HomeMy WebLinkAboutCRPS-05-021 - Mayfair Elevator
~
Report To:
Date of Meeting:
Submitted By:
Prepared By:
Ward(s) Involved:
Date of Report:
Report No.:
Subject:
Councillor B. Vrbanovic and Members of the Finance and
Corporate Services Committee
February 7,2005
G. Sosnsoki, General Manager of Corporate Services & City
Clerk
L. Proulx, Director of Facilities Management
February 2, 2005
CRPS-05-021
ELEVATOR REPLACEMENT - MAYFAIR
RECOMMENDATION:
That Council authorize an expenditure of $312,000. from the Economic Development
Investment Fund to replace the existing elevator at the Mayfair with a new elevator utilizing the
existing exterior shaft at 158 King Street West.
BACKGROUND:
The current elevator was manufactured and installed circa 1950 and is becoming increasingly
problematic in terms of service. The service contractor has indicated that of the 1,164 elevators
they service, this is the oldest and therefore the highest risk. The availability of parts is
becoming problematic, and of late the City has had some difficulty in obtaining a service
contract due to the age of the elevator and related liability issues. In addition, safety concerns
have been expressed by KJA Consultants Inc. (the City's elevator consultant) as well as the
maintenance service provider.
The Mayfair is part of the Centre Block property, the development of which is currently under
consideration. At this time no decision has been made on the final disposition of the Mayfair
building or the development of the balance of the site.
REPORT:
The undersigned undertook a review of the current situation late in 2004 and it was determined
that the City has two options in terms of replacing the existing elevator as outlined below.
Ootion 1 - replacement with elevator of comparable size
One option is to provide a new cab and elevator system within the existing elevator shaft, with
the cab being of a size identical to the existing. The existing cab is very small and the
dimensions of the existing shaft will only allow replacement with a similar sized cab. The
replacement cab, like the current one would not provide barrier free access, nor allow the
movement of furniture or appliances between floors. In other words a cab of this size is limited
entirely to moving people between floors. The size of the cab would also constrain any
renovation and development above the ground floor level. The total cost of this option is
$209,000.
Ootion 2 -
The second option, and the recommended one, would involve utilizing an existing exterior
elevator shaft at the adjacent City-owned property at 158 King Street West. There is presently a
three-storey concrete freight elevator shaft immediately adjacent to the Mayfair elevator. This
elevator has been abandoned, and is in need of replacement, but is not required at present as
158 King is not in use. Option 2 would require the shaft to be extended by another three storeys
plus a mechanical room above with a short connector between it and the Mayfair elevator shaft
which would involve cutting into the firewall and refitting the Mayfair elevator shaft with
permanent floors to the new elevator. This option would provide a larger shaft which would
accommodate a barrier free elevator as well as additional head room for the handling of larger
equipment, furniture and appliances. The cost of this option is $312,000. A diagram showing
Option 2 is attached.
Analvsis - Ootion 1
Pro -less costly than Option 2 by approximately $103,000.;
- would be considered a modification rather than a new installation and as a
result certain Elevator Code implications would continue to be acceptable;
- it is the easiest and least time consuming replacement option (though the
elevator would still be out of operation for a minimum of one month).
Con - does not allow the elevator to be barrier free, and as a result would likely not
comply with the Ontarians with Disabilities legislation currently before the
Legislature;
- limits further use of the elevator unit due to the size of the cab. Elevators of this
small a dimension have limited utility and could not be easily transferred to
another development;
- though the elevator could be replaced quicker, it would also require the unit to
be out of service for a longer period of time than Option 2, this time estimated at
between 4-6 weeks;
- elevator has practically no freight capability due to size.
Analvsis - Ootion 2
Pro - would allow barrier free access and comply with pending legislation;
- would allow for movement of furniture and appliances and allow more flexibility
in future development of the Mayfair;
- could be relocated to a development elsewhere in the block as the size is not as
restrictive as the current cab;
- is the least disruptive option in terms of downtime. It is estimated that the
elevator would be out of service for 2-3 weeks in order to reconstruct entry doors
and create the bridge over the existing elevator shaft. However, the current
elevator could be used while the ancillary shaft and new elevator are being
con structed.
Con - more costly than Option 1;
- more extensive modification required which results in the overall project taking
longer to complete.
FINANCIAL IMPLICATIONS:
It is proposed that the expenditure amount be debited from the Economic Development
Investment Fund being used for the Centre Block.
Ootion 1
Elevator Package
Related Installation Work
Design and Engineering Services
10% contingency
$ 150,000.
$ 20,000.
$ 20,000.
~
$ 209 000.
Ootion 2
Elevator Package
Related Installation Work
Design and Engineering Services
10% contingency
$ 180,000.
$ 80,000.
$ 26,000.
$ 26 000.
$ 312.000.
COMMUNICATIONS:
This report and recommendation has been vetted with Kitchener Housing Inc. which concurs
with the recommended option.
The matter was also discussed by Corporate Management Team on February 1,2005 and there
was general agreement that the City should replace the elevator at this time rather than delay
for clearer direction on the future of the Centre Block. It was felt that there is too much risk in
delaying replacement, especially given the problems encountered to date in obtaining a service
contract.
CONCLUSION:
If the City decides to do nothing at this time, it would be running the risk of continuing to operate
an elevator which is considered by some to be unsafe. Though it at present meets Provincial
safety requirements, there is no way of knowing if this will be the case for a short or longer
period of time. Parts availability is always a concern, and in the event a part is not available or
the Technical Standards Safety Association feels the elevator is unsafe it would have to be shut
down while the replacement process is undertaken. This will result in longer down time as the
elevator would not continue to be operational while an ancillary shaft is constructed.
Notwithstanding the increased cost of Option 2, staff feel that it is the wiser long term
investment, providing more redevelopment options and the only one which would comply with
barrier free legislation.
Laurier Proulx
Director of Facilities Management
GS/lk
C: C. Ladd
P. Houston
L. Gordon
B. Davey / K. Kwiatkowski
D. Hergott
L. MacDonald