HomeMy WebLinkAboutCRPS-06-010 - Demolition Contract and Related Issues - 31 Young Street (Forsyth Building)Report To: Mayor C. Zehr and Members of Council
Date of Meeting: January 16, 2006
Submitted By: G. Sosnoski, General Manager of Corporate Services & City
Clerk
Prepared By: L. Proulx, Director of Facilities Management l L. Gordon,
Director of Purchasing
Ward(s) Involved: Ward 1
Date of Report: January 12, 2006
Report No.: CRPS-06-010
Subject: DEMOLITION CONTRACT AND RELATED ISSUES - 31
YOUNG STREET (FORSYTH BUILDING)
RECOMMENDATION:
None at this time -for information only.
BACKGROUND:
On January 9, 2006 the City was served with the attached Orders to Prohibit Occupancy and to
Remedy an Unsafe Condition. These were issued by J. Witmer, Chief Building Official, and in
accordance with the Building Code Act. This was as a result of an engineering report entitled
`Review of the Forsyth Factory Building - 31 Young Street, Kitchener, Ontario' prepared by Sze
Straka Engineers (Structural Division of MTE Consultants Inc.) and dated January, 2006. The
report concluded that deterioration of the structure had increased exponentially to the point
where the building may collapse in an unpredictable time period, possibly very soon. The
unsafe conditions with respect to the structural integrity of the building were seen as posing a
threat to public safety, and the barricades currently surrounding the structure were judged by
the consulting engineer to be insufficient to ensure 100% public safety. Following a review of
the report, J. Witmer and Dr. Yulun Sze, Sze Straka Engineers, toured the building to validate
the engineering concerns, following which the above Orders were issued. The City
subsequently took steps to initiate demolition of Phases 1, 2 and 4 of the Forsyth Building
complex, details of which are outlined below.
On November 28, 2005, Council directed Facilities Management staff to reactivate the fire alarm
system and to implement measures to improve drainage and other protective measures with
respect to water penetration. In the course of undertaking this work, Mr. L. Proulx, Director of
Facilities Management, noticed that some bricks had recently fallen off of the Young Street
building fagade immediately over a public sidewalk. Just priorto Christmas, arrangements were
made for a structural engineer and a mason to examine the building in greater detail. As a
result of their preliminary observations, the engineer directed staff to block the sidewalk and
enclose the entire site in order to ensure public safety. The Sze Straka engineering report was
prepared between Christmas and the New Year and received by staff the morning of January 9,
2006.
Subsequent to the staff decision to demolish Phases 1, 2 and 4 of the Forsyth complex, a
special meeting of Heritage Kitchener was held on January 10, 2006, at which time the
Committee put forward a recommendation with respect to preservation of Phase 5 of the
Forsyth complex (Art Deco addition) and the house wedged between Phases 4 and 5. The
recommendation also suggested that Council should salvage as much of the building fabric as
possible. This recommendation was directed to the January 16, 2006 Council meeting.
REPORT:
Tenders l Salvage Issues:
Tenders were requested of five potential bidders and a site meeting was held with these firms
on Wednesday, January 11. The bids were requested as two separate components, the first
(Bid Item A) relating to demolition of the building alone, with the demolition contractor retaining
all salvage rights. The second component (Bid Item B) related to the additional cost which the
City would incur should it wish to retain the building materials as recommended by Heritage
Kitchener. This amount does not include any storage and future transportation costs or any
labour costs that may be required to render the materials in a condition suitable for future re-
use.
The following are the tenders received for Items A) and B) as outlined above:
Bidder Bid Item A Bid Item B
Bel-Air Excavating & Grading Ltd $ 206,510. $ 313,510.
Kieswetter Demolition 1992 Inc. $ 255,355.50 $ 647,644.25
HAZCO Environmental Services $ 283,710.50 $1,605,000.
Belco Contracting Brantford Inc. $ 294,206.74 $ 374,076.28
Sittler Environmental Inc. $ 309,999.80 $1,398,516.75
The tenders submitted were reviewed by staff at Noon on Thursday, January 12 and the
demolition portion of the tender (Item A) was awarded to Bel-Air Excavating & Grading Ltd.
(Cambridge) at their tendered price of $206,510., including GST. Bel-Air also submitted the
lowest bid for Item b) which would provide for the salvage of all materials including brick, wood
floors, columns and specifically the painted signage bands on the building, with these materials
to be skidded and transported to the Utilities Operations Centre (Elmsdale), all at a cost of
$313,510. including demolition.
Staff were compelled to act on the demolition portion of the tender immediately in order to
ensure that the work is undertaken as quickly as possible. The General Manager of Corporate
Services & City Clerk invoked the emergency provisions of Chapter 170 (Purchasing and
Materials Management) of the Municipal Code to authorize the purchase order relative to the
demolition tender. Under that provision a Department Head can authorize without Council
approval if the situation is such that failure to act would endanger `life, limb or property'. This
report is intended to fulfill the reporting requirement under Section 170.7.1 (b) of Chapter 170.
Council is free to deal with the Bid Item B portion of the tender on January 16, 2005 as it sees
fit, this to allow for consideration of the recommendation of Heritage Kitchener that "throughout
the demolition process all measures be taken to salvage all materials of heritage significance
and interest including but not limited to all brick, wood floors, beams, columns and specifically
the painted sign bands reading `John Forsyth Co. Ltd.' and `Fine Shirts -Underwear -
Pajamas'....". Should Council concur with the Committee's recommendation, consideration
should be given to what specific materials are to be retained, the long-term storage of these
materials and any labour costs involved in rendering them suitable for adaptive re-use.
Alternatively, Council may wish to consider retaining a limited amount of the building materials
as representative artifacts. It is anticipated this could be done at a much reduced cost. At this
point the City has no specific inventory of items to be salvaged for future use, nor any plans as
to how or where this material would be utilized.
Prior to initiating demolition, and in recognition of the fact there is no guarantee that the house
and the Art Deco addition will survive the demolition of the Forsyth Building proper, Leon
Bensason was given an opportunity to remove selected features from the interior of either the
Forsyth Building, the house or the Art Deco addition under the supervision of an engineer, and
provided that this can be done safely and without undue risk to staff. Mr. Bensason entered the
building on the morning of January 13 to remove any interior building features which he thought
were of architectural l heritage value. It was also confirmed the City has in its possession two
different sets of measured drawings of the Forsyth Building complex, and that Mr. Bensason will
take additional exterior photographs to augment the existing collection. Mr. Bensason was able
to remove a number of artifacts of anon-structural nature with the Forsyth name or which
reflected an architectural style of design which could be used to interpret the architectural style
of the building.
Demolition and Related Issues
The contractor entered the site to prepare it for demolition on January 13, and by that date the
water, gas and hydro service to the building was shut off. The contractor plans to begin
demolition early on January 14, beginning on the Young Street fagade with the portion closest to
Duke Street, provided all pre-demolition environmental concerns have been addressed.. They
plan to work down along the entire Young Street fagade and then back into the site once the
entire Young Street fagade has been demolished. Given the direction to demolish for reasons
of public safety, the City was anxious to proceed as soon as possible and the Saturday date is
the earliest this could occur given the site preparation and environmental issues. In addition,
the Saturday demolition start allows the work on the Young Street fagade directly opposite the
entrance to the City Hall Parking Garage to take place at a time when the Garage is not heavily
utilized and traffic in the Downtown is at lower levels that during the week. It is not expected
that it will be necessary to close the City Hall Parking Garage during the demolition, and the
contractor expects to keep one lane on Young Street open to allow access and egress to the
parking garage from Duke Street. However, it may be necessary to temporarily close the
Garage for short periods of time at various stages in the demolition process. Through traffic will
be blocked from the King Street entrance to Young Street.
The contractor estimates it will take between 5-6 weeks to demolish the entire structure, and it is
estimated that it will take approximately 1 week to remove the entire Young Street fagade,
weather permitting.
Consulting engineers will oversee the demolition and it is estimated that within 3 weeks staff will
be in a position to begin evaluating whether the Art Deco portion and the house can be retained.
At this point the contractor can give no clear indication as to whether it is possible to retain the
two buildings in whole or in part. A report will be prepared for Council once staff have a clearer
picture. The Chief Building Official will also have to assess whether further demolition beyond
building Phases 1, 2 & 4 is required for reasons of public safety, and if necessary will issue
subsequent orders.
If demolition proceeds according to plan, demolition of Phase 2 will result in the south elevation
of the Art Deco addition being almost entirely removed. If it is determined that the building can
be preserved, a temporary 2-3 storey wall will have to be constructed to secure the building.
Again the Chief Building Official and consulting engineer will make a determination in this
regard. It is not clear at this time as to whether additional remedial work would be required to
the house, as it is staffs' understanding that this does not share a common wall with the Phase
4 portion of the Forsyth complex.
Preparation of grading plans is currently underway with respect to backfilling of the cavity which
will be left as a result of demolition and removal. Engineering is working with Facilities
Management in preparing cost estimates in this regard and a determination will have to be
made as to the use of the site pending finalization of plans for the Centre Block. Given the
current use, staff are proceeding on the assumption that this would be converted into parking for
the near term.
Traffic and Parking staff are working with the demolition contractor to determine the extent to
which the parking lot bounded by Young and Duke Street will have to be closed during the
demolition process. The contractor will need a staging area and public safety and possible
vehicular damage would have to be considered when making this decision. At the time this
report was written only portions of the Centre Block parking lot will be closed with access only
from Duke Street. Effected monthly parkers are being diverted to the Duke /Ontario Garage.
The small parking lot at Young and Duke will be closed for the duration of the demolition.
FINANCIAL IMPLICATIONS:
At this point, staff are still in the process of identifying all of the costs related to demolition and
remediation as follows:
- The demolition cost based on tender award with the demolition contractor retaining all
salvage rights - $206,510.;
- Salvage costs in the event Council determines that it wishes to preserve building
materials are known based on Bid Item B in the tender, but have not been committed by
staff. It is our understanding that the $313,510. amount bid by Bel-Air would include
both demolition and salvage. Therefore the City could expect to pay an additional
$107,000. for exclusive salvage rights. The contractor has confirmed that any decision
by Council which reflects limited salvage could be negotiated at a lesser amount. The
exact amount would depend on the materials to be salvaged and the amount of labour
required returning them to the City in a reusable form. The present bid amount with
respect to salvage includes skidding and delivery of any materials for outdoor storage at
Elmsdale;
- Removal of environmental materials is known to be an issue which the City is required to
address, but the exact nature and cost in this regard is unknown at this time. Frontline is
working with staff to make a determination in this regard;
- Fill and grading costs will be incurred but are unknown at this time, and additional
information in this regard will be provided to Council when available;
- The City continues to experience costs with respect to security fencing initially put in
place prior to Christmas, and will continue to do so during the course of demolition and
re-grading. The total cost is not known at this time;
Environmental and engineering consulting costs are and will continue to be incurred but
the total amount is not known at this time and will depend entirely upon how the
demolition proceeds and whether it is necessary to demolish more than Phases 1,2 and
4 of the Forsyth complex;
Costs will be incurred if the Art Deco addition is retained relative to construction of a
temporary wall on the south elevation to enclose the building pending a decision on its
future. The extent of any work required to stabilize the house portion of the complex is
not known at this time and can only be determined as demolition progresses.
Any costs related to the demolition and remediation of the site will come from the Economic
Development Investment Fund, specifically that portion related to the Centre Block
development.
COMMUNICATIONS:
Corporation Communications will continue to keep the press and public advised as to progress
in remedying the unsafe condition and related issues. Leon Bensason, Heritage Planner, will
continue to keep Heritage Kitchener abreast of developments, and they will be consulted where
required or appropriate. Traffic and Parking staff will continue to deal with the City's parking
customers and to the best of their ability ensure alternate arrangements during the course of
demolition and site remediation. The public will also be kept apprised of any necessary street
closures or traffic disruption.
L. Proulx
Director of Facilities Management
G. Sosnoski
General Manager of Corporate Services
& City Clerk
c: C. Ladd
P. Houston
R. Browning
J. Witmer
M. Selling
M. May
L. Bensason
C. Goodeve
Heritage Kitchener
L. Gordon
Director of Purchasing