HomeMy WebLinkAboutCRPS-05-112 - Accelerated Implementation Schedule - Twin Pad Arena ~ Report To: Date of Meeting: Submitted By: Prepared By: Ward(s) Involved: Date of Report: Report No.: Subject: Mayor C. Zehr and Members of Council June 20, 2005 G. Sosnoski, General Manager of Corporate Services & City Clerk G. Sosnoski (on behalf of the Twin Pad Steering Committee) June 16, 2005 CRPS-05-112 ACCELERATED IMPLEMENTATION SCHEDULE - TWIN PAD ARENA RECOMMENDATION: None at this time - information requested by Council. BACKGROUND: At the Finance and Corporate Services Committee meeting of June 13, 2005, a recommendation was adopted directing staff to investigate the feasibility of accelerating construction of a Twin Pad Arena to coincide with the start of the 2007 / 2008 hockey season. A preliminary estimate of time and impact is being presented to Council at this time as several decisions would have to be made in the very near future were we to accelerate this process. REPORT: Attached are two schedules relating to the process for design and construction of a new Twin Pad Arena. Schedule 'A' is the normal schedule which would be followed in preparing a business case, selecting a site, developing a budget, consulting with stakeholders and completing the design and construction process. This is the course of action recommended by staff as being the most realistic and comprehensive approach. Schedule '8' is a compressed schedule which could see occupancy in the early Fall of 2007. This course is not recommended by staff as the schedule is very tight with little margin for error or delay and would require the curtailing or elimination of steps which we feel are important. It should be stressed that these schedules are at a very preliminary stage. If Council wishes to proceed with the compressed schedule, the decision-making process must be dramatically accelerated. Staff would need clear direction to proceed with the accelerated schedule on June 20 or June 27 at latest. Approval to advance funds (approximately 20% of the project budget) to begin the process of retaining a consultant would be required by the end of June. Approval of the full project budget would be needed by the end of August in order to proceed with an Expression of Interest for consultant services by September 1. The following are the expected process / project impacts arising from a compressed timeline as outlined in Schedule 'B': · Business Case process. There would be no business case document before Council in advance of a decision to fund the project. Staff would be principally focused on selecting the site, developing a project budget and retaining a consultant. · The Capital Budget for the Twin Pad would have to be dealt with exclusive of the remainder of the Capital Forecast. This is necessary as the budget is required to select the consultant in September, 2005. · Investigation of bundling options would be limited and would result in the elimination of any complex bundling options. · The sites reviewed would be limited to those currently owned by the City. · There would be no investigation of possible partnership options. · There would be little or no public consultation on the selection of the preferred site. · There would be a greater margin for error in estimating project costs and an increased likelihood of cost overruns. · The Development Charge By-law (DC) is still under appeal with the indoor recreational facilities being an issue. We will not know by mid-August what proportion of DC funding will be available. This could also be a risk in regard to Schedule 'A'. · There could potentially be a gap in service provision if any facilities (eg. lit ball diamonds) on the preferred site cannot be relocated prior to the start of construction. There are also several broad assumptions built into the accelerated timeline; namely: that every aspect of the implementation process would have to strictly adhere to deadlines as there is little or no option for delay; that there would be no delays in the construction phase due to material shortage, strikes, etc.; the existing amenities on the construction site would be relocated prior to construction beginning. FINANCIAL IMPLICATIONS: At present, the Steering Committee only has a very preliminary budget estimate (plus or minus 30%) in part due to not having identified a site and an incomplete understanding of project scope. A commitment to fund the entire project would be required well in advance of the scheduled 2006 budget process and immediately following selection of the site and refinement of the project budget in July / August of this year. The funding for the project would have to be advance from 2008 / 2009 / 2010 which may require deferral of another capital project. CONCLUSION: As indicated above staff cannot recommend the compressed timeline outlined in Schedule 'B' but will do our very best if directed by Council to implement. This project is relatively complex, not because of the nature of the building as much as the related issues of public consultation for the new arena and for the decommissioned site, relocation, decommissioning of an existing facility and site selection, all of which will have a significant impact on neighbouring residents and user groups. G. Sosnoski General Manager of Corporate Services & City Clerk