD-14-037) prepared in support of the Official Plan
Amendment (OPA) and environmental assessment (EA) for the Robert Ferrie Drive
extension (June 2014) includes the following conclusion:
the traffic and transportation needs in the Brigadoon and Doon South communities the
Transportation studies done as part of the Integrated EA and OPA process confirmed
that the extension of Biehn Drive is necessary to meet the current and projected
transportation needs of the Brigadoon/Doon South Communities. It is therefore also
recommended that the EA process for the extension of Biehn Drive commence as soon
as possible and further that it be concurrent with the EA for the extension of sanitary
. The integrated
transportation system policies of the Official Plan are s
Transportation Master Plan. Map 11 (Integrated Transportation System) of the in-effect
Official Plan identifies the approved Robert Ferrie Drive alignment and confirms that
Biehn Drive will be extended from its current terminus southerly and connect to Robert
Ferrie Drive. The final alignment of Biehn Drive is to be constructed within the corridor
identified on Map 11.
Municipal Act, 2001
Planning Act
APPROVED BY: Justin Readman, General Manager, DSD
ATTACHMENTS:
Figure 1 - Borehole Location Plan
HFPUFDIOJDBM
JOWFTUJHBUJPO
CU!FOHJOFFSJOH
Cjfio!Esjwf
Ljudifofs-!Poubsjp
Cpsfipmf!)Dbncjvn-!3133*
Npojupsjoh!Xfmm!)Dbncjvn-
3133*
Npojupsjoh!Xfmm!)NUF-!312:*
Qspqptfe!Cpsfipmf
)Dbncjvn-!3134*
Qspqptfe!Npojupsjoh!Xfmm
)Dbncjvn-!3134*
Opuft;
.!Cbtf!nbqqjoh!gfbuvsft!bsf!ª!Rvffo(t!Qsjoufs!pg!Poubsjp-!312:!)uijt!epft
opu!dpotujuvuf!bo!foepstfnfou!cz!uif!Njojtusz!pg!Obuvsbm!Sftpvsdft!ps!uif
Poubsjp!Hpwfsonfou*/
.!Ejtubodft!po!uijt!qmbo!bsf!jo!nfusft!boe!dbo!cf!dpowfsufe!up!gffu!cz
ejwjejoh!cz!1/4159/
.!Dbncjvn!Jod/!nblft!fwfsz!fggpsu!up!fotvsf!uijt!nbq!jt!gsff!gspn!fsspst!cvu
dboopu!cf!ifme!sftqpotjcmf!gps!boz!ebnbhft!evf!up!fssps!ps!pnjttjpot/!Uijt
nbq!tipvme!opu!cf!vtfe!gps!obwjhbujpo!ps!mfhbm!qvsqptft/!Ju!jt!joufoefe!gps
hfofsbm!sfgfsfodf!vtf!pomz/
2:5!Tpqijb!Tusffu
Qfufscpspvhi-!Poubsjp-!L:I!2F6
Ufm;!)816*!853/8:11!!!Gby;!)816*!853/8:18
xxx/dbncjvn.jod/dpn
CPSFIPMF!MPDBUJPO!QMBO
Ebuf;
Qspkfdu!Op/;Nbsdi!3134
Sfw/;
22:7:.113Q
Tdbmf;Qspkfdujpo;
1366186211236
2;4-111
n
Dsfbufe!cz;Difdlfe!cz;Gjhvsf;
NBU
\[M
2