HomeMy WebLinkAbout2008-03-17
AUDIT COMMITTEE MINUTES
MARCH 17,2008
CITY OF KITCHENER
The Audit Committee met this date commencing at 5:05 p.m.
Present: Mayor C. Zehr - Chair and Councillors J. Smola, B. Vrbanovic, K. Galloway, G.
Lorentz and C. Weylie
Staff: C. Ladd, Chief Administrative Office
R. Browning, General Manager, Development & Technical Services & Fire Chief
D. Chapman, General Manager, Community Services
G. Murphy, Director of Engineering
R. Gosse, Committee Administrator
1 . DTS-08-043 - Enaineerina Audit
The Committee was in receipt of Development & Technical Services Department report DTS-08-
043 dated March 11, 2008 regarding the audit of engineering projects. Attached was the report
submitted by MMM Group dated December 2007 titled 'Engineering Audit Report - Engineering
Audits: Victoria Street Reconstruction and Joseph/Gaukel Streets Reconstruction Projects'.
Mr. G. Murphy advised that in 2002 and 2003 the City undertook two projects in the Downtown
area: Victoria Street and Joseph/Gaukel Streets Reconstruction: which included the conceptual
and detail design and contract administration for the Victoria Park Entrance. Both projects were
complex with many issues and City staff faced many challenges including scheduling and costs.
Mr. Murphy further advised that in June 2007 the City retained MMM Group Ltd to undertake an
independent review of the processes and methodologies used for the two projects with the intent to
better understand the issues and problems with the projects and to look for improvements which
could be made for future projects.
Mr. Tom Chang, P. Eng., Manager of Project Management for MMM Group Limited gave a
presentation highlighting the audit framework, the project management context, the summary of
findings from the audit and conclusions and recommendations. Mr. Chang advised that for
purposes of this audit the City's processes were evaluated under the framework identified by the
Project Management Institute and the Project Management Body Of Knowledge (PMBOK). Within
context of PMBOK the audit focused on 5 areas: site management and monitoring; soil testing;
cost estimating; risk management; and, consultant selection. Mr. Chang briefly reviewed the 5
focus areas and outlined the following opportunities for improvement:
· Clearly defined expectation regarding the required project management and
environmental management scope of services by the successful consultant;
· Clearly define the expected deliverables over project life cycle;
· Consider implementing a two-envelope Request For Proposal submission process;
· Consider applying a contingency in budgets appropriate to the level of information that
was available to develop the estimate;
· Consider using a formalized reporting process that would provide early identification of
significant changes to established project baselines;
· Consider requiring more frequent and formal reporting on project costs and schedule
status by the project manager;
· Consider developing a standard reporting template that would improve internal reporting
consistency;
· Standardized document filing and retrieval procedures;
· Specify in the Expression of Interest that environmental site assessments be supervised
by qualified person;
· Allow adequate lead time in the construction schedule to complete required environmental
investigations;
· As part of the Expression of Interest a materials management plan be required as a
project deliverable;
· Consider incorporating risk management planning and monitoring on future complex
projects.
AUDIT COMMITTEE MINUTES
MARCH 17,2008
- 4 -
CITY OF KITCHENER
Mr. Chang concluded his presentation adding that a lessons-learned process to transfer experience
gained between projects would be extremely beneficial in developing better methodologies for
these construction projects.
Councillor G. Lorentz advised that there were several staff turnovers during these projects and
asked whether this may have had a bearing on some of the challenges. Mr. Chang responded that
staff turnovers are a risk of every project and with better documentation, knowledge and status of
the project can be passed on to new staff members. Councillor B. Vrbanovic asked if risk
management plans were common in other municipalities. Mr. Chang advised that risk
management plans are typically done for complex projects and are not necessarily required for
every project undertaken. Councillor C. Weylie pointed out that one of the challenges for both
these projects dealt with environmental issues and she asked how the City could deal with this
more effectively in the future. Mr. Chang advised that more time is required up-front when planning
the project in order to assess the environmental risk to be addressed. Mayor C. Zehr asked if a
two-envelope approach to the consultant selection was not being used for some Expressions of
Interest. Mr. Murphy replied that currently for some projects there is a two-stage approach
whereby consultants are short-listed but this is not necessarily considered to be what is referred to
as a two-envelope selection process. Mayor Zehr asked in regard to risk management who would
be expected to monitor the plan. Mr. Chang advised that it could be done in-house if the expertise
exists, if not, then it would be part of the Expression of Interest that a consultant would undertake
that portion of the plan.
Mayor Zehr advised that the recommendation contained in the staff report directs staff to develop
an implementation plan and he asked when that would be expected. Mr. R. Browning advised that
staff have not yet discussed in detail the development of a plan suggesting that later this Fall would
be appropriate. Councillor B. Vrbanovic pointed out that the implementation plan would identify
what actions would be taken and when and not necessarily required the implementation of those
actions therefore the plan should be developed sooner in order to address those actions that will
benefit projects as early as this year such as better document control and the lessons-learned
process. Mr. Murphy advised that staff could develop a matrix and identify time-lines and this could
be completed by April/May of this year.
On motion by Councillor B. Vrbanovic-
it was resolved:
"That Council receive the Engineering Audit Report for the Victoria Street Reconstruction
and Joseph/Gaukel Reconstruction, dated December 2007, as prepared by the MMM
Group and directs staff to develop an implementation plan for its recommendations."
Councillor B. Vrbanovic requested that an annual report be developed and presented to this
Committee regarding obligations of the City under various Acts showing if the City has met its
obligations. Councillor Vrbanovic added that Wilfred Laurier University undertakes this exercise
annually and it is helpful for members of the board. Mr. D. Chapman advised that staff would need
to undertake a scoping exercise to develop the list of legislation and obligations and can report
back to the Committee.
2. ADJOURNMENT
On motion, the meeting adjourned at 5:38 p.m.
R. Gosse
Committee Administrator