HomeMy WebLinkAboutDTS-06-177 - Onward Ave Reconstruction
)
c,_>
KITCHENER
Development &
Technical Services
~
Report To:
Date of Meeting:
Submitted By:
Prepared By:
Ward(s) Involved:
Date of Report:
Report No.:
Subject:
Councillor Berry Vrbanovic, Chair of Finance and Corporate
Services Committee
December 11 th, 2006
Dave Mansell, P.Eng, Director of Engineering
Mike Henderson, C.E.T., Supervisor Engineering Asset
Management
Ward 1
December 11 th, 2006
DTS 06-177
ONWARD AVENUE RECONSTRUCTION (KING STREET TO
WEBER STREET) ASSESSMENT OF LIQUIDATED
DAMAGES REPORT
RECOMMENDATION:
That the request for additional engineering fees of $11,760.74 submitted by Stantec
Consulting Ltd. relative to Expression of Interest E04-074 (Consultant Services - Onward
Avenue Reconstruction), be approved.
EXECUTIVE SUMMARY:
The reconstruction of Onward Avenue between King Street and Weber Street was substantially
completed September 15th, 2006. The reconstruction was complicated by the Terracon's
inability to successfully test and commission the temporary watermain system. This ultimately
resulted in a delay to the project's completion as well as additional consulting and testing fees.
After the project was completed the engineering consultant Stantec Consulting Ltd. submitted a
request for compensation based on additional working days over and above those indicated
within the contract. The reason for the request included the need for additional inspection time
and additional effort ultimately related to the repeated failed temporary watermain testing. The
contractor was given opportunity to advance or "catch up" their construction schedule after the
time when the temporary watermain testing became a problem and to the end of the contract's
stipulated working days.
Engineering staff have been reviewed the request for additional fees and the assessment of
liquidated damages are in place within the contract expressly for this purpose. The requested
fee increase in this report is the direct result of notification to Terracon Underground Ltd. that
liquidated damages would be applied to compensate for costs incurred due to working days
exceeding the amount stipulated within Contract T06-008.
BACKGROUND:
Expression of Interest E04-074, Consultant Services - Onward Avenue Reconstruction was
awarded to Stantec Consulting Ltd. late in 2004 and an agreement for those services entered
into on February 3rd, 2005. After the project was awarded to Stantec Consulting Ltd. the
original scope was expanded as outlined and approved within a previous report to council, DTS
06-119. This expanded work included an Environmental Assessment related to traffic calming
and contaminated material removal.
After construction was completed, a separate request for additional fees related to this project
was submitted. The liquidated damages assessment can be directly related to the time lost with
the temporary watermain systems failed commissioning and the resulting extra sampling and
testing. This delay resulted in the contract's working days being extended beyond the original
scope. In order to recover those costs to the City the Liquidated Damages clause within the
contract was invoked.
REPORT:
After construction was completed, a separate request for additional fees from Stantec
Consulting Ltd. related to the project was submitted. Stantec Consulting Ltd. requested
compensation for work that was in excess of the original fee estimate and fee estimates for the
expanded scope. The claim can be summarized as follows;
1) Additional watermain testing and sampling
The amount of effort (staff time and sampling costs) required by Stantec to adequately test and
sample the temporary watermain exceeded the fee estimate submitted for this work. The
additional expenditures were required in an effort to ensure proper water quality was achieved
for the residents of Onward Avenue during the construction. Terracon's efforts resulted in this
temporary watermain requiring 7 rounds of testing and sampling prior to acceptance and
commissioning.
2) Additional inspection and contract administration time due to working days being
exceeded
The temporary watermains repeated commissioning failures resulting in several inefficient
construction procedures being undertaken by Terracon Underground Ltd., in order to move
forward with the construction schedule. This ultimately affected the construction schedule by 11
working days. Terracon Underground Ltd. was given opportunity to recover this lost time to their
schedule through the balance of the construction activity but was ultimately unable to maintain
their contractual schedule. This directly affected Stantec's staffing requirements for the project
relative to their field inspection time and their contract administration time.
FINANCIAL IMPLICATIONS:
Funding Available:
Index Code 852403 Balance $187,593.89 (excluding GST)
Funding Required: $11,760.94 (excluding GST)
Balance Remaining: $175,832.95 (excluding GST)
CONCLUSION:
Engineering staff have reviewed in detail the request for increased fees for Stantec Consulting
Ltd. related to the assessment of Liquidated Damages and believe that compensation of
$11,760.94 (excluding GST) is warranted to Stantec Consulting Ltd. for the increased working
days on this project. An analysis of the funding for this project shows that holdbacks applied to
Terracon Underground Ltd. will fund the additional consulting fees.
Mike Henderson, C.E.T.
Supervisor, Engineering Asset Management
Dave Mansell, P.Eng
Director of Engineering