HomeMy WebLinkAboutDSD-2024-159 - Outcomes of Accelerating Commercial Business Approvals Review
REPORT TO: Finance and Corporate Services Committee
DATE OF MEETING: April 22, 2024
SUBMITTED BY: Mike Seiling, Director, Building Division, Development Services,
519-741-2200 ext. 7669
PREPARED BY: Margaret Love, Manager, Service Coordination and Improvement,
Development Services, 519-741-2200 ext. 7042
WARD(S) INVOLVED: All
DATE OF REPORT: March 25, 2024
REPORT NO.: DSD-2024-159
SUBJECT:
RECOMMENDATION:
That the use of Building Enterprise funds to: (1) pilot a Project Manager for an 18-
month staff secondment position and (2) support the implementation of initial
improvements for lan
project, including supporting a portion of the cost to develop a roadmap/handbook
for business owners be endorsed; and further,
That the remaining funding in the Development Services Review capital budget be
reallocated to support initial improvements for
REPORT HIGHLIGHTS:
The purpose of this report is to share high-
Enterprise funds to pilot an 18-month secondment position and support the
implementation of initial improvements.
The key finding of this report is that financial resources are required to begin
implementing the improvements from the Accelerating Commercial Business
, and that initial implementation can be supported by
Building Enterprise funds and the remaining Development Services Review budget.
The financial implications outlined in this report include a request to use Building
Enterprise funds to: (1) support one full-time, temporary Project Manager position at
approximately $101,239 (Step 1) - $126,550 (Step 4) per year (includes 29% fringe
benefits) and (2) $50,000 (one-time funding), plus approximately $48,000 remaining
capital funding from the development services review to support the implementation of
initial improvements.
*** This information is available in accessible formats upon request. ***
Please call 519-741-2345 or TTY 1-866-969-9994 for assistance.
Community engagement included one-on-one interviews with a cross-section of
business owners that opened their business within the last 12 months, to gain insights
.
This report supports Creating an Economically-Thriving City Together: Focuses on
growing an agile, diverse local economy powered by talented entrepreneurs,
workers & artists; creating opportunities for everyone and a resilient future that
propels our city forward.
BACKGROUND:
current Strategic Plan and 20-year vision for our community,
businesses and community members identified Creating an Economically Thriving City
Together as one of the five pillars in the Strategic Plan. Staff were subsequently directed by
Council to review the Cit, approvals, and licensing processes to
ensure that: (1) businesses can open their doors quicker, (2) the City is delivering first-rate
customer service, and (3) Kitchener remains attractive to new businesses and
entrepreneurs moving forward, particularly in a post-pandemic landscape when business
attraction is critical. To deliver on this direction, in 2023, a new Strategic Plan project was
identified: Accelerating Commercial Business Approvals. A Lean review of seven processes,
administered within five internal business areas, was completed between September 2023
and March, 2024, which resulted in 55 improvement recommendations.
REPORT:
The objectives of review were to:
Streamline permitting, approvals and licensing processes for new business
owners, relocating businesses, or businesses undertaking major renovations so
that they can open their doors quicker;
Ensure the City is delivering first-rate customer service; and,
Ensure that Kitchener remains attractive to new businesses and entrepreneurs.
The following processes were reviewed end-to-end as part of a Lean review (note: process
administrator/owner are identified in square brackets):
1. Zoning Occupancy Certificate \[Planning Division\]
2. Interior Finishing Permit \[Building Division\]
3. Business Licence \[Legislated Services\]
4. Permanent Sign Permits \[Planning Division/Building Division\]
5. Encroachment Agreement \[Legal Services\]
6. Patio Approval \[Building Division\]
7. Façade Grant \[Economic Development\]
There was an intentional focus on downtown/Mainstreet businesses, as this is where the
majority of issues arise (e.g., conversion of older buildings, inaccessible buildings,
constrained by space, etc.), however, this review and the improvements generated will
eventually apply more broadly and will benefit new businesses across the city.
The review was completed over a 5-month period and involved engagement with business
owners, City staff, and staff from the Waterloo Region Small Business Centre.
Based on estimates provided by business owners, the length of time to obtain the necessary
approvals and open their doors for business ranged from five weeks to over a year, with the
average being five months. The most difficult process to navigate and obtain approvals was
(i.e., a building permit
for interior construction/renovations), as it is a highly technical and complex process,
requiring the expertise of design professionals to support business owners through the
application, inspection, and approvals processes.
The top 10 process improvement themes recommended by business owners included:
1. Info package / handbook / roadmap document for businesses with steps to help
plan properly (e.g., things to consider/what you need to know when opening,
timelines, contacts, tips/tricks for each business type - restaurant, office, retail,
checklist with the order to obtain approvals, etc.);
2. Project Manager/Liaison role point person throughout the process;
3. Point person at the City for each service area, with staff hand-off at appropriate
time;
4. Processes need to be less transactional and more invested in relationships and
face-to-face contact;
5. Meeting upfront with key stakeholders in approvals process (identify issues /
concerns, requirements, and expectations);
6. Mobilize quickly to find solutions to issues;
7. Have different streams for independent businesses and larger organizations /
corporations;
8. Review resubmissions quicker;
9. Provide a 3-month reminder if building permit is still open; and,
10. Provide a 15-minute call ahead window for inspections (versus half day).
The above-noted recommendations for improvement were shared with the Citcross-
disciplinary project team early in the process. The team built upon these ideas and spent
several months and
defining problems, identifying root causes, and developing additional improvement
strategies. In total, 55 improvement recommendations were prioritized out of several
hundred ideas that were generated. Over 50% of the prioritized recommendations are
it is anticipated that businesses will experience a high
impact from implementing the improvement, and a lower effort will be required by staff to
implement them. A 2-year implementation plan was developed with staff leads assigned to
support the implementation of the 55 prioritized improvements. Attachment A to this report
provides a consolidated summary of the top prioritized improvements.
During the 2024 budget cycle, staff proactively requested funding to support the
implementation of this Strategic Plan project, however, Council decided that the review
should be completed and recommendations known prior to requesting funds for
implementation. As the busiest season for many businesses is fast-approaching summer
staff are bringing this report forward to begin implementing the prioritized process
improvements.
To fund initial improvements, staff are recommending that the remaining capital budget
allocated to the Development Services Review (DSR) be re-allocated and pooled with
funding from Building Enterprise to support initial implementation efforts from this review (as
outlined in the Financial Implications section of this report). The rationale for this
recommendation is that all the improvements from the DSR have now been implemented
and 24 of the 55 prioritized improvements from this review directly impact Building Services
processes.
There are two immediate improvements that require funding:
(1) A new, 18-month Project Manager staff secondment, supported by Building
Enterprise, that would act as the single point of contact/liaison for businesses and
further streamline approvals processes a pilot project that, if successful, would
result in the development of a business case to make the role permanent (similar
concept to the two PMs that support affordable housing applications/strategic
projects in Planning division), and
(2) The development of a highly visual and informative handbook-type document for
and will support planning and decision-
making as businesses open, relocate or renovate this requires third-party
consulting services to support both content creation and graphic design.
These two improvements have been prioritized for funding as they align with the top two
improvements recommended by business owners as well as staff.
Additional budget requests may be made as part of the 2025 budget cycle to support the
implementation of additional improvements in year 2 of the 2-year implementation plan.
STRATEGIC PLAN ALIGNMENT:
This report supports Creating an Economically-Thriving City Together: Focuses on
growing an agile, diverse local economy powered by talented entrepreneurs, workers
& artists; creating opportunities for everyone and a resilient future that propels our
city forward.
FINANCIAL IMPLICATIONS:
Capital Budget The recommendation has the following impact on Capital Budget:
The remaining capital funding from the Development Services Review (approximately
$48,000) will be used to support the implementation of initial recommendations from
this review including, but not limited to, funding a portion of the handbook document
for businesses.
Operating Budget The recommendation has the following impact on Operating Budget:
Building Enterprise funds will be used to support an 18-month secondment at approx.
$101,239 (Step 1) - $126,550 (Step 4) per year (estimate based on interim rating and
includes 29% fringe benefits) , and
Up to $50,000 of Building Enterprise funds will be used to support initial
improvements from this review, including funding a portion of the handbook
document for businesses (one-time funding).
COMMUNITY ENGAGEMENT:
INFORM dvance of
the council / committee meeting and an email with this link has been sent to business owners
who engaged with staff during the review.
CONSULT
Customer feedback surveys undertaken in business licensing from 2018 2023
One-on-one interviews with business owners in 2023
Feedback survey circulated to business owners to prioritize solutions
Future consultation on several improvements will include collecting feedback from
business owners via workshops as well as feedback surveys
The Kitchener Development Liaison Committee was engaged on March 22 and did
not object to the use of Building Enterprise funds to implement the recommendations
within this report as improvements will support faster permit approvals.
PREVIOUS REPORTS/AUTHORITIES:
There are no previous reports/authorities related to this matter.
APPROVED BY: Justin Readman, General Manager, Development Services
ATTACHMENTS:
Attachment A Consolidation of Improvements & Summary of Benefits
Efficiency
Quality
Improvement
Cost
s
Reduce
Risk
s
Reduce
Education/
Communication
/
Automation
Digitization
/
Customer
Service
Satisfaction
Enhanced
g
n
business
law to
-
the
by
develop a visual
to obtain
independenteducate the business licensing
,
application meeting
-s capacity to complete
staurants, offices, retail, and more consistent
approvals that will be
usiness owners and will
to open their business
to support
business owners with the option to potential
person pre
.
service standards when booki
required
-
work with staff to
in
Consolidation of Improvements & Summary of Benefits
site
businesses by ensuring there is equal
ingle point of contact to answer questions level so a meeting can be held to discuss a
-
-
on
explain the
independent
project manager
uired for the business to open
Improvement Consistent customer inspections with City of Kitchener staff.Hire aowners in navigating City processesnecessary approvalsfaster with a sand help resolve issues. This role
will also take on accountability for ensuring improvements from this review are implemented successfully.Provide request an where representatives from Building, Fire, Licensing, Planning
and Economic Development (as applicable) willattend toreqowner, provide guidance and build relationships. Pilot with downtown business owners with the potential to expand beyond the
downtown if successful.Hire a consultant to roadmap that business owners can use as their 'handbook' when opening a business in Kitchener. The guide will include simple steps to help
plan for opening a business, the types of City approvals required for common business types (e.g. reservices), and contact information. Support businesses owners by escalating significant
technical/code issues from customers quickly to the managementresolution. Increase Fire Prevention Officerinspections at coverage throughout the week response timeframesUndertake a
review of the currentallow for multiple services under one licensing application to ensure City of Kitchener is aligning with current business best practices and trends as more of these
types of businesses are opening. This will also ensure there are less fees for breduce the number of inspections required before opening.
Attachment A
Efficiency
Quality
Improvement
Cost
s
Reduce
Risk
s
Reduce
Education/
Communication
/
Automation
Digitization
/
Customer
Service
Satisfaction
Enhanced
-
-
d
of Patio
off.
-
off
-
Manager and
n permit
the
construction
-
. A delegation report
after occupancy at the 6
is needed, identify circulation
preparation and sign
process for confirming if an
Development
s to the business owner reminding them
approved encroachment agreement
delegate
-
n internal
Economic
redlining and approving drawingsbeginning the detailed review of incomplete applications as soon as they are receivedprioritizing resubmissionsrequesting a phone or teams meeting with
the applicant or consultant after their status letter is issued to ensure they understand the requirements
ormalize a
Improvement Develop a pretemplate and Approval encroachment agreements to Director ofwill be submitted to Council to eliminate the Fencroachment agreement criteria that can be established
with utility companies to only include them on encroachments that have a higher likelihood of impacting utilities, and create a centralizecirculation and commenting process.Identify
the types of façade improvements that could lead to additional mandatory amendments and added costs for business owners and streamline the reimbursement process so business owners can
get reimbursed faster.Accelerate the issuance of permit approvals by:Staff to coordinate and host onsite premeetings with Fire and Building staff wheapproval is issued. Staff to print
and bring approved/redlined drawing set, inspection schedule, and signage reminding contractors of top things to remember, for example, to call for inspections, leave work open if completed
on weekends, etc. Develop an occupancy letter template and begin to issue occupancy certificates that include what "occupancy" means and next steps to complete/close their permit. After
occupancy is granted send regular, recurring, autogenerated emailto complete the necessary work and call for an inspection if the permit is open month mark and every month thereafter
until it is closed.
Efficiency
Quality
Improvement
Cost
s
Reduce
Risk
s
Reduce
Education/
Communication
/
Automation
Digitization
/
Customer
Service
Satisfaction
Enhanced
-
with
via
ire and
F
and during
rowing the call
business owners
for
mpleted within 12
comments
initial
up with the business owner
if inspections are not booked
-
:
, and copying business owners on all
/ enhancing them within AMANDA,
patio drawings.
Zoning occupancy certificateInterior finishing permitBusiness licenseSign PermitsPatio permitFaçade grant
generated emails
-
uilding when providing
Improvement Streamline the inspections process by narahead window, eliminating duplication between Bonsite inspectionscorrespondence related to permit status and inspections.Building
staff to followautoafter the building permit has been issued to undertake an inspection of the site and to notify them that the permit can be revoked if work is not comonths. Create
a more streamlined application process for downtown patios with key dates and timelines, as well as simplified, visual instructions/toolsto complete Automate and digitize processes
by adding them to the AMANDA portalthe goal of having one integrated portal interface for the following processes