HomeMy WebLinkAboutDSD-2026-077 - Notice of Intention to Demolish - 63 Courtland Avenue East
Development Services Department www.kitchener.ca
REPORT TO: Heritage Kitchener
DATE OF MEETING: March 3, 2026
SUBMITTED BY: Garett Stevenson, Director of Development and Housing Approvals
519-783-8922
PREPARED BY: Garett Stevenson, Director of Development and Housing Approvals
519-783-8922
WARD(S) INVOLVED: Ward 9
DATE OF REPORT: February 12, 2026
REPORT NO.: DSD-2026-077
SUBJECT: Notice of Intention to Demolish Î 63 Courtland Avenue East
RECOMMENDATION:
That, in accordance with Section 27(9) of the Ontario Heritage Act, the Notice of
Intention to Demolish received on February 3, 2026, regarding a portion of Building
1 and the entirety of Building 2 and 3, as per the approved Heritage Impact
Assessment, at the property municipally addressed as 63 Courtland Avenue East,
be received as information and that the notice period run its course.
REPORT HIGHLIGHTS:
The purpose of this report is to consider the proposed demolition of a portion of
Building 1 and the entirety of Building 2 and 3, as per the approved Heritage Impact
Assessment, at the property municipally addressed as 63 Courtland Avenue East,
which is listed as a non-designated property of cultural heritage value or interest on
The key finding of this report is that demolition of portions of Building 1 and all of
Building 2 and 3 is required to facilitate site remediation and future redevelopment,
and that such redevelopment will be regulated by Site Plan approval conditions,
including a condition that requires the future designation of sections A, B, Ci and Cii of
Building 1 under Part IV of the Ontario Heritage Act.
There are no financial implications associated with this report.
Community engagement included consultation with Heritage Kitchener.
This report supports the delivery of core services.
BACKGROUND:
The Development and Housing Approvals Division is in receipt of Site Plan application
SPF25/090/C proposing to develop the property municipality addressed as 63 Courtland
*** This information is available in accessible formats upon request. ***
Please call 519-741-2345 or TTY 1-866-969-9994 for assistance.
Page 3 of 282
Avenue East. The proposed development will include five (5) stacked townhouse
buildings, including the conservation and adaptive reuse of the existing built heritage
resource. A Heritage Impact Assessment (HIA) was submitted with a complete Site Plan
application under the Planning Act. A draft HIA for the proposed development dated
January 2025 (updated February 2025) was prepared by MHBC and presented to
Heritage Kitchener on April 1, 2025. The focus of this HIA was the partial demolition of
Building 1 and the full demolition of Building 1 and 2. In response to Heritage Planning
staff comments and Heritage Kitchener comments, a revised draft HIA dated January
2025 (updated February 2025, October 2025) was prepared by MHBC and presented to
Heritage Kitchener on February 23, 2026. The focus of this HIA was the proposed new
construction and alterations to the existing built heritage resource.
Figure 1: Location Map Î 63 Courtland Avenue East
In addition to the Site Plan application noted above, the Development and Housing
Approvals Division is in receipt of a Notice of Intention to Demolish a portion of Building 1
and the entirety of Building 2 and 3, as per the approved Heritage Impact Assessment, at
the property municipally addressed as 63 Courtland Avenue East. The reason for this
notice is that it will facilitate the work required to be undertaken for a Record of Site
Condition, it will reduce the number and size of vacant buildings in the interim before
redevelopment proceeds, and it will allow for the redevelopment. The subject property was
listed by Council as a non-designated property of cultural heritage value or interest on the
.
The Notice of Intention to Demolish
received on February 3, 2026.
Page 4 of 282
Photo 1: Aerial photograph identifying the proposed building demolitions (shown in
red) (Source: MHBC, 2026)
Ontario Heritage Act Provisions
Part IV, Section 27(9) of the Ontario Heritage Act (see excerpt below) provides restrictions
on demolitions to property that is listed as non-designated property of cultural heritage
Restriction on demolition, etc.
(9) If property included on the register under subsection (3) has not been
designated under section 29, the owner of the property shall not
demolish or remove a building or structure on the property or permit
the demolition or removal of the building or structure unless the owner
gives the council of the municipality at least 60 days notice in writing
of the ownerÓs intention to demolish or remove the building or structure
or permit the demolition or removal of the building or structure.
In accordance with the Ontario Heritage Act, Council has 60 days as of and including
February 3, 2026 (the date of receipt of the Notice of Intention to Demolish), to pass a
Notice of Intention to Designate as a means of preventing the demolition.
REPORT:
The existing building (Building 1) located at 63 Courtland Avenue East is a 2-storey brick
building situated on a 1.57-acre parcel of land located on the south side of Courtland
Page 5 of 282
Avenue East between Benton Street and Peter Street in the Cedar Hill and Schneider
Creek Cultural Heritage landscape. Building 1 is comprised of eight sections constructed
th
between the early and late 20 century. These sections are identified as A, B, Ci and Cii.
Section A was constructed c. 1909 as the original single storey brick addition to the former
J.M. Schneider home. Section B, Ci and Cii were constructed between 1909 and 1914.
Section B was a second story addition above A, Section Ci was one storey addition
adjacent to A, and Section Cii was a second storey addition above Ci. The applicant is
proposing to demolish Section B, Ci and Cii of Building 1 and all of Building 2 and 3.
Photo 2: Aerial photograph identifying Building 1, including sections, and Building 2
and 3 (Source: MHBC, 2026)
Structural Reports
Three structural reports were prepared by Tacoma Engineers and submitted as part of the
Notice of Intention to Demolish. The structural engineer who authored and signed all the
assessments is a member of the Canadian Association of Heritage Professionals.
A condition assessment (Attachment A) was completed by Tacoma Engineers in May
2024 to confirm the structural stability of Building 1. This assessment concluded that the
building is generally in fair condition, structurally stable, and that sections of the building
could be demolished while avoiding adverse impacts to the heritage attributes and cultural
heritage value. A supplementary feasibility and condition assessment (Attachment B) was
completed by Tacoma Engineers in December 2024 to determine the feasibility of
Page 6 of 282
retaining sections of the building. This assessment concluded that the building continues
to be in fair condition, and nothing was observed that would suggest concern for the
structural stability of the building. It was noted that the exterior masonry is showing signs
of distress but was silent on the existing condition of the cornice. This assessment also
reconfirmed that sections of the building could be removed without affecting the structural
stability of the existing built heritage resource.
Photo 3: View of Building 1 (east and north elevations), including the identification
of the portion of building proposed for retention and conservation (MHBC, February 6,
2026)
A structural report (Attachment C) to address the partial demolition was completed by
Tacoma Engineers in February 2026 to outline how the sections of the building will be
removed without compromising the structural stability of existing built heritage resource.
This assessment concluded that some sections of the building could be removed without
compromising the structural stability of the existing built heritage resource. This
assessment also outlined five (5) recommendations (see bullets below).
Roof framing should be removed by hand where it interacts with the portions to
remain. This will ensure that the buildings roof framing will not be compromised
during the demolition of the addition roof framing.
During demolition, the floor and roof framing of the building should remain intact, as
it provides lateral support to the load bearing walls.
Floor framing of the addition should be reviewed, and separated by hand from the
building structure, as to not damage the building during demolition of the addition.
All openings created by demolition of the recent addition should be made weather
tight to prevent damage to the heritage asset. These weather tight closures can be
made after the demolition is complete, but should be constructed without significant
delay.
Demolition should be carried out by a licensed demolition contractor, with
experience in the demolition of heritage properties.
Heritage Impact Assessment
A revised draft Heritage Impact Assessment (HIA) dated January 2025 (updated February
2025, October 2025) was prepared by MHBC and submitted as part of the Notice of
Page 7 of 282
Intention to Demolish. Links to the first draft and revised draft HIA are provided in the
port.
Photo 4: View of Building 1 (west elevation), including the identification of the
portion of building proposed for retention and conservation (MHBC, February 6, 2026)
The revised draft HIA provides a description of the subject property, overview of the policy
context, historic overview and site history, existing conditions, descriptions of all buildings,
evaluation using Ontario Regulation 9/06, condition assessment, description of proposed
development, impact analysis, alternative development approaches, and mitigation and
conservation recommendations. The revised draft HIA concludes that the subject property
meets two (2) of nine (9) criteria for determining cultural heritage value or interest under
Ontario Regulation 9/06.
O. Reg. 9/06 Criteria Met? Rationale
(Yes/No)
1. The property has design
Yes Portions of Building 1 are considered
value or physical value
representative of the Romanesque
because it is a rare,
architectural style. Building 2 and 3 do not
unique, representative or
demonstrate design/physical value.
early example of a style,
type, expression,
material or construction
method.
Page 8 of 282
4. The property has direct
associations with a Yes The property is associated with John M.
theme, event, belief, Schneider and the J.M. Schneider & Sons
person, activity, business from 1897 to 1924/1925 for a
organization, institution period of approximately 28 years.
that is significant.
6. The property Yes The original portion of Building 1 (c. 1909)
demonstrates or reflects was constructed by Jacob Baetz, a stone
the work or ideas of an mason, bricklayer and skilled tradesman
architect, artist, builder, who was active in Kitchener during the
designer or theorist who late 19th and early 20th centuries.
is significant to a
community.
Based on the evaluation, the revised draft HIA concludes that the subject property meets
the minimum two criteria for designation under Part IV of the Ontario Heritage Act. The
revised draft HIA provides three mitigation recommendations:
1. Submission of a Conservation Plan which details how the building will be
appropriately conserved over the short, medium, and long-term. The Conservation
Plan will include information related to any structural systems needed to ensure the
building is stabilized during construction activities.
2. Submission of a Documentation and Salvage report which documents the existing
buildings with photographs and identifies any materials which could be salvaged for
a range of uses.
3. Submission of a Commemoration and Interpretation strategy which outlines the
strategy for the interpretation of the history of the site.
Site Plan Application
A Site Plan application to develop the subject property was received on November 4,
2025. The development will include five (5) stacked townhouse buildings, and the
conservation and adaptive reuse of the existing built heritage resource. A revised draft HIA
was submitted in support of the application. Both the original draft and revised draft HIA
were presented to Heritage Kitchener. Their comments have been considered in the
revised draft HIA and in the final heritage conditions prepared by Heritage Planning staff
for Site Plan Approval in Principle.
The final heritage conditions for Site Plan Approval in Principle address the following:
Approval of HIA;
Submission and approval of additional heritage studies, including: Conservation
Plan; Demolition, Stabilization and Temporary Protection Plan; Hoarding and
Construction Plan; Structural Assessment; Vibration Monitoring Plan; Risk
Management Plan; Documentation, Salvage and Reuse Plan; and,
Commemoration, Interpretation and Reuse Plan;
Page 9 of 282
Submission of Heritage Works Certification Forms prepared by a qualified Heritage
Consultant certifying that the recommendations of the approved heritage studies
have been completed;
Implementation of the final recommendations of all heritage studies to the
satisfaction of the Director of Development and Housing Approvals;
Provision of a cost estimate for 100% of the total cost of all short- and medium-term
conservation works identified in the approved Conservation Plan;
Provision of a Letter of Credit for 100% of the total cost of all short- and medium-
term conservation works; and,
Designation of the property under Part IV of the Ontario Heritage Act.
A draft Cultural Heritage Conservation Plan (CP) dated February 2026 and prepared by
MHBC has been submitted for review by Heritage Planning staff. The draft CP includes
information related to: demolition, stabilization and temporary protection of Building 1;
hoarding and construction adjacent to Building 1; a structural assessment of Building 1;
vibration monitoring during demolition and construction on the subject property; risk
management before, during and after development; and commemoration and
interpretation of the subject property. A separate Documentation and Salvage Plan dated
February 2026 and prepared by MHBC has also been submitted for review by Heritage
Planning staff.
Figure 2: Site Plan with retained section of Building 1 outlined in red (MHBC, 2026)
Page 10 of 282
Heritage Planning Comments
Heritage Planning staff have reviewed three structural reports and are satisfied that
section D, E, F and G of Building 1 can be demolished without compromising the structural
integrity of section A, B, Ci and Cii of Building 1. Heritage Planning staff note that the
reports mention the need to repair brick masonry but is silent on the condition and
conservation recommendations for the cornice (referred to as the stone or concrete
banding and dentils in the HIA). Heritage Planning staff will require the structural engineer
to review the condition of the cornice and provide conservation recommendations before
the sections D, E, F and G of Building 1 are demolished. Through the Site Plan process,
Heritage Planning staff will require the structural engineer to provide a detailed condition
assessment of heritage attributes on each elevation, including recommendations for short-
and medium-term conservation works, and an itemized cost estimate for each heritage
attribute.
Heritage Planning staff are in a position to recommend approval of the HIA subject to one
comment that requires further discussion and approval through the Site Plan process.
Heritage Planning staff have expressed concerns with cladding Section Ci and Cii of
Building 1 with dark grey fibre cement panels. Heritage Planning staff would like to
understand why the original cladding cannot be repaired or reconstructed. If it is
demonstrated that repair and reconstruction is not feasible, Heritage Planning staff may
support the fibre cement panels in a colour that is complimentary to the existing building.
Heritage Planning staff do not support the use of dark grey for cladding, which results in a
heavy contrast that distracts from the existing building.
Heritage Planning staff have reviewed the Site Plan application and the heritage studies
submitted to support the application. Heritage Planning staff comments are scoped to the
relevant components related to the partial demolition of Building 1 and the full demolition
of Buildings 2 and 3. The relevant components address matters related to risk
management, demolition, temporary protection, monitoring and documentation and
salvage.
With respect to risk management, the draft CP provides recommendation for construction
fencing, security cameras and vibration monitoring during demolition and construction.
Heritage Planning staff will require that the draft CP be updated to address risks
associated with vacant buildings such as deterioration to heritage attributes due to lack of
heat and partial or total loss of the building due to a fire.
With respect to demolition, the draft CP includes three structural reports that confirm that
sections D, E, F and G of Building 1 can be demolished without impacting the structural
integrity of sections A, B, Ci and Cii of Building 1 (see page 4 and 5 of this report). The
structural reports and the draft CP outline the proposed demolition methods, including
areas where demolition must occur by hand to ensure that structural parts are not
compromised during the demolition process. Based on these reports and the requirement
for a demolition report when an application to demolish is submitted under the Ontario
Building Code, Heritage Planning staff have reviewed three structural reports and are
satisfied that section D, E, F and G of Building 1 can be demolished without compromising
the structural integrity of section A, B, Ci and Cii of Building 1.
Page 11 of 282
With respect to temporary protection, the draft CP explains that the building will be made
weather tight following the demolition of sections D, E, F and G of Building 1. The draft CP
also explains that the short-term conservation works will include mothballing the building.
All doors and windows will be boarded. Heritage Planning staff agree with boarding the
building and will ask that the boarding comply with the following: all boards used in the
boarding shall be installed from the exterior and shall be property fitted in a watertight
manner to fit within the side jambs, head jamb, and the exterior bottom of the door or
window so that any exterior trim remains uncovered by the boarding; and, all boards shall
be 12.7 mm (0.5 in) weatherproofed sheet plywood secured with nails or screws at least
50 mm (2 in) in length and spaced more than 150 mm (6 in) on centre. This approach to
boarding must be added to the CP before sections D, E, F and G of Building 1 are
demolished
With respect to monitoring, Heritage Planning staff generally agree with the approach to
inspect the building, at minimum, every four weeks and to address any issues that arise.
Heritage Planning staff will require the details of the qualifications of who should undertake
those inspections, what they should do if deficiencies arise, and what timelines should be
followed to address the deficiencies.
With respect to documentation and salvage, Heritage Planning staff agree that existing
heritage attributes associated with sections A, B, Ci and Cii of Building 1 should be
retained in-situ and not salvaged. Heritage Planning staff also agree that, at minimum,
bricks that are in good condition and that are similar in colour, material, patina, and
dimensions should be salvaged and retained for use in the conservation and rehabilitation
of the retained sections of Building 1. Heritage Planning staff will require that the
documentation and salvage plan identify the minimum number of bricks to be salvaged
and more details regarding their storage with a strong preference for the bricks to be
stored on site in a building or structure.
Heritage Planning staff will require all comments noted above to be addressed prior to the
demolition of sections D, E, F and G of Building 1, and any other comments raised
between the date of this report and final Site Plan Approval will need to be addressed
before staff is able to clear approval in principle conditions.
C ouncilÓs Options
Under the Ontario Heritage Act
Intention to Demolish. Rather, Council has three options:
1. Request further information;
2. Receive the Notice of Intention to Demolish, allowing the notice period to run its 60-
days course, at the end of which the Building Division may issue a demolition
permit as early as April 4, 2026; or
3. Council may issue a Notice of Intention to Designate, at which point Council would
have the authority to deny demolition.
Based on the Heritage Planning staff comments above, Heritage Planning staff
recommend that Council proceed with Option 2. This option results in Council receiving
the Notice of Intention to Demolish and allowing the 60-day notice period to run its course.
Page 12 of 282
Through the conditions of Site Plan Approval in Principle, the owner will be required to
fulfill various conditions before the different stages of construction proceed (e.g., before
grading, or before servicing, or before final Site Plan Approval, etc.). One of these
conditions requires that the owner agree to designation of 63 Courtland Avenue East
under Part IV of the Ontario Heritage Act. Heritage Planning staff are satisfied that these
conditions will conserve the cultural heritage value and heritage attributes of the subject
property.
STRATEGIC PLAN ALIGNMENT:
This report supports the delivery of core services.
FINANCIAL IMPLICATIONS:
Capital Budget The recommendation has no impact on the Capital Budget.
Operating Budget The recommendation has no impact on the Operating Budget.
COMMUNITY ENGAGEMENT:
INFORM
the March 3, 2026 Heritage Kitchener committee meeting.
CONSULT The Heritage Kitchener committee will be consulted at the March 3, 2026
Heritage Kitchener committee meeting.
PREVIOUS REPORTS/AUTHORITIES:
CSD-13-110 Listing of Non-Designated Property of Cultural Heritage Value or
Interest on the Municipal Heritage Register and Refinements to the 4-Step Listing
Process
DSD-2025-110 Draft Phase 1 Heritage Impact Assessment 63 Courtland Ave E
DSD-2026-004 Draft Heritage Impact Assessment 63 Courtland Avenue East
Ontario Heritage Act
Planning Act
REVIEWED BY: Sandro Bassanese, Manager of Site Plan
APPROVED BY: Justin Readman, General Manager, Development Services
Department
ATTACHMENTS:
Attachment A Structural Report, Feasibility Study, 63 Courtland Avenue East
prepared by Tacoma Engineers and dated May 10, 2024
Attachment B Structural Report, Feasibility & Condition Assessment, 63 Courtland
Avenue East prepared by Tacoma Engineers and dated December 9,
2024
Attachment C Structural Report, Partial Demolition, 63 Courtland Avenue East
prepared by Tacoma Engineers and dated February 2, 2026
Page 13 of 282
Page 14 of 282
Page 15 of 282
TW-1481-24
MAY 10-24
Page 16 of 282
Page 17 of 282
Page 18 of 282
TW-1481-24
DEC 9-24
Page 19 of 282
Page 20 of 282
TW-1481-25
FEB 2-26
Page 21 of 282
PARTIAL SECOND FLOOR / ROOF DEMO FRAMING PLAN - SCHEMATIC
PARTIAL FIRST FLOOR DEMO FRAMING PLAN - SCHEMATIC
Page 22 of 282