HomeMy WebLinkAboutDTS-08-036 - Construction of New Sidewalks in Existing Urbanized Areas1
K KR
Development&
Technical Services
REPORT
Report To: DTS Committee, Chair - Christina Weylie
Date of Meeting: March 31, 2008
Submitted By: Grant Murphy - Director of Engineering, Development and
Technical Services
Prepared By: Greg McTaggart - Manager of Engineering Asset Planning
Wards} Involved: All
Date of Report: February 19, 2008
Report No.: DTS-08-036
Subject: CONSTRUCTION OF NEW SIDEWALKS IN EXISTING
URBANISED AREAS
RECOMMENDATION:
A} That Council continue to endorse the annual new sidewalk installation program
which supports the City's Pedestrian Charter (adopted by Council in April of 2005}
and the Air Quality In Kitchener Report, recommendation 2.8 (presented to Council in
May of 2006} that support the principles of accessibility, equity, health and well-
being, environmental sustainability, personal and community safety, and are used to
ensure walking is a safe, comfortable and convenient mode of urban travel; and
further,
B} That staff be directed to continue to work with the community to assist in developing
awareness in regard to the importance of these principles when sidewalk
construction is being proposed; and further,
C) That the following list of proposed new sidewalk segments developed using the
methodology described in this report be approved for use in the 2008 new sidewalk
construction program, and that this methodology be approved for future new
sidewalk infill prioritisation.
BACKGROUND:
In 2003, a Sidewalk Study Group was convened consisting of staff from Engineering Services,
Community Services, Information Technology, and Economic Development finalized the
development of a model that was intended to be used to identify areas of greatest need for
sidewalk, and specifically assist in the prioritization and budgeting of the construction of new
sidewalks in locations other than industrial areas, or new subdivisions that are being planned or
currently under construction. These areas generally are already developed and urbanized, but
for various reasons did not have sidewalks installed at the time of their initial construction. The
process of filling in these "gaps" in the city's existing sidewalk network is often referred to as
"sidewalk infilling".
Although it would be desirable to have new sidewalk constructed in a significant portion of these
locations in as short a time as is possible, the reality is that it will take at least 27 years at the
current rates of funding allocated to this activity to address the top one-third (in terms of priority)
of this backlog, due to the shear scope of the task. The intent of prioritising this work is to
ensure that locations with the greatest need for sidewalks are addressed as soon as possible,
with lower priorities coming later in the process. This is intended to ensure that the greatest
public need is addressed first, and that funding allocated to this activity is spent in the most
effective manner possible.
Until now, this model has not been vetted through Council to affirm these objectives or the
methodology intended to effectively administer and plan for the installation of sidewalks.
Notwithstanding, Engineering staff have begun to use the model to prioritize the allocation of
capital funding that is allocated annually to new sidewalk construction, and to address sidewalk
needs in other projects and programs that comprise the accelerated infrastructure program -
such as road reconstruction projects may be affected by this issue. The model is being used to
assist with the development of the annual budget, prioritisation and timetables for work, and
longer-term funding forecasts. Prior to using this model, the process of selection for new
sidewalk involved information based on random observations, anecdotal information, and citizen
concerns -both requesting and opposing new sidewalks in their neighbourhood. The decision
support model that has been developed ensures that all possible locations in the city are being
assessed in an objective and consistent manner.
REPORT:
In developing the sidewalk demand model, the Study Group conducted an extensive review of
the factors that influence the priority of need for sidewalks. Features within the City that
generate the highest demand for sidewalks were inventoried, and then a comparison of public
demand relative to each other was applied to develop a demand weighting for each of the 10
features defined as generating above-typical demand for sidewalk. To use some examples, the
three highest factors that were determined to drive the greatest demand for sidewalks were: (1)
schools, due to schoolchildren walking to and from school everyday, (2) special needs facilities
such as hospitals and social service agencies due to their being commonly used public
"destinations", and (3) streets with high vehicular traffic volume, due to the increased risk that
pedestrians face walking in such conditions.
A point scoring system was then developed and applied to the identified demand features, with
features deemed to generate a higher demand for sidewalk receiving a higher proportional point
value on a possible scale of 100. Together, the values for all demand features total 100 points,
therefore the location with the highest possible demand for a new sidewalk would be assessed
100 points. Presented in Table 4 & 5 are the identified demand features used in the system, and
the relative score applied to each.
In order to develop a prioritisation for new sidewalk infill construction, if any location currently
without sidewalk fell within a predetermined buffer distance from any of the identified demand
features, it was awarded the score assigned to that particular demand feature. The buffer
distances were set at 50 metres, except for 120 metres for schools. Most locations in the city
will receive more than a "0" score as they will likely fall within the buffer zone of at least one
feature. From this assessment, a prioritised list of all locations in need of new sidewalk infill in
the city was developed.
For example, if a particular location currently without sidewalk was 80 meters from a school, 40
meters from a library, 35 meters from a community trail, fell within a high density population
area, and had both a bus route and posted speed of 60 kmlh on the street adjacent to it, the
location in question would be rated as follows:
Proximity to school = 23 points
Proximity to library = 8 points
Proximity to community trail = 8 points
Within a high population density zone= l 0 points
Adjacent to a bus route = 10 points
On a street with higher posted speed limits= 5 points
TOTAL SCORE FOR THIS LOCATION= 64 points
Once all locations without sidewalk were assessed and rated, a prioritisation class system was
assigned to all candidate new sidewalk locations that garnered points in the assessment.
Table 1: Prioritisation Class System
PRIORITY CLASS WEIGHTING SCORE
Priorit 1 68 - 100 oints
Priorit 2 46 - 67 oints
Priorit 3 29 - 45 oints
Priorit 4 1 - 28 oints
Using the example used previous, the location that was assessed a demand score of 64 points
would be assigned the priority class "2".
Table 2 following illustrates the classification of all identified locations under City stewardship
currently without sidewalk into the 4 priority classes for new sidewalk installation, by amount of
work required to complete each class (in kilometres), and the amount each class represents as
a percentage of the all locations identified.
Table 2:
New Sidewalk Priorities By Class Breakdown
Based on the above criteria, staff have developed a recommended installation plan for the new
sidewalk construction program that addresses new sidewalk needs that fall within the "priority 1 "
demand category firstly; ranks the order of construction of each of those priority 1 locations from
highest to lowest based on their assessed weightings, and then positions them in an anticipated
construction year based on capital budget allocation for this program in the 10-year capital
forecast. The same processes are done for "priority 2" and "priority 3" locations. Identified
locations assessed as priority classes 1 through 3 that lie within areas slated for other planned
infrastructure work, such as a full road reconstruction, would receive sidewalks at the time of
that project's execution. Locations that have been assessed a priority 4 designation would be
assessed on acase-by-case basis, as the demand features driving a need for sidewalk in these
locations are fewer in number and other factors unique to the location may override the few
demand sidewalk features existing in that location.
FINANCIAL IMPLICATIONS:
The adoption of this system has no immediate effect from a funding perspective, as it is used to
prioritise new sidewalk installation work based on the greatest public need, not determine the
desired rate of progress. It will prioritise the locations in need of sidewalk based on objective
criteria and specify the number of those locations that can be addressed in a given year, based
on the budget available to perform that work and the estimated cost of installing new sidewalk at
each location. In a larger context, will demonstrate the time that it will take to address each
prioritisation class of sidewalk based on current budget projections in the 10-year capital
forecast.
Priority 1: 5 km Priority 2:27 km
2% of Total ~ 9% of Total
The attached Appendix `A' provides the list of locations identified as Priority Class 1 and 2 for
new sidewalk installation, and their recommended installation period based on the current
capital budget allocation for such works as is specified in the 10-year capital forecast.
This model is not intended to determine the matter of how quickly new sidewalk installation work
should be completed. It can however project how much time is required to address each priority
class based on any funding model for such work that is put forward. Funding model alternatives
that Council might consider include: (1) keeping the status quo, (2) increasing the funding
allocated to new sidewalks with the goal of expediting the new sidewalk installation process, or
(3} reducing funding for this activity. Table 3 below describes the anticipated time in years
required to complete construction for each class of new sidewalk installation based on priority
classes 1, 2, 3 and 4 with the status quo budget trends, and example projections for a
theoretical reduction in funding of 25%, and an increase in funding of 25%.
Table 3.
Priority Priority Priority Priority
1 2 3 4
Fundin Model
9 Total Years To Complete All
Locations (approx)
Status Quo 1 year 5 years 21 88 115 years
years years
25% Greater 0.7 ear
y 4 ears
y 17 68
Fundin ears ears 90 ears
25% Lesser 1.2 6 ears
y 28 113
Fundin ears ears ears 148 ears
There currently is no recommendation to change the current funding projections for this activity
from the status quo, and the increase/decrease scenarios are shown for illustrative purposes.
CONCLUSION:
It is our long term objective to have sidewalks on both sides of the street where possible to
assist in addressing the goals stated in the City's "Clean Air Plan" and "Pedestrian Charter".
In addition, it is a stated goal of the city to whenever possible to employ practices that will
improve the air quality for citizens. To ensure walking is as safe, comfortable and convenient a
mode of urban travel as possible in the city, this approach furthers the principles of accessibility,
equity, health and well-being, environmental sustainability, personal and community safety, and
community cohesion and vitality. With this in mind, we are advancing the recommendations
stated above for future sidewalk installations within the City of Kitchener.
Grant Murphy, P.Eng.
Director, Engineering Services
Greg McTaggart, C.Tech.
Manager, Infrastructure Asset Planning
Table 4: Demand features for new sidewalk used in the system, and the relative weighting
score applied to each.
Demand Feature Weighting Score Buffer Distance From
oints Feature meters
School Areas 23 120
Special Needs Facilities 15 50
includes:
- Hospitals and clinics
- Senior's facilities
- Chronic care facilities
- Child care facilities
- Government services
High Vehicular Traffic Areas: average annual 12 50
daily traffic greater than or equal to 6000
vehicles
Public Transportation Facilities 10 50
includes:
- Bus route
- Railwa assen er terminal
High Density Population: neighbourhood 10 50
density greater than or equal to 6013 persons
er s uare km.
Neighbourhood Pedestrian Links 8 50
includes:
- Walkways
- Communit trails
Community Facilities and Resources 8 50
includes:
- Public sports facilities (sports fields, sports
centres, basket ball courts, arenas, pools)
- Parks
- Community resources (community centres,
libraries)
- Skatin rinks
Places Of Worship 5 50
includes:
- Churches
- Mosques
-Synagogues
- Temples
Streets With Higher Vehicle Speeds: posted 5 50
seed limit is reater than ore ual to 60km/hr
Tourist Attractions 4 50
POSSIBLE TOTAL 100
Table 5: Proportional comparison of the weighting applied to new sidewalk demand features
used in the system.
New Sidewalk Criteria Weighting
Tourist Attractions Posted Speed >= 60kn~lhr
4% 5 %r.
School Areas Places of Worship
23% 5%
~ Public Recreation Facilities
/~~ 8%
~,
Neighbourhood Li~~lcs
8%
Special Needs
15 %r `~
Population Density
~, 10%
\,___
,~---~
AADT >= 6000
12% Transit
10%
Appendix `A': Locations identified as Priority Class 1 and 2 for new sidewalk installation, and
their recommended installation period based on the current capital budget allocation for such
works as specified in the 10-year capital forecast.
2008 Construction Year
SCORE PRIORITY
CLASS
73 P1(>67 )
72 P1(>67 )
70 P1(>67 )
STREET
CONESTOGA COLLEGE
BLVD
HERITAGE DR
GAGE AVE
68 P1(>67) DOON VALLEY DR
68 P1(>67) ORCHARD MILL ORES
68 P1(>67) DOON VALLEY DR
66 P2 (46-67) OLDFIELD DR
65 P2 (46-67) NORTH DR
65 P2 (46-67) PANDORA AVE S
2009 Construction Year
61
61
60
58
58
58
58
58
57
56
56
56
P2 (46-67)
P2 (46-67)
P2 (46-67)
P2 (46-67)
P2 (46-67)
P2 (46-67)
P2 (46-67)
P2 (46-67)
P2 (46-67)
P2 (46-67)
P2 (46-67)
P2 (46-67)
UNION ST
ARNOLD ST
ROCKWAY DR
SIMEON ST
BLOCK LINE RD
WOOLWICH ST
WOOLWICH ST
HOMER WATSON BLVD
STIRLING AVE S
MORGAN AVE
DOON VILLAGE RD
VANIER DR
CONESTOGA COLLEGE
BLVD
FROM_STREET
DOON VALLEY DR
OTTAWA ST N
WAVERLY RD
CONESTOGA COLLEGE
BLVD
DOON VALLEY DR
PINNACLE DR
OTTAWA ST N
QUEENS BLVD
STIRLING LANE
MARGARET AVE
OXFORD ST
FLORAL ORES
STIRLING AVE N
HANOVER ST
SHIRK PL
BRIDGE ST W
STIRLING AVE S
FORK IN ROAD
FAIRWAY RD N
DOON SOUTH DR
B ONIFACE AVE
TO_STREET
HOMER WATSON
BLVD
EB YDALE DR
BELMONT AVE W
END
DOON VALLEY DR
DURHAM ST
EB YDALE DR
SPADINA RD W
KING ST E
SUNSET PL
LANCASTER ST W
DOON RD
FORK IN ROAD
HOMER WATSON BLVD
BRIDGE ST W
HILLCREST LANE
HOFFMAN ST
COURTLAND AVE E
SOUTHILL DR
END
WALTON AVE
HOMER WATSON BLVD
56 P2 (46-67)
2010 Construction Year
SCORE
56
55
55
55
55
54
54
54
54
53
53
53
53
PRIORITY
CLASS
P2 (46-67)
P2 (46-67)
P2 (46-67)
P2 (46-67)
P2 (46-67)
P2 (46-67)
P2 (46-67)
P2 (46-67)
P2 (46-67)
P2 (46-67)
P2 (46-67)
P2 (46-67)
P2 (46-67)
STREET
DOON VALLEY DR
FLORAL ORES
ROCKWAY DR
DOON RD
BLOCK LINE RD
STIRLING AVE N
NICHOLE ORES
ZELLER DR
SUSAN CRT
CARWOOD AVE
EULER AVE
MONTGOMERY RD
TYSON DR
DOON VALLEY DR
FROM_STREET
PINNACLE DR
ROCKWAY DR
FLORAL ORES
FLORAL ORES
LAURENTIAN DR
LYDIA ST
THE COUNTRY WAY
JANET CRT
SUSAN ORES
CAYLEY CRT
WEBER ST E
WEBER ST E
BRIDGE ST E
TO_STREET
DURHAM ST
DOON RD
DOON RD
ROCKWAY DR
WESTMOUNT RD E
EAST AVE
THE COUNTRY WAY
WILD MEADOW ST
CUL DE SAC
COURTLAND AVE E
PROSPECT AVE
BRENTWOOD AVE
HORNING DR
53 P2 (46-67) NORTH DR MARLBOROUGH AVE HIGHLAND RD W
53 P2 (46-67) KNELL DR WESTWOOD DR GLASGOW ST
2011 Construction Year
53 P2 (46-67) KEHL ST HOFFMAN ST OTTAWA ST S
51 P2 (46-67) CHAPEL HILL DR CARYNDALE DR EVENSTONE AVE
50 P2 (46-67) MILL ST BORDEN PKY MILL ST
50 P2 (46-67) TURNER AVE VICTORIA STN FREDERICK ST
50 P2 (46-67) GLASGOW ST WESTMOUNT RD W GLASGOW LANE
50 P2 (46-67) WASHBURN DR BLEAMS RD TRILLIUM DR
50 P2 (46-67) ARDELT AVE ARDELT PL HANSON AVE
2012 Construction Year
50 P2 (46-67) WILSON AVE FAIRWAY RD S WEBSTER RD
50 P2 (46-67) WASHBURN DR BLEAMS RD TRILLIUM DR
49 P2 (46-67) SCENIC WOOD ORES THALER AVE THALER AVE
49 P2 (46-67) BELLEVIEW AVE SMITHSON ST SUFFOLK AVE
49 P2 (46-67) DOON SOUTH DR DOON VILLAGE RD WINDRUSH TRAIL
49 P2 (46-67) GOUNDRY ORES RITTENHOUSE RD ERINBROOK DR
49 P2 (46-67) IMPERIAL DR OTTAWA STS CUL DE SAC
49 P2 (46-67) ST GEORGE ST PETER ST CEDAR ST S
49 P2 (46-67) IMPERIAL DR OTTAWA STS CUL DE SAC
49 P2 (46-67) WINDERMERE CRT ROLLING MEADOWS DR CUL DE SAC
49 P2 (46-67) TRADEWINDS PL ROLLING MEADOWS DR CUL DE SAC
49 P2 (46-67) CUMBERLAND PL ROLLING MEADOWS DR CUL DE SAC
2013 Construction Year
48 P2 (46-67) HOMER WATSON BLVD STIRLING AVE S HOFFMAN ST
47 P2 (46-67) STRASBURG RD CHANDLER DR OTTAWA ST S
47 P2 (46-67) CHANDLER DR STRASBURG RD WOODFERN CRT
46 P2 (46-67) DOON VALLEY DR OLD MILL RD END
46 P2 (46-67) CARYNDALE DR ROBERTSON ORES CHAPEL HILL DR
46 P2 (46-67) ZELLER DR JANET CRT WILD MEADOW ST
46 P2 (46-67) HEARTHWOOD ORES HEARTHWOOD DR HEARTHWOOD DR
46 P2 (46-67) BEECHROYAL PL WESTFOREST TRAIL WESTFOREST TRAIL
46 P2 (46-67) VANIER DR CUL DE SAC BONIFACE AVE
46 P2 (46-67) LANG ORES SPRINGDALE DR BRIDGEPORT RD
46 P2 (46-67) BATTLER RD HURON RD OLD HURON RD