Loading...
HomeMy WebLinkAboutDTS-07-024 - Emergency Repairs, Lower Laurel Creek WatercourseL Ki REPORT Development& L Technical Services Report To: Councillor Christina Weylie, Chair of Development and Technical Services Committee Date of Meeting: February 19, 2007 Submitted By: D. Mansell, Director of Engineering Prepared By: G. MacDuff, Manager of Development Engineering Ward(s) Involved: Ward 2 Date of Report: January 29, 2007 Report No.: DTS 07-024 Subject: Emergency Repairs, Lower Laurel Creek Watercourse RECOMMENDATION: That Council authorize Engineering Services to tender the emergency repairs on the Lower Laurel Creek watercourse with said tender and total costs to be brought back to Council for approval. BACKGROUND: In 2001, Council approved a Lower Laurel Creek slope stabilization project for a section of the Laurel Creek watercourse immediately behind the Bridgeport Grand Hotel. This slope stabilization work addressed significant erosion problems along an outside bend of the main channel of Laurel Creek, and consisted of the placement of several layers of armourstone, as well as some additional geotechnical materials on the slope face itself. At the time of these works, the remaining downstream section, which consisted of gabion baskets (stone filled wire mesh "baskets") showed no indications of instability, and accordingly, remained in-place. In December of 2006, Operations staff identified that the remaining section of gabions between the 2001 works and Carisbrook Drive supporting the easterly embankment of Laurel Creek had abruptly collapsed, and significant erosion of the remaining embankment was occurring. The collapse resulted in more than two-thirds of the gabion wall completely sliding into the main channel of the watercourse, forming a blockage within the main channel itself (see attached). After preliminary review, Engineering staff determined that immediate repair of the wall failure would be necessary to avoid further risk to persons/property/bridge, and accordingly under the provisions of the Purchasing Policy, retained Stantec Consulting Limited to prepare a restoration plan for the affected area. Engineering staff have also liaised with the Grand River Conservation Authority (GRCA) and obtained their concurrence that immediate repairs are necessary; failure to initiate repairs prior to peak spring runoff periods would (potentially) result in further risk to the public, as well as impacts to the natural watercourse (Grand River). Furthermore, preliminary review indicates that the westerly gabion wall structure is becoming unstable, and poses a failure risk as well. As such, we will be addressing the failure of the easterly embankment and the potential failure of the westerly bank. It is our intent to continue a similar armourstone wall design on the remaining section of the watercourse from the limit of the works undertaken in 2001 to the confluence of the watercourse with the Grand River. The total approximate length of the easterly bank is 35m, with the westerly bank comprising approximately 35m. FINANCIAL IMPLICATIONS: No budget provision currently exists for these works, estimated to cost $700,000. Staff proposes that the capital out of current portion be funded through an increased allocation from the Hydro Capital Investment Reserve Fund to the capital pool and that the growth-related portion be funded through Development Charges as follows: C/C $630,000 DC $ 70,000 Total $700,000 Note: This is a pre-tender estimate of total project cost. Actual tender amounts may differ due to the nature and timing of the works. The projected opening balance for the Hydro Capital Reserve Fund is $2,271,000 in 2007. $1,570,000 has been notionally allocated to fund the increased costs of the Hanson Avenue Twin Pad, leaving $701,000 available for other purposes in 2007. CONCLUSION: In order to protect persons /property /bridge and the natural environment, immediate emergency repairs are necessary on the Lower Laurel Creek watercourse. Due to the presence of a warm water fishery (Grand River), this work must be completed within a very narrow window of opportunity. As any impact to the watercourse should be minimized, the repair cannot be staged or deferred. As such, we request that Council authorize the tendering of this work with the final costs and funding approach to be brought back to Council for approval following the close of the tender. D. Mansell, P. Eng. George MacDuff, CET Director of Engineering Manager of Development Engineering Affected Area