HomeMy WebLinkAboutDTS-08-201 - King St Streetscape - Design PO Extension~ ~, ~
T~ E
Development &
Technical Services
Report To: Mayor and Members of Council
Date of Meeting: December 8, 2008
Submitted By: Grant Murphy, P.Eng. Director of Engineering Services
Prepared By: Steve Allen, P. Eng., Manager, Enginering Design and
Approvals
Ward(s~ Involved: Ward 1 & 6
Date of Report: December 3, 2008
Report No.: DTS 08-201
Subject: KING STREET & THE CITY CENTRE DISTRICT:
STREETSCAPE MASTER PLAN -DESIGN PO EXTENSION
RECOMMENDATION:
That Council approve the extension of the purchase order for IBI Group to a maximum
amount of $100,000 (excl. GST~ for additional services provided during the design
phases of the King Street and City Centre District Streetscape Master Plan with actual
fees to be negotiated between the City and IBI Group.
BACKGROUND
In early 2007 the King Street and City Centre District Streetscape Master Plan and
Environmental Assessment SEA} project was awarded to IBI Group. At the time of award, IBI
provided the City with a fee estimate that was based on the scope of services described in the
Terms of Reference for the project. At the time IBI Group submitted their fee estimate the
anticipated project budget was assumed to be approximately $3.3M, based on public
information available. Over the course of the project in 2007 and early 2008, as the
requirements of the various stakeholders in the project were developed, the complexity of the
project increased and accordingly, the overall cost of the project increased. In June of 2008,
Council approved a revised project budget of $8.8M.
In May of 2008, IBI submitted to the City a request for consideration for payment related to
delivered services that they considered to be outside of their original scope of services, or
services that could not have been reasonably identified at the time the original fee estimate was
provided.
Staff have reviewed the request and have had meetings with IBI to discuss the request. Staff
have identified some services provided by IBI that are either outside the original Terms of
Reference or required more effort than could have reasonably been anticipated at the time the
fees were submitted, and are recommending that IBI be compensated accordingly. The amount
of the fee increase can be accommodated in the existing King Street budget.
REPORT:
In March of 2007 the King Street and City Centre District Streetscape Master Plan and
Environmental Assessment (EA) project was awarded to IBI Group. Generally speaking, the
scope of services at the time of the project award was to lead the City through the EA process
for the streetscape masterplans of King Street and City Centre district, prepare detailed designs
for King Street, and to prepare the tendering package for the construction of King Street. At the
time of the award of the project it was anticipated by City staff that the total project budget would
be approximately $3.3M.
A Terms of Reference was written to be used during the consultant selection phase of the
project which is meant to define the consultant's scope of work. The Terms of Reference
identified primary and secondary objectives of the King Street /City Centre plan to be used as
guiding principles. These objectives included high level characterizations of how King Street
would look and function. For example, the Terms of Reference required the streetscape to be
"lively" and "liveable" and provided examples of streetscape elements that would help achieve
this objective. The intent of this approach was to provide a general framework for the study
while leaving the specific details and requirements to be determined through the EA process
and consultation with stakeholders.
Throughout the first half of 2007 City staff and IBI Group continued to work on completing the
masterplan and preliminary design using the guiding principles and objectives of the project.
Based on the public's feedback and detailed review by the Steering Committee, the Pedestrian
First model was the preferred option. The Pedestrian First model involves narrowing King Street
in the City Centre District to widen sidewalks and improve accessibility, including upgrades to
both the design and surface treatment of major and minor intersections. The area directly in
front of City Hall is designed as a special civic area that can be easily closed and used for
special events. Parking spaces will be converted and relocated to give way to a vehicular drop
off and loading zone. A rolled curb will be introduced for King Street from Frederick to Victoria
to improve pedestrian movement and improve accessibility.
With the Pedestrian First model established as the preferred direction, the consultant's work
focused on the details of design consistent with this direction. Over the remainder of 2007 and
early 2008 City staff and IBI Group continued to complete the detailed design. During this
phase of the project many innovative design elements were proposed, evaluated and
incorporated into the project. As an example, to meet some of the "green" objectives of the
project an innovative storm water planter was developed. The planter is designed to accept
street runoff during the summer to augment or eliminate the need for routine watering of street
trees and plantings. The stormwater planter meets the primary objective of the green
requirement outlined in the "liveable" objective as described in the original Terms of Reference,
but was not specifically identified at that time. Other complex design elements included the
flexible street design, the incorporation of traffic bollards, the accommodating of special event
needs (electricity and water} at various locations, the complete redesign of Speakers' Corner,
pedestrian scale lighting and detailed paving patterns using premium materials like granite and
specialized concrete pavers. Many of these design elements were new to the design team
including the consultant and have not been used in other City projects. As a result, the amount
of effort expended researching, evaluating, and designing for these elements was greater than
what would be expected for typical streetscape projects the City has completed in the past.
As a result of the increasing complexity of the project, the consultant was directed to complete
various tasks which were either extra to the scope of services listed in the City's Terms of
Reference, or to an extent beyond what could be reasonably anticipated at the time the fees
were first submitted. A number of these additions to the scope were identified at the time of
completion of the work, while others were identified towards the end of the design phase in
spring of 2008. In May of 2008, the IBI Group Ltd. presented City staff with a request for
additional payment for services they believed to be outside the scope of the original Terms of
Reference. City staff have reviewed the request in detail and in conjunction with meetings with
the consultant, have determined that IBI should be compensated for services outside of the
original fee structure. The fee increase request can be accommodated in the approved King
Street budget.
FINANCIAL IMPLICATIONS:
Total Project Funding
E D I F $3, 830, 000
Roads Program $1,500,000
CSD Parkettes $ 350,000
Provincial Grant $3,200,000
Total Council Approved Funding $8,880,000
Urban Design $ 150,000
Cost Recovery Utilities, hydro, Telecoms} $ 601,157
Total Funding $9,631,157
Incurred and Anticipated costs
Engineering, Design and Consulting $1,486,631
Construction Contract * $7,235,396
Lighting and Traffic pole procurement $ 679,130
Art and Urban Vitality $ 230,000
Total Projected Costs $9,631,157
Balance $ 0
CONCLUSION:
Staff has reviewed the request from IBI Group and is recommending that IBI be compensated
for services outside of the original scope. The fee increase can be accommodated in the
proposed budget for King Street.
K. Grant Murphy, P.Eng.
Director of Engineering Services
Steve Allen, P.Eng.
Manager Engineering Design and
Approvals