Loading...
HomeMy WebLinkAboutDTS-08-105 - King street master plan streetscape project updateREPORT Report To: Chair Christina Weylie and Members Development and Technical Services Committee Date of Meeting: June 16, 2008 Submitted By: K. Grant Murphy P.Eng. Director, Engineering Services Rod Regier Executive Director, Economic Development Prepared By: Steve Allen, P.Eng. Manager, Engineering Design and Approvals Cory Bluhm, MCIP, RPP Urban Investment Advisor Eric Saunderson, C.E.T. Design and Construction Project Manager Ward(s~ Involved: All Date of Report: June 9, 2008 Report No.: DTS 08-105 Subject: KING STREET MASTER PLAN STREETSCAPE PROJECT UPDATE RECOMMENDATION: That staff be directed to initiate design modifications for the King Street Streetscape project as outlined in Option 4, contained in Development and Technical Services Department report DTS 08-105, dated June 9t", 2008, that will result in a streetscape for King Street that will meet the objectives of the King Street Master Plan at an estimated cost of $7,900,000 including Engineering fees; and, That the Municipal Infrastructure Investment Initiative grant of $3,200,000 be allocated towards the King Street project in addition to the previously approved budget of $5,680,000, with any ultimate project surplus to be returned to their original funding sources; and, That the purchase order to IBI Group for the design of the King Street project be extended by $100,000 for the design and retendering associated with Option 4, with actual fees to be negotiated between the City and IBI Group; and further, That staff be directed to meet with members of the Kitchener Downtown Business Association to determine an appropriate scheduling and phasing plan. EXECUTIVE SUMMARY: The purpose of this report is to provide an update on the activities completed to date related to the King Street streetscape project and seek approval from Council to proceed with the project as detailed in Option 4. In light of new information which clearly shows the potential for the project to cost more than the approved amount, on April 7, 2008, Council directed staff to pause the King Street project to permit time to complete a detailed third-party cost review to confirm that the existing design of the project would exceed the approved budget, and to complete a Value Engineering Assessment which would look at ways to reduce the overall projected costs on the project by looking for ways to optimize the design and potentially reduce the quality of the materials being used. The result of the cost review confirms that the construction cost of existing design would exceed the approved budget if tendered without changes. Staff from Engineering Services and Economic Development have completed a Value Engineering Assessment in an effort to reduce the cost. Various options have been considered and staff is recommending that Council provide direction to proceed as outlined in Option 4 which would result in a high quality streetscape meeting the objectives of the "pedestrian first" philosophy between College Street and Frederick Street, and selected streetscape improvements between Francis Street and College Street. Flexibility will be incorporated into the construction contract to permit additional upgrades to the Francis to College block in the event of favourable pricing at tendering. BACKGROUND: On April 24, 2007, the King Street Master Plan project committee conducted a streetscape design workshop and charrette. The workshop commenced with a presentation followed by a general overview and an approach for the stakeholder charrette. The approach encouraged stakeholders to comment on a series of questions focusing on themes for King Street. On May 22, 2007, the project team presented the design themes and streetscape concepts at the first of three public consultation centres. Based on the theme approach, participants were asked to comment on design concepts and elements that can be added to enhance King Street. Each design concept included an image to illustrate how King Street might look based on each theme. A series of elements were listed for each theme and participants were asked to select which items they'd like to see on King Street. Based on the public's feedback and detailed review by the Steering Committee, the Pedestrian First model Concept 3} was the preferred option. The Pedestrian First model involves narrowing King Street in the City Centre District to widen sidewalks and improve accessibility, including upgrades to both the design and surface treatment of major and minor intersections. The area directly in front of City Hall will be designed as a special civic area that can be easily closed and used for special events. Parking spaces will be converted and relocated to give way to a vehicular drop off and loading zone. A rolled curb will be introduced for King Street from Frederick to Victoria to improve pedestrian movement and improve accessibility. On September 26, 2007, preliminary design drawings for the pedestrian first, streetscape design for the King Street & Speakers Corner were submitted to the City and Steering Committee for 2 review as part of 30% design submission. A revised design was later released for public consultation on October 11, 2007 at W.L.U. School of Social Work. In December 2007, a 60% design package and a detailed business case were presented to City Council for its consideration. At that time City Council ear-marked $5.68M in capital funding for the King Street Streetscape and Speaker's Corner project. On February 4 the final budget for the project was approved by Council as part of the City's 2008 budget process. Additionally, a proposal was submitted to the Province of Ontario, as part of the Municipal Infrastructure Investment Initiative program and on March 28 the City received $3.2M. The provincial government recently announced the City was successful in securing those provincial funds for the King Street Streetscape project. In an attempt to gain a better understanding of the increased cost projections for the project staff instructed the IBI Group to complete a detailed design cost estimate prior to releasing the bid packages to the field of pre-qualified contractors Based on this work the IBI Group provided revised cost estimates for the project that range between an additional $2M - $4M. According to the IBI Group there are five key components of this project which have significantly affected the overall construction costs: construction phasing and staging; timing of the tender; surface treatments ~i.e. granite); street lighting, and; other ambient lighting. Separately, staff have reviewed the work from the 60% design to the 100% stage in an effort to determine the reasons for the large variance between the proposed budget and the final cost estimate. Several factors were identified as having a significant contribution to the variance: The innovative and unique nature of many of the features in the design coupled with City and Consultant staff's limited experience with some of the these features resulted in more than typical variances in cost estimates from the 60% to 100% stages, as many of the design details of these features were undetermined at 60%. Based on feedback received from the public and Council, the King Street Master Plan Steering Committee selected a high quality streetscape that met the needs of many of the key stakeholders. This resulted in 1 }the selection of materials, furnishings and other features with highly variable costs; and 2) a highly detailed plan (ex: extensive banding, inclusion of electrical power at special event pads, etc.}. The need for the street lighting to address factors beyond just roadway and sidewalk lighting (facade lighting, ambient/accent lighting, etc.} required the selection of a customized light standard after the 60% stage. The specific requirements of the lighting type reduced the number of options available which increased the cost. The costs associated with the restrictive nature of the staging dictated in the final design was not fully accounted for the in the 60% cost estimate. On April 7th, 2008, a pause in the King Street project was approved by Council. The pause permitted staff to confirm the increased cost and to complete a value engineering assessment to identify potential cost reductions. On April 17th, A.W. Hooker and Associates was retained to complete a detailed cost estimate. The results of their detailed review confirm that the existing design might exceed the approved budget by $5.5M, or about double the original budget, if tendered without changes. A Value Engineering Assessment was completed by A.W Hooker and City of Kitchener staff that identified aspects of the project that should be reviewed for cost savings. Throughout the end of 3 March and early June, staff have identified several options for changes to the King Street streetscape project which are identified in this report. REPORT: Proposed Options for Moving Forward: Staff have considered a number of options for moving forward with this project which are detailed below. Option 1 -Postpone Project indefinitely • Defer King Street Project completely and re-prioritize it against other projects in 2009. • No time commitment to proceed with construction • Life Span of the Infrastructure -Immediate maintenance needs of King Street must be addressed • Pedestrian First Objectives - no enhancement of the City's ability to foster a lively King Street; no improvements to barrier free accessibility; no improvements to existing lighting conditions. • Environmental Sustainability - no enhancement to environmental sustainability, with potential to add bike racks and enhanced transit shelters over time. • Number of Street Trees - 50 • Business Attraction, Retention & Development - no improvement to the City's ability to attract and retain investment into the Downtown Area. • On-Street Parking Spaces - 49 spaces Option 2 -Basic streetscape Renewal This option would result in a replacement of all surface elements of King Street between Frederick Street and Francis Street. Concrete finishes would be used extensively in-place of higher end materials like granite. New and upgraded street lighting with improved spacing would be incorporated throughout . Minimal use of street furniture (bike racks and benches). Standard curb and gutter with no flexible parking layout. The density of trees and planters would be similar to what is currently present. No coloured concrete or paving stones. • Extensive re-design would be required including new tendering package • Construction could start in 2009. Construction complete 2010 • Cost is within previously approved budget • Life Span of the Infrastructure -short term deficiencies would be addressed, concrete susceptible to become worn, stained and chipped. 4 • Pedestrian First Objectives - Ability to "program" street for various uses is limited. • Environmental Sustainability - no enhancement to environmental sustainability, with potential to add bike racks and enhanced transit shelters over time. • Number of Street Trees - 50 • Business Attraction, Retention & Development -limited improvement in the ability to attract and retain investment • On-Street Parking Spaces - 49 spaces Proposed Timeline (Option 2) Summer /Fall 2008: re-design Fall 2008: tendering Spring 2009: construction start Summer 2010: construction complete Project Costs (Option 2) Construction cost: $4.9 M Re-design: $0.1 M Contract Admin: 0.3 M Total $5.3 M Option 3 -Pedestrian First -Basic Renewal The approach proposed in this option is to reduce the overall quality of materials used with the goal of reducing the cost while maintaining the original scope of the project Frederick Street to Francis Street}. This option would result in a replacement of all surface elements of King Street. Concrete finishes would be used extensively in-place of higher end materials. New and upgraded street lighting with improved spacing would be incorporated throughout. No street furniture would be installed. The design would meet the objectives of the "pedestrian first" philosophy, incorporating flexible parking delineated by removable bollards. Coloured concrete and decorative pavers would be incorporated in sidewalks throughout the project. The density of trees and planters would be similar to what is currently present. • Re-design would be required including new tendering package • Construction could start in 2008. Complete in 2010. • Life Span of the Infrastructure -short term deficiencies would be addressed, concrete susceptible to become worn, stained and chipped. • Pedestrian First Objectives -street could be fully programmed with cafes, events, etc.; lack of trees would create micro-climate concerns; improved barrier free accessibility. • Environmental Sustainability -decreased environmental sustainability due to loss of street trees, with potential to add bike racks and enhanced transit shelters over time. • Number of Street Trees - 40 to 50 5 Business Attraction, Retention & Development -moderate improvement in the ability to attract and retain investment On-Street Parking Spaces - 71 flexible spaces Proposed Timeline (Option 3~ Summer: re-design Summer /Fall 2008: tendering Fall 2008: construction start Summer 2010: construction complete Project Costs (Option 3) Construction cost: $7.4 M Re-design: $0.1 M Contract Admin: 0.4 M Total $7.9 M Options 4 and 5 -granite pricing The following two options propose the use of granite in varying degrees. Granite is a natural material with a high variability in type, quality (aesthetic and structural}, origin, and consequently price. The intention is to procure the granite for these options through the general contractor. The benefit of this approach is that the City would not be responsible for issuing a separate tender, arranging storage, handling and delivery, coordination, and general supply scheduling. The City and the City's consultants have obtained estimated unit prices from multiple granite suppliers. Notwithstanding the pricing obtained by the City and its consultants, there is no guarantee that the prices given to the general contractor from these same suppliers will match prices quoted to staff and the City's consultants. This applies to all material in the contract, however due to the extent of this variability and the impact it could have on the total cost, the cost estimates provided for each of the following options are expressed as a range. It is staff's opinion that the low end of the range is more probable due to the competitive nature of the bidding process, however, it is believed that the most prudent approach is to advise Council of the price variability. Option 4 (Recommended)- Pedestrian First -Full Streetscape Renewal -Modified Limits The approach proposed in this option is to reduce the physical limits of the project, reducing the cost while maintaining the high-quality finishes in the Frederick Street to College Street block. The primary difference between Option 4 and Option 3 is that Option 4 utilizes higher quality materials but over a shover section of King Street. This option would result in the replacement of all surface elements of King Street between Frederick Street and College Street. Selectively reduced use of high quality materials such as granite in the roadway, sidewalks and crosswalks. New and upgraded street lighting with improved spacing would be incorporated throughout. The design would meet the objectives of the "pedestrian first" philosophy, incorporating flexible parking delineated by removable bollards. Sustainable design elements such as extensive tree planting and storm water infiltration planters would be utilized. The blocks between College Street and Francis Street would be upgraded with concrete finishes, improved lighting, tree plantings and street furniture to match the Frederick to College block. More high-end surface 6 treatments to be used at Francis Street to create a gateway effect into the City Centre District. The implementation of this option would encourage a higher level of fagade maintenance on private structures fronting the improvements. The construction tender would be structured for maximum flexibility to take advantage of any favourable pricing in the granite component. For example, the tender could be written to include upgraded treatments in the College to Francis block as an optional item, to be used only to the extent of the positive pricing on the granite or other items. • Re-design would be required including new tendering package • Construction could start in 2008. Complete fall 2009 • Life Span of the Infrastructure -short term deficiencies would be addressed; concrete susceptible to become worn, stained and chipped; granite pavers and curbs used between College and Frederick would have extended life span being more durable and readily cleaned and renewed. • Pedestrian First Objectives -the section from Frederic to College could be fully programmed with cafes, events, etc.; Civic Square would be designed as one coordinated space for major festivals; enhanced accent lighting at night; microclimate would be enhanced; improved barrier free accessibility. • Environmental Sustainability -storm water infiltration planters would be introduced between Frederick and College; new transit shelters would be installed between Frederick and Francis; some new bike racks and benches would be installed. • Number of Street Trees - 85-90 • Business Attraction, Retention & Development -substantial improvement in the ability to attract and retain investment • On-Street Parking Spaces - 65 spaces Proposed Timeline for (Option 4~ Summer re-design Summer/Fa112008: tendering Fall 2008: construction start Fall 2009: construction complete Project Costs (Option 4) Construction cost: $6.0 M - 7.4 M Re-design: $0.1 M Contract Admin: 0.4 M Total $6.5 M - 7.9 M Option 4 is being recommended because it combines the high-quality needs of the streetscape with the need to reduce project costs. It is believed that four high-quality blocks between Frederick Street and College Street will have a greater effect on attracting people and business to the downtown than six blocks of moderate quality streetscape (as proposed in option 3). By minimizing the amount of work in the College to Francis block, the City's options for future upgrades remain open while that block undergoes future redevelopment. There is also the 7 opportunity to return and upgrade the streetscape in the College to Francis block once redevelopment has been established. Option 5 -Pedestrian First -Full streetscape Renewal las currently desianed Replacement of all surface elements of King Street between Frederick Street and Francis Street. Extensive use of granite in the sidewalks, curbs and crosswalks. New and upgraded street lighting with improved spacing would be incorporated throughout. The design would meet the objectives of the "pedestrian first" philosophy, incorporating flexible parking delineated by removable bollards. The implementation of this option would encourage a high level of fagade maintenance on private structures fronting the improvements. • No change to current design and could tender project immediately • Construction could start in summer 2008. Completed by end of 2010. • Potential for very high fluctuations in costs due to late tendering period and thus exceeding the approved budget. • Would not jeopardize the provincial funding received for the project. • Life Span of the Infrastructure -High quality materials would have extended life span being more durable and readily cleaned and renewed. • Pedestrian First Objectives -street could be fully programmed with cafes, events, etc.; Civic Square would be designed as one coordinated space for major festivals; enhanced accent lighting at night; microclimate would be enhanced; improved barrier free accessibility. • Environmental Sustainability -storm water infiltration planters and new transit shelters would be introduced throughout; new bike racks and benches would be installed. • Number of Street Trees -106 • Business Attraction, Retention & Development -maximum improvement in the ability to attract and retain investment. • On-Street Parking Spaces - 71 spaces Proposed Timeline for (Option 5~ Summer 2008: tendering Fall 2008: construction start Fall 2010: construction complete Project Costs (Option 5) Construction cost: $9.7 M - 11.3 M Re-design: $ NIL Contract Admin: 0.4 M Total $10.1 M - 11.7 M 8 FINANCIAL IMPLICATIONS: The business case presented to Council on December 10, 2007 outlined the $5,680,000 of funding for King Street project. In March of 2008, the City received aone-time grant of $3,200,000 through the Provincial Municipal Infrastructure Investment Initiative (MIII}for this project. The grant was approved based on the design outlined in Option 5 of this report. Any significant departure from the work plan outlined in the grant application might jeopardize grant eligibility. Staff is of the opinion that the recommended plan is consistent with the original grant application. Applying the grant to the King Street project results in following funding scenario: Source of Funding EDIF $3,830,000 DTS Road Resurfacing $1,500,000 CSD Downtown Parkettes $ 350,000 M l l l g rant 3 200 000 Total Funding . $8,880,000 The costs presented in each of the options does not include the already approved work associated with the Public Art piece at Speaker's Corner or the Urban Vitality component. These costs were included in the original project budget of $5,680,000. Including these costs in the total cost for option 4 results in the following estimated costs for the King Street streetscape project (using only the high-end of the estimate range}: King Street streetscape Costs Total Cost of Option 4 (high-end} $7,900,000 Public Art at Speaker's Corner $ 130,000 Urban Vitality 100 000 Total Costs . $8,130,000 Projected Surplus = $ 750,000 The final surplus from the King Street project would be returned back to the original funding sources (EDIF, DTS Road Resurfacing or CSD Downtown Parkettes and/or capital surplus). COMMUNICATIONS: On direction to proceed from Council, staff will continue to communicate with downtown businesses and stakeholder organizations as required. Staff will work closely with downtown businesses to develop an appropriate staging plan for the construction work. Staff have discussed these options with members of the KDBA and DAC. CONCLUSION: Staff are recommending that Council provide direction to proceed with the King Street project as outlined in Option 4. This option includes the following: replacement of all surface elements of King Street between Frederick street and College Street. • selective use of high quality materials such as granite in the roadway, sidewalks and crosswalks (Frederick to College). 9 • upgraded lighting to meet the objectives of the King Street Master Plan (Frederick to Francis} • design would meet the objectives of the "pedestrian first" philosophy, incorporating flexible parking delineated by removable bollards (Frederick Street to College Street) • sustainable design elements such as extensive tree planting and storm water infiltration planters would be utilized (Frederick to College}. • Standard concrete finishes, improved lighting, new tree plantings and street furniture for the block between College Street and Francis Street Ito blend into the Frederick to College block) • High quality surface treatments and extensive street furnishings to be used at Francis Street to create a gateway effect into the City Centre District This option is being recommended for the following reasons: • Provides ahigh-quality streetscape between Frederick Street and College Street that is required to attract investment into the downtown • Balances the high-quality requirements for investment with a reduced scope to optimize spending • Establishes a benchmark for quality and durability that can be adopted for other sections of King Street and other downtown streets in the future • The design is closely aligned to what has already been approved by Council • Allows the opportunity to upgrade the block between College to Francis in the future, to the new standard when these blocks are redeveloped. K. Grant Murphy, P. Eng. Director of Engineering Services Development and Technical Services Department Rod Regier Executive Director, Economic Development 10 Appendix A -Comparison of KSMP Design Alternatives Chart 1: Comparison of the Design Elements in Each Option Element Option 1 Option 2 Option 3 Option 4 Option 5 Frederick to College to College & Francis The Francis Gateway Gateway (excluding the Gateway) 1. Approach Postpone Basic Pedestrian- Introducing apedestrian-first, Proceed as project streetscape first design, high quality design from designed, with indefinitely. renewal. using Frederick to College and at the a pedestrian- moderate Frederick and Francis Street first, high quality gateways. Maintain College to quality design design the Francis gateway but introduce throughout. elements. new lighting, new concrete sidewalks, planters and furnishings to match the rest of the street. 2. Sidewalk Retain All white A mix of A mix of All white A mix of Surfaces existing mix concrete. concrete granite paving concrete. granite paving of paving paving stones and stones and stones and stones and poured poured poured poured concrete. concrete. concrete. concrete. 3. Sidewalk Retain All white Concrete Granite paving Granite paving Granite Trim/Banding existing mix. concrete. paving stones in select stones at paving stones stones in locations. intersections to throughout. select match locations. remainder of street 4. Intersection Retain White White White White concrete. Granite Ramps existing mix. concrete. concrete. concrete. paving stones. S. Curbs Retain Standard Concrete; Granite; Standard Granite; existing concrete mountable mountable to concrete gutter/ mountable to concrete gutter/ barrier to allow for allow for barrier curb. allow for curbs. curb. flexible flexible flexible parking. parking. parking. 6. Crosswalks Retain Painted lines. Painted Mix of painted Painted lines. Granite. existing. lines. lines and granite (at Frederick and Francis gateways and King/Queen intersection) 7. Bollards None. None. Quantities Quantities None. All necessary scaled back scaled back to quantities to meet meet short purchased to short term term demands. meet long demands. term demands. 11 $. None. None. None. Selective use None. Selective use Illuminated, at Civic at Civic Solar Square; option Square; option Powered to retrofit at a to retrofit at a Bollards later date. later date. 9. Roadway None. None. Quantities Quantities None. 5-10 per Bollards at scaled back scaled back to intersection, Intersections to 4 per 4 per as designed. and intersection. intersection. Crosswalks 10. Lighting Same as New lighting, New New lighting, New lighting, New lighting, existing. with selective lighting, with selective with selective with upper use of upper with use of upper use of upper lighting lighting selective use lighting lighting column column. of upper column. column. throughout. lighting column. 11. Accent Existing x- Existing x- None. Selective use Selective use of Extensive use Tree and mas lights. mas lights. of tree up- tree up-lighting of tree up- Planterwall lighting and and planter lighting. Lighting planter wall wall down down lighting. lighting. 12. Use existing. Minimal use Minimal use Selective use Extensive use Extensive use Furnishings of new of new of new of new of new benches, bike benches, benches, bike benches, bike benches, bike racks, etc. bike racks, racks, etc. racks, etc. racks, etc. etc. 13. Street 50 50 40-50 85-90 106 Trees 14. Planters Use existing, Replace New New planters as New planters New planters red concrete existing red planters as designed, with as designed, as designed, planters; no concrete designed, granite finish and with granite with granite eco-friendly planters with but with eco-friendly finish; no finish and storm water white concrete storm water eco-friendly eco-friendly infiltration. concrete; no finish; no infiltration. storm water storm water eco-friendly eco-friendly infiltration. infiltration. storm water storm water infiltration. infiltration. 1S. Contin- None. None. None. Selective use, None. Used uous Tree but reduced in extensively. Trench with size where trees Irrigation have been eliminated. 16. Flower Use existing. Use existing. Use existing Minimal use of Selective use Selective use Pots green flower new flower pots; of new of new flower pots. option to add flower pots; pots; option to more at a later option to add add more at a date. more at a later date. later date. 12 17. Civic Same as Same as White White concrete n/a White Square existing. existing. concrete throughout, concrete throughout, selective use of throughout, selective use granite banding. extensive use of concrete of granite banding. banding. 18. Gateways None. None. Use of Use of banner n/a Use of banner banner columns, trees, columns, poles, trees, planting beds, trees, planting planting granite pavers, beds, granite beds, and granite pavers, concrete crosswalks and granite pavers at concrete crosswalks intersection. roadway. and concrete roadway. 19. Parking 49 perm-anent 49 permanent 71 flexible 44 flexible 71 flexible Spaces parking parking parking parking stalls; parking stalls; spaces; 3 spaces; 3 stalls; 7 17-21 permanent 7 parking / loading loading parking / parking stalls, 7 loading spaces. spaces. loading parking /loading spaces. spaces. spaces. 20. Speakers Proceed as Proceed as Proceed as Proceed as designed, with Proceed as Corner designed, with designed, with designed, potential reductions in the quality designed. potential potential with of surface materials. reductions in reductions in potential the quality of the quality of reductions surface surface in the materials. materials. quality of surface materials. 13 Chart 2: Evaluation of Each Option Evaluation Criteria Option 1 Option 2 Option 3 Option 4 Option 5 Meeting No enhancement No enhancement Street could be Street from Street could be Pedestrian of the City's of the City's fully pro- Frederick to fully pro- First ability to foster ability to foster grammed with College could be grammed with Objectives - and program a and program a cafes, events, fully pro- cafes, events, Fostering a lively street; no lively King etc.; lighting grammed with etc.; special Lively King improvements to Street; lighting conditions would cafes, events, event pads Street existing lighting conditions would be improved; etc.; special serviced with conditions. be improved. improved event pads electricity; mobility/ serviced with lighting cond- accessibility; electricity; no itions would be Civic Square enhancements dramatically would look and would be made improved function as one from College to through large public Francis; lighting extensive use of square; lack of conditions would ambient lighting; street trees would be improved; improved create micro- improved mobility/ climate concerns. mobility/ accessibility; accessibility; Civic Square Civic Square would look and would look and function as one function as one large public large public square; event square. pads would be serviced with electricity and hydro. Environmental No enhance- New transit New transit New transit New transit Sustainability meets made. shelters; some shelters; some shelters; some shelters; new - Fostering a new bike racks new bike racks new bike racks bike racks and Liveable King and benches; and benches; and benches; benches; storm Street moderate tree improved improved water planter plantings. walkablity; walkablity beds; some solar moderate tree (Frederick to powered plantings; College); storm bollards; up to S6 moderate use of water planter additional street recyclable and beds; some solar trees; improved reusable powered micro-climate; materials. bollards; up to 40 continuous tree additional street trench; extensive trees; improved use of recyclable micro-climate; and reusable continuous tree materials (eg. trench; granite). significant use of recyclable and reusable materials (eg. granite). 14 Fostering Kigh Would not meet Would not meet Would generally Would generally Would generally Quality Urban the intent of the the intent of the meet the intent of meet the intent of meet the intent of Design City's downtown City's downtown the City's the City's the City's urban design urban design downtown urban downtown urban downtown urban policies; would policies; would design policies design policies design policies lessen the City's not enhance the (increased (high quality (high quality ability to City's ability to flexibility for streetscape, streetscape, encourage high encourage high festivals and increased increased quality private quality private events, flexibility for flexibility for sector design. sector design. maximizing festivals and festivals and sidewalk space events, events, for cafes and maximizing maximizing outdoor sidewalk space sidewalk space retailing); for cafes and for cafes and would enhance outdoor outdoor the City's ability retailing); retailing); to encourage would greatly would high quality enhance the significantly private sector City's ability to enhance the design. encourage high City's ability to quality private encourage high sector design. quality private sector design. Business Would not Would somewhat Would enhance Would Would Attraction - enhance the enhance the the City's ability significantly significantly Fostering City's ability to City's ability to to attract new enhance the enhance the Vibrant attract new attract new restaurants, City's ability to City's ability to Shopping & restaurants, restaurants, retailers, etc. attract new attract new Dining retailers, etc. retailers, etc. restaurants, restaurants, retailers, etc. retailers, etc. Economic Would not Would enhance Would greatly Would greatly Would signif- Development enhance the the City's ability enhance the enhance the icantly enhance Strategy City's ability to to attract new City's ability to City's ability to the City's ability attract new developments or attract new attract new to attract new developments or employment; developments or developments or developments or employment; would not employment; employment; employment; would not enhance the would enhance would not would not enhance the City's ability to the City's ability enhance the enhance the City's ability to attract and retain to attract and City's ability to City's ability to attract and retain talent. retain talent. attract and retain attract and retain talent. talent. talent. 15 Durability of Immediate Concrete will Concrete pavers Granite pavers Granite pavers Surface maintenance deteriorate over will deteriorate will last indef- will last indef- Materials concerns would time regardless over time initely where initely where still need to be of installation regardless of installed and installed and addressed. and maintenance. installation and maintained maintained maintenance. appropriately; appropriately; ability exists to ability exists to sandblast the sandblast the granite to refresh granite to refresh the visual the visual appearance of the appearance of the street; applied street; applied sealants improve sealants improve ease of cleaning; ease of cleaning. concrete used between College and Francis will deteriorate over time regardless of installation and main- tenance; Night Lighting Current lighting Night lighting Night lighting Night lighting Night lighting & Ambience deficiencies and would be would be would be would be safety concerns enhanced, add- enhanced, add- enhanced, add- enhanced would not be ressing current ressing current ressing current significantly, addressed. deficiencies; deficiencies; deficiencies; addressing selective use of selective use of selective use of current light-columns light-columns light-columns deficiencies; would add would add would add light-columns ambient and ambient and ambient and would add facade lighting. facade lighting; facade lighting; ambient and illuminated illuminated facade lighting; bollards would bollards would illuminated add ambience to add ambience to bollards would Civic Square. Civic Square; add ambience to tree-lighting in Civic Square; planters and tree-lighting at select locations every planter and would add street tree would additional maximize ambient lighting. ambient lighting. 16 Alignment Not in alignment. Not in alignment. Functionality of Functionality of This option with Council's the design aligns the design and represents the Original with original quality of the originally Approval approval; quality materials from approved design. of the materials Frederick to does not align; College align loss of green with original elements does approval; section not align. from College to Francis would not align except at Francis gateway; option to construct full build-out in the future still possible, streetscape elements (eg. planters, lighting, etc) align with original approval. MIII Would not be Would not be Would be Would be Would be Provincial consistent with consistent with consistent with consistent with consistent with Funding the application. the application. parts of the the application. the application. Application application (such as providing a pedestrian-first design), but would not be consistent with a significant component of the application -the use of environ- mentally sustainable features. Estimated Cost Minimal ~ $5.3 million ~ $8.2 million ~ $7.9 million ~ $11.9 million 17 Chart 3: Evaluation Score of Each Option Evaluation Option 1 Option Z Option 3 Option 4 Option 5 Meeting Pedestrian First Objectives - Fostering a Lively King Street Environmental Sustainability F i t - ng a er os Liveable King Street Fostering Iligh Quality Urban Design Business Attraction - Fostering Vibrant Shopping & Dining Economic Development Strategy Durability of Surface Materials Night Lighting & Ambience Alignment with Council's i i l O r g na Approval MIII Provincial F ndin g u Application Estimated Cost Total Rating 4 / 40 9 / 40 19 / 40 30 / 40 37 140 Overall Lowest Low Medium High Highest Rating 18