HomeMy WebLinkAboutDTS-06-041 - Voisin Greenway Rehabilitation Environmental Assessment
)
R
Development &
Technical Services
Report To:
Chair and Members
Development and Technical Services Committee
March 27, 2006
Date of Meeting:
Submitted By:
Prepared By:
Ward(s) Involved:
Date of Report:
Report No.:
Subject:
R. Shamess, Director of Engineering Services
C. Curtis, Senior Project Manager, Engineering (2419)
Ward 5
March 6, 2006
DTS 06-041
VOISIN GREENWAY REHABiliTATION ENVIRONMENTAL
ASSESSMENT
RECOMMENDATION:
That the recommendations of the Voisin Greenway Rehabilitation (Stirling Avenue to the
Conestoga Parkway) Municipal Class Environmental Assessment Study Report be
accepted; and
That Council allow the Voisin Greenway Rehabilitation (Stirling Avenue to the Conestoga
Parkway) Municipal Class Environmental Assessment Study Report to submitted to the
Ontario Ministry of Environment for the mandatory 30 day review period as required by
the Environmental Assessment Act; and further
That following the 30 day mandatory review period and Ontario Ministry of Environment
acceptance of the study, implementation of the recommendations of the Study be
allowed to proceed.
EXECUTIVE SUMMARY:
A Schedule 'B' Class Environmental Assessment Study was initiated for Voisin Greenway to
develop a rehabilitation plan to address the existing and potential future concern areas along
the Greenway while considering flood conveyance, natural, social and economic aspects. The
limits of this study are from Stirling Avenue to the Conestoga Parkway (at Fischer Hallman
Road) .
The City of Kitchener retained Stantec Consulting ltd. to undertake the study and complete any
design works for the preferred alternatives identified through the process. Based on various site
investigations and assessments as well as from public input gained through two Public
Information Centres held in December and February, various works along the Greenway are
being recommended. The following table and attached figure summarize the recommendations
of the report and repairs anticipated to occur in this coming summer/autumn.
Area of Potential Work
Failed ba wall section at 24 Ston brook Dr.
Failed bagwall section at 18 Farmbrook PI.
Preferred Alternative
Re- rade bank and stabilize with ve etation
Restore to previous condition with concrete
ba s
Repair gabions and immediate vicinity
Minor maintenance/repairs completed as
required
Re air with stone
Protect with stone at wall bottom
Selectivel thin or remove existin ve etation
Culvert inlet repair work at 136 Ruskview Rd.
Area immediately upstream of Westmount
Rd.
Re air of various storm sewer outfalls
Protection of toe erosion at various locations
Ve etation mana ement within main channel
In addition to these repairs, the Environmental Assessment Study Report is recommending the
implementation of an annual vegetation management program as well as a visual
inspection/monitoring program to identify any issues that may arise in the future.
BACKGROUND:
The portion of the Voisin Greenway system evaluated for the Environmental Assessment Study
Report lies within Ward 5 between the confluence with Borden Greenway (at Stirling Avenue) at
the downstream end and the upstream limit being the Conestoga Parkway (at Fischer Hallman
Road). The Greenway is surrounded by predominantly single family residential dwellings.
In its current state, the Voisin Greenway system is exhibiting numerous signs of disrepair and
failure. Several locations along the watercourse are experiencing significant issues of concern
including undermining, erosion, slope stability, and excessive sediment aggradation. Problems
of this sort along the Greenway have been observed for a number of years with previous repairs
focussed on relatively small areas of immediate concern. The City of Kitchener Stormwater
Policy (2002) and subsequent Annual Audits identified a number of problem areas and coupled
with recent and anticipated creek failures, prompted the current Study, which reviews the
system, evaluates alternatives for repair, selects a preferred alternative, and provides a means
to implement rehabilitation measures for the system as a whole.
REPORT:
Voisin Greenway is located in Ward 5 and drains a 510 ha component of the Schneider Creek
headwater system. The reach of the Greenway system within the Study Area (approximately
2.1 km) consists largely of an engineered watercourse system that replaced and re-aligned the
original natural watercourse in conjunction with the development of the area as a residential
community in the 1950's. Varying bed and bank materials can be observed along the subject
reach including such components as concrete bag walls, armour stone retaining structures,
steel "bin" walls, bioengineering, and minor sections of earthen 'natural' channel. Throughout
much of the Study Area the Greenway is confined to a narrow right-of-way between private
properties, primarily of single-family residential character.
In its current state, the Voisin Greenway system is exhibiting numerous signs of disrepair and
failure. Several locations along the watercourse are experiencing significant issues of concern
including undermining, erosion, slope stability, and excessive sediment aggradation. Problems
of this sort along the Greenway have been observed for a number of years with previous repairs
focussed on relatively small areas of immediate concern. In order to address the current
conditions of the Greenway, the City retained Stantec Consulting Inc. to undertake a Schedule
'B' Class Environmental Assessment Study to review the system, evaluate alternatives for repair
and design, and provide a means to implement rehabilitation measures for the system as a
whole.
In accordance with the Terms of Reference the Consultant Team completed various
investigations and evaluations of existing physical conditions within the study area with an
objective to secure information that would assist in the determination of an appropriate solution.
Site investigations included a geotechnical/stability assessment, topographic and vegetation
survey, geomorphological assessment, aquatic biology/fisheries habitat assessment and a
hydraulic capacity assessment. The results of the existing conditions assessments generally
conclude that the Greenway system is, by and large, functioning well from a conveyance
perspective, generally stable across the majority of it's length, and of limited environmental
sensitivity. The results of the Public Information Centres generally indicated that the adjacent
landowners are, for the most part, very satisfied with the Greenway and long for the days of
routine maintenance. The net result is that there does not seem to be a need or desire for
large-scale remediative works or revisions to the existing condition, from an economic,
environmental, public use, or cost perspective.
These assessments, coupled with information obtained through two Public Information Centres,
formed the basis for development of alternatives and selection of preferred alternatives for
rehabilitation of the Greenway. Alternatives developed were evaluated based on the following
criteria: cost, public acceptance, environmental impact, maintenance/long-term benefit, ease of
construction, aesthetics, risk to property, conveyance, and potential for future failure. The
following table summarizes the preferred alternatives and the works to be undertaken to
address the problem locations along the Greenway.
Area of Potential Work
Failed ba wall section at 24 Ston brook Dr.
Failed bagwall section at 18 Farmbrook PI.
Preferred Alternative
Re- rade bank and stabilize with ve etation
Restore to previous condition with concrete
bags
Re air abions and immediate vicinit
Minor maintenance/repairs completed as
re uired
Repair with stone
Protect with stone at wall bottom
Selectivel thin or remove existin ve etation
Culvert inlet re air work at 136 Ruskview Rd.
Area immediately upstream of Westmount
Rd.
Repair of various storm sewer outfalls
Protection of toe erosion at various locations
Ve etation mana ement within main channel
In addition to these repairs, the Environmental Assessment Study Report is recommending the
implementation of an annual vegetation management program as well as a visual
inspection/monitoring program to identify any issues that may arise in the future.
Subsequent to Council approval and Ministry of Environment acceptance of the Environmental
Assessment, construction of the preferred alternatives would be scheduled for the
summer/autumn of 2006.
FINANCIAL IMPLICATIONS:
The works described above as the preferred alternative have been included in the 2006 capital
budget and it is anticipated the budget is sufficient to cover the recommended works.
COMMUNICATIONS:
As per the requirements of the Environmental Assessment process, several notifications have
been provided to the public as well as to the required Provincial Ministries. Two notices were
placed in the Kitchener Waterloo Record advertising the two Public Information Centres as well
as the Notice of Intent. In addition, invitation letters to the Public Information Centres were
mailed to residents backing onto the Greenway. A third letter describing the proposed works
was also provided to the residents for their information and comment. It should be noted that
the Grand River Conservation Authority was included on the Study Team.
CONCLUSION:
Recent and anticipated failures of existing bagwall along the Voisin Greenway prompted
commencement of a Schedule 'B' Class Environmental Assessment to identify the need for
rehabilitation of the Greenway. The results of the existing conditions assessments generally
conclude that the Greenway system is, by and large, functioning well from a conveyance
perspective, generally stable across the majority of it's length, and of limited environmental
sensitivity. The results of the Public Information Centres generally indicated that the adjacent
landowners are, for the most part, very satisfied with the Greenway and long for the days of
routine maintenance. The net result is that there does not seem to be a need or desire for
large-scale remediative works or revisions to the existing condition, from an economic,
environmental, public use, or cost perspective. Based on these evaluations and public input,
preferred alternatives to the various issues have been proposed, and budgeted for in the 2006
Capital budget. Subsequent to Council and Ministry of Environment acceptance of the
recommended remedial works, construction of the proposed alternatives will commence in the
summer of 2006.
Carrie Curtis, P. Eng.
Senior Project Manager
DTS - Engineering
Robert Shamess, P. Eng.
Director of Engineering
J