HomeMy WebLinkAboutKPL - Central Library Project Update - February 1, 2006KITCHENER PUBLIC LIBRARY '~~ ,~ Report To: Chair Vrbanovic and Members of Finance and Corporate Services Date of Meeting: February 6, 2006 Submitted By: Kitchener Public Library Board Prepared By: Sonia Lewis, CEO Ward(s) Involved: All Date of Report: February 1, 2006 Subject: Kitchener Central Library Project Update RECOMMENDATION: For information only. EXECUTIVE SUMMARY OF PROJECT: THE NEED FOR A NEW CENTRAL LIBRARY: The need for a new library was first identified in 1999. KPL's current central library is 44 years old, and built to serve a population of 73,000. It no longer meets the needs of Kitchener's estimated 203,417 residents. The current central library is deficient in 11 of the 16 criteria established by provincial, national and international library associations. The following deficiencies have been identified with the current central library: ^ Inadequate space for services and programs. ^ Outdated and crowded areas for young adults and children. ^ Limited accessibility -does not meet the City's own standards (Joint Accessibility Plan). ^ Insufficient and inflexible technology infrastructure -not enough public Internet terminals. ^ Insufficient space for total collections. ^ Insufficient number and variety of meeting rooms for the public. ^ Inadequate parking at peak hours -number one complaint of customers. ^ Deteriorating mechanical systems in the building. The central library is the heart of the system, managing crucial administrative and planning functions. Kitchener's current system of branch libraries cannot be expanded without a stronger central librarv to subbort more branches. Page 1 Beckman Associates Library Consultants have concluded, "The current location and size of the Kitchener Public Library's Main Library is not adequate to accommodate the current usage levels and will not accommodate further expansion opportunities in order to serve projected growth". THE VISION FOR A NEW CENTRAL LIBRARY: A new central library located on Centre Block will be a true community gathering place, providing much needed public space in the downtown core while engaging in partnerships with the other local libraries, local school boards, the two new downtown university campuses, local museums, art galleries, and community centres. As a gathering place that attracts citizens from all walks of life and from all points of Waterloo Region, the new central library will be a beautiful, modern, dynamic facility that draws people and their disposable income into a vibrant downtown, seven days a week. Complementing Kitchener's flourishing education and knowledge creation cluster, a new central library on Centre Block will have a significant economic impact on the downtown, and is a key component to City Council's vision of re-energizing the core and making it 'a place for people.' In addition, a new main library will help establish the quality and character of the surrounding neighbourhood, serving as a standard for nearby property development. A new central library at Centre Block will improve and modernize public library services in the city. It will offer larger, more diverse collections and programs, increased resources for youth and multicultural groups, and friendly space for children and families. It will encourage children to develop a lifelong love of reading and learning. It will be fully accessible and conveniently located near public transit. It will offer new technology and other resources to help Kitchener's diverse population access opportunities and improve their skills to ensure Kitchener continues to take advantage of its unique position in the new economy. THE BENEFITS OF A NEW CENTRAL LIBRARY: A new central library in downtown Kitchener will have numerous short-term and long-term benefits, some of which are tangible and some of which are not: Economic Benefits of New Central Library: ^ $59.6 million annually =total recurring economic impact in the region by year five of the new library. ^ $28 million per year in indirect visitor impacts to the downtown (primarily increased retail spending). ^ $33.6 million added to the local economy (one-time -construction). ^ $24 million in wages and salaries (one-time -construction). ^ $18 million in revenue for the federal, provincial, regional and local government (one-time - construction). (Impact Analysis and Due Diligence Review of a New Main Branch Kitchener Public Library. Adventus Research. 2004.) Page 2 Community Benefits Of A Better Central Library: ^ Increase the number of visits to the central library by 60% in the first year alone to 800,000. Double the number of visits to the central library to 1 million by year five. ^ Give KPL the ability to support new branch libraries throughout the city. ^ Modernize and strengthen Kitchener's entire library system. ^ Offer a wider variety of collections and programs for Kitchener's growing and diverse population. ^ Address all of the deficiencies of the current central library. Benefits To Downtown Kitchener: ^ Attract residents from across Waterloo Region to the downtown seven days a week. ^ Provide an institutional and financial incentive to encourage private developers to invest in Centre Block. ^ Play a key role in City Council's vision to re-energize the downtown core. ^ Complement the two new downtown Kitchener university campuses in the development of an education and knowledge creation economic cluster -potential partnerships. ^ Provide public space in the downtown. THE COST OF A NEW CENTRAL LIBRARY: A new central library will require considerable public investment, a comprehensive fundraising plan and a strong partnership with a private sector developer. According to the 2004 business case, the preliminary cost estimate for the project was between $44-51 M. That preliminary cost estimate, which was based on the information available at that time did not contemplate an underground parking garage on the site. The most recent cost estimates for the project is $58.7 M (details of which are contained in this report). This latest estimate is based on an analysis by Hanscomb Limited, input received when the estimates were presented to the Centre Block Committee in December 2005 and further work done by KPL Board and staff to reduce the cost of the project. The accuracy of these estimates is in the range of plus or minus 10%. At the design and preconstruction phase of a project typically cost estimates are further refined and reflect a higher degree of accuracy. In May 2005, Kitchener City Council confirmed the municipal contribution of $32.5 million to the total cost of the new library. In addition, KPL's 2004 business case estimated $2.5 M could be raised from the proceeds of the sale of the existing central library building and property. Since that time KPL has been working on a fundraising plan, and on the advice of an independent consultant has set a target of $5 M. The City's approach to combining the need to build a new central library with its desire to redevelop the Centre Block property is specifically aimed at finding a private sector developer. By leveraging the municipal investment in the library, the City hopes to find a developer who will redevelop the entire block while helping to build the new central library. Page 3 Kitchener Central Library Project Update February 1, 2006 BACKGROUND: In September 2004, the Kitchener Public Library Board presented City Council with a business case documenting the need for a new central library. The business case outlined preliminary projected costs for the project of $44-51 M based on a level of detail available at that time. A significant portion of the cost estimate outlined in the business case was based on an expert report produced by Beckman Associates Library Consultants. At its May 30, 2005 meeting City Council passed a resolution which included "That the hiring of an architect or consulting team, be approved, to review and finalize the building program (functional design); develop a schematic design; participate in a public open house and prepare detailed project cost estimates for Kitchener Public Library's proposed new central library". Following direction by City Council, in July 2005 the contract for this work was awarded to Levitt Goodman Architects and Phillip Carter Architect and their cost consultant, Hanscomb Limited. Hanscomb Limited is one of Canada's leading cost consultants with over 44 years' history, including numerous library projects. At the December 2005 meeting of the KPL Board, the conceptual design options and associated cost estimates were approved. That information was presented to the Centre Block Project Committee in December and was widely reported in the media. The majority of the increase in the cost estimates between the 2004 business case and the revised estimates presented to the Centre Block Project Committee in December were the direct result of two factors: 1. The 2004 business case contained a cost of $450,000 for surface parking on Centre Block. It did not contemplate an underground parking garage. Upon further study of the parking needs on the Centre Block once a new library is built, it is now clear that there is a requirement and a public desire for an underground parking lot at a total cost of $6.3 M - which is $5.8 M in new dollars which were not contained in the 2004 business case. 2. The 2004 business case assumed that construction on the new library would begin in 2006. When Hanscomb prepared its more detailed cost estimates, it assumed that construction would not begin until 2008 and therefore, it added 15% inflation to the cost of the project. After presenting Hanscomb's cost estimates to the Centre Block Project Committee in December 2005, KPL Board and staff worked to reduce the budget where possible in order to make the total project as attractive as possible to a potential private sector partner. The latest total cost estimates for the project are outlined in Table 4 of this report. From August to December 2005 the Library worked with KCI (Ketchum Canada Inc.) on a fundraising feasibility study. Its purpose was to determine the receptivity to a fundraising campaign to support the construction of a new central library and identify a fundraising goal. This report summarizes the results of the fundraising feasibility study and provides City Council with an update on the latest cost estimates for the new central library project. Alternatives for funding the project are outlined in an accompanying Centre Block Project Committee report. Page 4 Kitchener Central Library Project Update February 1, 2006 REPORT: Fundraising Feasibilitv Studv Results From August -November 2005 KCI (Ketchum Canada Inc.) conducted a study to determine the feasibility of a capital campaign to raise funds for the central library project. A summary of key findings follows: • KPL has a positive image in the community and there is support in principle for the Library's need to raise funds. However, study participants felt it would be challenging for KPL to raise funds as it lacks a significant history of major gift fundraising. • A comprehensive marketing and communications strategy is needed to provide greater clarity on development plans for Centre Block, to raise awareness of the library's role in the community and to address questions about regional library cooperation. • A compelling case for support for the project needs to be crafted and communicated to prospective donors. A strategy for building relationships with prospects is required. • A volunteer recruitment program must be developed to attract volunteer leadership for a capital campaign. • The campaign preparations noted above require dedicated staffing resources fora 12 month period. Based on the successful implementation of these preparatory activities, KCI suggested KPL establish a preliminary campaign goal of $5M and reassess it in six months. Work is underway by KPL's Fundraising Committee on addressing the recommendations in the feasibility study. Cost Estimates In the fall of 2005 Levitt Goodman Architects and Phillip Carter Architect worked with cost consultant, Hanscomb Limited to produce an order of magnitude cost estimate for the new central library. By its very nature and based on further detailed information not available in 2004, this new cost estimate was more detailed than the preliminary estimate contained in the original business case. Order of magnitude costing is typically prepared during the conceptual phase of a project. It is an approximate estimate made during the formative stages of a project for the purpose of initial evaluation and is based primarily on the size of the structure and its proposed use. The accuracy of these estimates is in the range of plus or minus 10%. At the design and preconstruction phase of a project typically cost estimates are further refined and reflect a higher degree of accuracy. FINANCIAL IMPLICATIONS: Estimated Proiect Costs The latest cost estimates for the new central library are summarized in the tables below. The range of costs listed at the bottom of the two tables reflects the degree of accuracy of the Hanscomb estimates at this stage of the project. This is in the range of plus or minus 10%. Tables 1, 2 and 3 below provide Hanscomb's updated cost estimates for the library construction, site costs and parking. It compares them with the cost estimates included in KPL's Central Library Project Business Case, September 2004. Costs reflect the Kitchener Page 5 Kitchener Central Library Project Update February 1, 2006 construction market. In order to help Council accurately draw comparisons between the preliminary cost estimates contained in the business case which assumed a construction start of 2006, these tables reflect current costs. For planning purposes Hanscomb recommended we assume construction costs will escalate by approximately 5% per annum. Energy efficiency measures and calculations for contingencies account for the major differences between the Hanscomb and business case estimates. The Hanscomb costs in Table 1 below include energy efficiency and green design measures consistent with Leadership in Energy and Environmental Design (LEED) and the Commercial Building Incentive Program (CBIP). These measures were not included in the business case costs. The benefit of CBIP is reduced energy costs for the life of the building. Achievement of any LEED level results in significantly reduced environmental impact, improved indoor environment and lower building maintenance costs. The investment in these measures will be offset in operating cost savings of approximately $82,000 per year. For the costs outlined in Table 1 Hanscomb assumed a 10% design contingency; whereas 8% was used in KPL's 2004 business case. Costs per square foot are $223 in the Hanscomb estimates. This is in line with projections prepared by Beckman Associates for the 2004 business case which assumed $225 per square foot. Table 1 Estimated Library Construction Costs 2006 KPL Business Library Construction Costs Case Hanscomb (Beckman) Building Construction $28,997,400 $29,000,000 Leadership in Energy and Environmental Design (LEED) Allowance $700,000 excluded Commercial Building Incentive Program (CBIP) Rebate ($60,000) excluded Design Contingency $2,899,700 $2,300,000 Construction Contingency $1,594,900 $1,400,000 Total Librar Construction Costs $34,132,000 $32,700,000 Possible Range Low -10% $30,718,800 High +10% $37,545,200 Table 2 outlines estimated site costs. The Hanscomb landscaping cost projections did not take into account development of the entire Centre Block site and therefore do not reflect savings that will be achieved through economies of scale. When landscaping is planned for the larger site and is based on a specific design, cost reductions are anticipated in this area. Page 6 Kitchener Central Library Project Update February 1, 2006 Contingencies were excluded from the 2004 business case but were included in Hanscomb's estimates. Table 2 Estimated Site Costs 2006 KPL Business Case Site Costs Hanscomb (Beckman) Landscaping Allowance $1,250,000 $300,000 Site Preparation and Servicing Allowance $250,000 $200,000 Site Design Contingency $150,000 Site Construction Contingency $82,500 Total Site Construction Costs $1,732,500 $500,000 Possible Range Low -10% $1,559,300 High +10% $1,905,800 Parking costs are outlined in Table 3. Costs in the 2004 business case were for surface parking with 150 spaces. It was assumed additional parking needs (280 spaces) would be met by adjacent or nearby parking lots. Surface parking on Centre Block is no longer an option available to KPL. City and Centre Block Project Committee directions, as well as public input at the design charette have dictated a need for underground parking, resulting in a significant increase in library parking costs. For the latest estimates parking needs were reassessed based on a library parking survey conducted in January 2006 at the request of City staff. Parking needs have been increased to 180 spaces to address daytime parking requirements of library customers. Parking needs are higher during the library's peak evening hours; however, we assume those additional parking requirements will be met by adjacent parking lots. It is anticipated that 50-60 KPL staff will require parking in the downtown when the central library moves to Centre Block. These parking requirements are not accommodated in the 180 spaces noted above. This would be income generating as we assume staff would pay for their parking, as they now do. Centre Block has been identified as a possible location for additional downtown public parking. Combining this public parking with Library parking would result in lower construction costs and operating efficiencies. Underground parking frees up surface areas on the site for additional development and creation of tax generating buildings. Contingencies are included in the Hanscomb parking estimates but were excluded from the 2004 business case. Page 7 Kitchener Central Library Project Update February 1, 2006 Table 3 Estimated Parking Construction Costs 2006 KPL Business Case Parking Costs Hanscomb (Beckman) Underground Parking - 180 spaces $5,431,700 Design Contingency $543,200 Construction Contingency $298,700 Surface Parking n/a $450,000 Total Parkin Costs $6,273,600 $450,000 Possible Range Low -10% $5,646,200 High +10% $6,901,000 Table 4 provides estimates for projected construction costs and other capital costs associated with the new central library. This includes costs for professional fees, project management fees, public art, furnishings, equipment, technology, moving and library collections and resources to meet recognized library standards. Notes at the bottom of Table 4 draw comparisons between the latest estimates and those included in the business case. As noted above, we anticipate cost projections for site costs and parking may be reduced when handled as part of the overall Centre Block development. Page 8 Kitchener Central Library Project Update February 1, 2006 Table 4 Estimated Total Project Costs 2006 Estimated Cost Library Construction and Contingency Costs $34,132,000 Professional and Design Fees $2,901,200 Project Manager $682,600 Public Art $300,000 Furnishings/Equipment/Technology $10,000,000 Moving Costs $300,000 * Library Collection Growth $2,400,000 SUBTOTAL $50,715,800 Site Costs $1,732,500 Parking Costs $6,273,600 TOTAL Estimated Pro'ect Cost $58,721,900 Possible Range Low -10% $52,849,700 High +10% $64,594,100 * Library Collection Growth: as per 2004 business case. Costs can be spread over 3 - 4 years with a first year cost of $600,000. Library Construction: as per Hanscomb; Hanscomb design contingency 2% higher than that of 2004 business case Professional and Design Fees: 8.5 % of library construction costs as per 2004 business case Project Manager: 2% of library construction costs as per 2004 business case Public Art: as per City of Kitchener 1 % Public Art Policy and 2004 business case Furnishings/Equipment/Technology: as per 2004 business case Moving: as per 2004 business case Site and Parking: as per Hanscomb including contingencies excluded in business case COMMUNICATIONS: As part of the development of this project, the Library conducted extensive public consultations including public open houses, focus groups, community surveys, and stakeholder sessions to solicit feedback from the community on the proposed new central library. Some of this work was undertaken by the Southern Ontario Library Service (SOLS), an agency of the Ontario Ministry of Culture. As a result of those public consultations, SOLS concluded, "the Library Board and City Council have clear confirmation from the public that there is a need for a new main library." Page 9 Kitchener Central Library Project Update February 1, 2006 During the latest phase of the project, the public had the following opportunities to learn more and provide feedback: • September 21, 2005 -Architect's preliminary report to the KPL Board. • September 25, 2005 -Central Library open forum at Word on the Street • October 13, 2005 -Public open house and architect presentation • October 2005 -Conceptual designs available on KPL website • November 16, 2005 -Architect's final report and fundraising consultant's report to the KPL Board • December 14, 2005 -Presentation of cost estimates to KPL Board Sixty-three members of the public attended one of the community consultation sessions, five people submitted written comments via the website, and there were 2,725 visits (January - December 2005) to the new central library project information page on KPL's website. In the City's recent Environics survey, 86% of Kitchener residents indicated they are either very satisfied or somewhat satisfied with public library service. 87% indicated they think the City of Kitchener should be spending about the same or more money on public library services. Only 5% of respondents indicated the City should be spending less. Previous public surveys have shown that 82% of Kitchener residents rate the library as one of their most valued City services. CONCLUSION: After months of detailed research and several opportunities for public input, the proposal to build a new central library on Centre Block and the accompanying detailed cost estimates which currently stand at $58.7 M (including $6.3 M for an underground parking garage).are ready to be included in an RFP for the redevelopment of the Centre Block. This is a very significant step towards completion of the project. A strategy for addressing the project costs is being developed in consultation with City staff and the Centre Block Project Committee. Further details on that strategy are addressed in an accompanying Centre Block Committee report. The KPL Board and staff remain committed to achieving the goal of a new central library through the construction of a welcoming and functional facility on the Centre Block site. Respectfully submitted by, Sonia Lewis, CEO Kitchener Public Library Page 10